CVE 4070 Construction Engineering Quality Control Value Engineering

Slides:



Advertisements
Similar presentations
THE HELP PROCESS. Professional medical equipment project management is the systematic, knowledgeable process through which all items of capital equipment.
Advertisements

Presented by: Fouad Al-Malazi ID No.: Managing Construction Contracts By Robert D. Gilbreath Chapter 1 CONSTRUCTION CONTRACTS: Roles and Relationships.
Ensure Vendor/Engineer of Choice Product Quality
Innovative Contracting Techniques that Consider Driver Impacts Use of A+B Bidding Presented by: David L. Kent P.E. New York State Department of Transportation.
CON 4003 CVE 4073/5073 The Estimating Process Prof. Ralph V. Locurcio, PE.
Construction Cost Estimating Class #2: Bidding Process Prof. Ralph V. Locurcio, PE.
CONSTRUCTION ADMINISTRATION Preconstruction Operations Dr. Alaattin Kanoğlu Spring, 2013 Professional Practice Management I.B.U. Architecture Undergraduate.
Requirements Engineering n Elicit requirements from customer  Information and control needs, product function and behavior, overall product performance,
SAE AS9100 Quality Systems - Aerospace Model for Quality Assurance
QUALITY MANAGEMENT DEFINITIONS AND CONCEPTS QUALITY MANAGEMENT TOOLS QA / QC PROCESS COMPUTERS AND PROJECT QUALITY.
Activities CTC-415. Activity Consumes Time Usually consumes resources (cure time for concrete) Definable start and finish Assignable – V. important –
THE PROJECT TEAM TYPICAL REQUIREMENTS AND RESPONSIBILITIES OF THE PROJECT TEAM TRADITIONAL TEAM ORGANIZATION AND VARIATIONS THE OWNER’S TEAM THE DESIGN.
PROCEDURES FOR SELECTING THE CONTRACTOR
Purpose of the Standards
Types of Drawings University of Palestine Eng. Nagham Ali Hasan
XII- COST CONTROL, MONITORING & ACCOUNTING
Auditing Standards IFTA\IRP Audit Guidance Government Auditing Standards (GAO) Generally Accepted Auditing Standards (GAAS) International Standards on.
CVE 1000 Construction Engineering The Project Delivery System Prof. Ralph V. Locurcio, PE.
Internal Auditing and Outsourcing
Chapter 4: Beginning the Analysis: Investigating System Requirements
Standards of Practice Course
Commissioning of Fire Protection and Life Safety Systems Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA.
1 BROOKHAVEN SCIENCE ASSOCIATES LOB - Ring Building Construction Coordination Michael P. Bromfield Construction Engineer NSLS-II Conventional Facilities.
Requirements Analysis
Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE.
From Research Prototype to Production
Software Inspection A basic tool for defect removal A basic tool for defect removal Urgent need for QA and removal can be supported by inspection Urgent.
Lecture #9 Project Quality Management Quality Processes- Quality Assurance and Quality Control Ghazala Amin.
I n t e g r i t y - S e r v i c e - E x c e l l e n c e Pacific Air Forces 1 Preconstruction Orientation HQ PACAF/LGC.
© 2006 Cisco Systems, Inc. All rights reserved.Cisco Public 1 Version 4.0 Gathering Network Requirements Designing and Supporting Computer Networks – Chapter.
CVE 4070 Construction Engineering Test-2 & Review Prof. Ralph V. Locurcio, PE.
Construction Cost Estimating Class #2: The Estimating Process Prof. Ralph V. Locurcio, PE.
CVE 4070 Construction Engineering Shop Drawings Quality Control
CON 2001-CVE 4070 Construction Engineering Project Organization & Stakeholders Prof. Ralph V. Locurcio, PE.
CVE 4070 Construction Engineering Value Engineering Prof. Ralph V. Locurcio, PE.
CON 4003 CVE 4073/5073 Construction Cost Estimating Class #2: The Estimating Process Prof. Ralph V. Locurcio, PE.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
Systems Analysis and Design in a Changing World, Thursday, Feb 1.
Project quality management. Introduction Project quality management includes the process required to ensure that the project satisfies the needs for which.
11/24/20151 CVE 5074 Leading Construction Operations Team Leadership Part VII – Ethics & Quality.
Prof Ralph V. Locurcio, PE CON 2001 CVE Sequence Single Family House - 3,000 square feet Duration 1 General Conditions 21 2 Apply for Permits.
CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE.
CVE 4070 Construction Engineering Risk Management Prof. Ralph V. Locurcio, PE.
CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.
CON 2001 & CVE 4070 Construction Engineering Risk Management Prof. Ralph V. Locurcio, PE.
Contract Specifications Written Set of standards and procedures informing the contractors or remediation professionals of materials & operation necessary.
CVE 4070 Construction Engineering Project Closeout & Pyramid Solution
CVE 4070 Construction Engineering Course Review Prof. Ralph V. Locurcio, PE.
CON 2001/CVE 4070 Construction Engineering Construction Estimating
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
What is “Constructability”?
1 Chapter 11 Planning. 2 Project Planning “establishing a predetermined course of action within a forecasted environment” “establishing a predetermined.
CVE 4070 Construction Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE.
Advanced Project Management Project Quality Management Ghazala Amin.
CVE 4070 Construction Engineering HW #6 review Test-2 & Review Prof. Ralph V. Locurcio, PE.
Managing Quality with Quality Through the Construction Management Leadership Manual Presented by: Aleksandr Sergek, PE, PMP Allison Justiniano, LEED AP.
Constructing Recreation Facilities 8 chapter. Groundbreaking Before the construction begins, a groundbreaking ceremony is often held in recognition of.
Leadership for Project and Program Success How professional Construction Management saves time, saves money and delivers quality projects.
Accounting systems design & evaluation 9434SB 18 March 2002.
QUALITY ASSURANCE MODULE 3. Definitions Quality Assurance - A process/effort that ensures that processes are followed, that the processes of doing right.
4 Chapter 4: Beginning the Analysis: Investigating System Requirements Systems Analysis and Design in a Changing World, 3 rd Edition.
The Design Team Carl James.
Estimating Project Costs
(Additional materials)
FIVE PROJECT PHASES 5C-3 Sun. 8:00-10:00am 21/ 2/2016.
Designers’ Manual Overview and Chapter Contents
Construction Engineering Change Order - 2 Prof. Ralph V. Locurcio, PE
Construction Engineering Change Order - 2 Prof. Ralph V. Locurcio, PE
DOD’S PHASED SYSTEM DEVELOPMENT PROCESS
TOTAL COST CONTROL ON CONSTRUCTION PROJECTS
Presentation transcript:

CVE 4070 Construction Engineering Quality Control Value Engineering Prof. Ralph V. Locurcio, PE

Quality Control

Savings from quality

Quality control tools…

Pareto analysis…

Control chart analysis…

Preconstruction Conference… Conducted by owner’s representative Owner & user may attend Sets tone for the project General agenda items: Review contract docs, award & notice to proceed info Responsibilities of all parties Review schedule & payment; contingencies; damages Quality Control Plan & inspection procedure Submittals: shop drawings, samples, record drawings Changes, mods & claims procedures Site safety & operational considerations Labor & union procedures: EEO, Davis-Bacon wages Emergency procedures & work stoppage Project Closeout & Beneficial Occupancy

Quality Control & Assurance… Quality control vs. quality assurance Required on government contracts Inspection & Testing manual Policy matters that govern acceptance Inspection procedures Technical checklists List of testing for materials & equipment Work flow diagrams

Quality Control Process… Must have a Quality Control Plan or Manual An inspection" system” Special considerations: Timing of inspections; preclude delays Protection of work in place Most work is irreversible; i.e.. concrete, foundations Logistical sequencing Follow plans & specifications; changes not authorized Report and correct errors & deviations from spec; documents Three phased inspections… before each task Preparatory inspection Pre-inspection Final inspection QC Staff must be qualified, trained & dedicated

Inspection & Testing Manual… Detailed inspection procedures: Preparatory inspection: work flow, submittals, methods Initial inspection: workmanship & components Follow-up: results of work, tests, appearance Acceptance/rejection criteria… per specs Testing required & frequency… specs & sched Responsibilities for testing… specific names Outside labs & testing agencies… list or schedule Timing of inspections & work… WBS & sched Reports required, frequency & format… contract Documentation of test results… contract

Value Engineering

What is VE… really? VE is a “systematic” analysis of a project design to obtain the most value for every dollar of cost… The elimination of any part of the project that adds to cost without adding to functionality… Not only design & construction, but life cycle costs as well…

A second look at the design… Major cost items Materials cost & availability Construction methods Shipping costs Organizing & project admin But…

Most productive when… Contractor is involved Advantage of contractor’s expertise in purchasing, construction methods, organizing, techniques and quality control… Generally requires an incentive clause in the contract…

But there’s are risks… VE analyst may not fully understand the design basis… VE generates changes that could delay project completion… VE may not recognize field conditions that might outweigh cost savings… VE could result in lower quality components…

Role of the owner’s representative... Advocate for the owner & the project… Control the risks… Retain the overall value of the project

VE in the design phase… VE considers costs related to: Materials Labor Equipment Overhead & supervision

Costs related to materials… Transportation or shipping Testing cycles Complex inspections Tolerances Fabrication process

Costs related to labor… Quality of workmanship needed Excavation Forming or finishing Fitting Availability materials that reduce labor Construction timing

Costs related to equipment… Allow use of high production equipment Reduce need for special equipment Minimize haul distances Not force use of special equipment

Costs related to overhead… Special security requirements Limited site access or laydown areas Complex supervision or inspection

Cost saving design features… Duplicate members Use modular components Simplified structural components Eliminate special forming or finishing Siting to reduce excavation Specify local materials Use simple, clear or standard specs Use prebid conferences

VE in construction phase… Study physical features such as topography, geology, climate… Construction phasing to minimize use of high cost equipment or labor Modify construction methods to reduce forming or finishing Increase use of new or high production equipment Substitute materials or components that reduce cost

The VE process… Information or study Brainstorming Analysis Development of alternatives Presentation Follow-up

Brainstorming techniques Set time limits Record all ideas; quantity vs. quality Avoid judgment, detail or analysis Neutral controller Light free flowing atmosphere Non-competitive; all contribute Review and categorize at end

Presentation Describe the process & alternatives Pros & cons of alternatives Compare costs of original & VE Compare quality & functionality Present an implementation plan Show cost savings to owner

Contractor incentives… Generally 45% of any real savings Must share with sub-contractors Important to include in contract VE suggestions are proprietary

Role of the owner’s rep Be the advocate for the owner & the project… Control the risks… Keep the overall value of the project in perspective…

Cost Estimate HW

Cost Estimate-1

What are the elements?

What are the elements? Foundation – units? Floor slab – units? Floor covering - vinyl Exterior walls – vinyl siding Interior walls – wallboard Insulation – exterior walls Ceiling - wallboard Roof – slope is 4/12

Cost Estimate-2

Cost Estimate-3

Cost Estimate-4

Cost Estimate-5 r = 16 + 144 r = 160 r = 12.649 Roof Calculations… Roof slope given as 4 on 12 slope…. So… how much larger is the sloped roof than the flat roof? Roof slope factor = 12.649/12.000 = 1.054 So the sloped roof will be 1.054 x area of the flat roof r 4 12 r2 = 42 + 122 r = 16 + 144 r = 160 r = 12.649

HW #6 Due on Thursday Bring your solution to class We will correct your HW in class Also, study guide for Test 2 Test 2 is next week on Oct 27th

Questions?

Case Study A chemical facility was to be redesigned. A key requirement was that the new design should operate at a higher efficiency than the existing facility. The plant operator had completed conceptual engineering and simulation to finalize the process flow scheme. There was considerable skepticism that value engineering might improve the design. However, the client was open-minded and the engineering team persuasive and it was agreed that the exercise would proceed. The value engineering facilitator prepared functional flow diagrams. A representative of the operator and several contractor engineers from different disciplines met for 2 sessions, each of which lasted for 4 hours. During these well-planned and carefully facilitated sessions, 12 ideas were generated, of which 6 were deemed practical. The most significant idea that emerged from these focused brainstorming sessions was to change a column configuration from parallel to series, thereby saving significant condenser costs and improving the energy efficiency tremendously. The idea was refined and implemented. Overall, the capital cost saving was about $1 million (5% of total capital), with an operating cost saving of about $4 million/year.

Ethics Paper due Nov 27 NSPE Rules of Professional Conduct Read all of the rules Summarize each of the obligations in one paragraph Pick a case study: 1,7,58,58,60 Write a 2-page paper applying the NSPE rules to the situation in the case What errors were made How should the engineer behave in the case