Improved Project Control Through CPM Scheduling What Owners, PM’s and CM’s Need to Know t H E T I B U R O N T I B U R O N G R O U P, L L C G R O U P, L.

Slides:



Advertisements
Similar presentations
Construction Delays & CPM Schedules
Advertisements

Chapter 6 Practical Methods to Reveal CPM Covert Activities
Administering Lump Sum P/T Contracts via a Cost Loaded Schedule
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 4 Standard CPM Smoke and Mirror Tricks (Manipulations)
DISTRICT FIVE CONSTRUCTION CONTRACT ADMINISTRATION UPDATE TRAINING Submission of Working Schedule Specification SP A.
CP Chapter 4 Schedule Planning.
Project Management from Simple to Complex
TIME MANAGEMENT 641 Topic 03 Activity Sequencing.
PRJ566 Project Planning and Management Lecture: Dependencies and Network Diagrams.
Work Breakdown Structures
©2012 Construction Science, LLC 1 Primavera P6 Settings Presented by Karen Reynolds, Partner Construction Science, LLC.
Having Fun with Gantt PERT &.
Defining activities – Activity list containing activity name, identifier, attributes, and brief description Sequencing activities – determining the dependencies.
Microsoft Project.
Project Time Management
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
CE 405 – SCHEDULING CRITICAL PATH In order to be an effective Scheduler/ Project Manager – and realizing that you will have too many things demanding your.
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 2 Key CPM Scheduling Terms.
AMERICAN SPORTS BUILDERS ASSOCIATION CRITICAL PATH METHOD SCHEDULING FOR SUCCESS December 6-8, 2008 New Orleans, Louisiana Presented By: Bill Pronevitch.
Project Time Management
Importance of Project Schedules
Reviewing & Analyzing Schedule
1 ®  Overview Benefits of a Good Construction Schedule Baseline Schedule Development Schedule Updating and Maintenance Managing Project Changes USACE.
Scheduling CTC-415. Activity Network Development Network Models Activity on Node Precedence Diagram Method Activity on Arrow Network Characteristics Discrete.
LSU 10/09/2007Project Schedule1 The Project Schedule Project Management Unit #4.
Copyright © Software Process Group 1 Software Process Group Microsoft Project Tutorial Steve Meyers
USING MS PROJECT 2010 Project management software programs such as Microsoft Project 2010 can be used for developing the project schedule and budget, and.
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 3 Requirements of a realistic CPM schedule.
Microsoft Project – Tutorial 2 Project Goal network company computers to easily share resources within a time frame of three months and within a budget.
HIT241 - TIME MANAGEMENT Introduction
Amin Salari, CCM, PMP, LEED AP – Lundgren Management
McDONOUGH BOLYARD PECK CONSTRUCTION ENGINEERING SUCCESSFUL STRATEGIES FOR SCHEDULING PROJECTS TO FINISH ON TIME Presented by Christopher J. Payne, PE,
Scheduling Sequence & Time.
Hartley, Project Management: Integrating Strategy, Operations and Change, 3e Tilde Publishing Chapter 5 Time Management Developing and controlling the.
POST GRADUATE PROGRAM OF INFORMATION TECHNOLOGY
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 5 Advanced Techniques of CPM Deception and Mystery.
EGNR 300 Project Management Planning & Scheduling ENGR 300 Dept. of Computer Science and Engineering University of Bridgeport,
~ pertemuan 6 ~ Oleh: Ir. Abdul Hayat, MTI 03-Apr-2009 [Abdul Hayat, Project Time Management, Semester Genap 2008/2009] 1 PROJECT TIME MANAGEMENT.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
Planning and Scheduling. Project Planning –Selecting Construction Methods and sequence of work –Must complete planning before doing scheduling –Steps.
Quick Recap.
© Construction Management Association of America. Do Not Duplicate or Reproduce. Standards of Practice Course CPM Scheduling Lab.
T.L. Martin & Associates Copyright © 2008 Chapter 1 Fundamentals of Scheduling T.L. Martin & Associates, Inc Office Park Drive Gaithersburg, Maryland.
Microsoft ® Office Project 2007 Training Linking Project tasks [Your company name] presents:
Microsoft Project – Tutorial 4 Leveling Overallocations In some cases, a resource could be assigned more work in a given time period than it has working.
Copyright © 2003 Primavera Systems, Inc Primavera User Conference Schedule Bingo presented by Mike Stone w/Professional Project Management Services.
CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)
Project Time Management
Scheduling. Putting the activities in chronological order –Chicken or the egg Allows the PM to determine the time required to complete a project.
Lessons Learned – Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International Charlie Jackson, PSP,
Hannah Schumacher, PSP, LEED AP, PMI-SP Hill International Charlie Jackson, PSP, Primavera Certified Trainer Project Life Span, LLC Construction CPM Conference.
CLAIMS MANAGEMENT. PRESENTATION OUTLINE INTRODUCTION TYPICAL CLAIMS AGAINST OWNER TYPICAL CLAIMS AGAINST CONTRACTOR CRITICAL PATH METHODS UTILIZATION.
Scheduling CTC-370. Value Engineering Provides alternatives to the proposed design –Save Owner $$ –Must be as good or better than original design –Must.
SOFTWARE PROJECT MANAGEMENT
Performing a Critical Path Analysis Presented by Jonathan Japka, PMP Japka Management Moorestown NJ
Managing Schedule Slack/Float PMI Scheduling Forum January 6, 2015 January 6, 2015 Presented by: Ric Albani, PMP, PMI-SP, PMI-RMP, MCTS.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
VA Primavera P6: Baselining the Project Department of Veterans Affairs Office of Information and Technology IT Workforce Development (ITWD) in collaboration.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
SCHEDULE MANAGEMENT MODULE 8. Required by Specification City/Caltrans Level 1 schedule – simple Less than $1 million, less than 100 working days Advanced.
PROJECT SCHEDULING Presented by: G. Dudley Smith, PE Construction Bureau.
Establishing and Managing a Schedule Baseline
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
Chapter 6: Project Time Management
ENGINEERING MANAGEMENT (GE 404)
CHAPTER 6 PROJECT TIME MANAGEMENT
How to perform Time Impact Analysis / Window Analysis in Primavera P6
Guide to Project.
5th Annual Construction Berkeley Research Group
CHAPTER 6 PROJECT TIME MANAGEMENT
Presentation transcript:

Improved Project Control Through CPM Scheduling What Owners, PM’s and CM’s Need to Know t H E T I B U R O N T I B U R O N G R O U P, L L C G R O U P, L L C September 25, 2015 September 25, 2015

Baseline Considerations Realistic Plan and Timeline From NTP Through Construction Realistic Plan and Timeline From NTP Through Construction Tool to Manage Resources and Project Stakeholders Tool to Manage Resources and Project Stakeholders  Tool to Report to Project Stakeholders Ability to Manage Costs Ability to Manage Costs

Baseline Considerations Schedule Needs to be of Sufficient Detail to: Schedule Needs to be of Sufficient Detail to:  Minimize Secondary Effects of Construction on Operations  Do Preconstruction Schedule to Accomplish This  Document As Built Conditions  Demonstrate Need for Time Extensions and Work Around Options  Tool to Resolve Disputes

Baseline Considerations Analyze Time Impacts Analyze Time Impacts Develop Work Around Options Develop Work Around Options Furnishings, Fixtures And Equipment Furnishings, Fixtures And Equipment Coordinate With Third Party Contracts Coordinate With Third Party Contracts Start Up and Commissioning Start Up and Commissioning Move In Move In

Contract Requirements “You Can’t Enforce It If It’s Not In The Contract.” The Specifications Need To Be At a Strength Level that Match the Needs of the Project. The Specifications Need To Be At a Strength Level that Match the Needs of the Project.  Too Stringent on Small Projects  Not Stringent Enough on Large Complex Projects

Contract Requirements Scheduling Requirements Stronger for Larger Projects Stronger for Larger Projects Require Latest Primavera, P6, P3 or SureTrak Require Latest Primavera, P6, P3 or SureTrak Require Cost and Manpower Loading Require Cost and Manpower Loading Require Monthly Narrative & Reports Require Monthly Narrative & Reports Require Time Impact Analysis for Time Extensions Require Time Impact Analysis for Time Extensions Tie Updates to Progress Payments Tie Updates to Progress Payments

Baseline Review Do Thorough and Detailed Review of Baseline Do Thorough and Detailed Review of Baseline Analyze Baseline for Abuses and Flaws Analyze Baseline for Abuses and Flaws Assure Contractor Has Adequate Scheduling Resources Assure Contractor Has Adequate Scheduling Resources Assure Contractor Has Included Adequate Detail Assure Contractor Has Included Adequate Detail

Baseline Review Do Not Allow Sequestering of Float Do Not Allow Sequestering of Float  Through Logic and Constraints Check Near Criticality Check Near Criticality  Not More Than 20% of Activities with 10 Working Days of Float Check Preferential Logic Check Preferential Logic Check Calendar Usage Check Calendar Usage

Baseline Review Do Not Allow Compound Activities Do Not Allow Compound Activities  Activities Containing Multiple Trades Require All Submittals are Included Require All Submittals are Included Check Excessive Float Check Excessive Float  Float Value > 40% of Project Duration Don’t Accept Early Completion Schedule Don’t Accept Early Completion Schedule  Can Set Up Early Completion Delay Claim  Add Project Float Activity

Some Analysis Tools Claims Digger Claims Digger (Comes with P6) (Comes with P6) Schedule Analyzer Pro Schedule Analyzer Pro Sure Change Sure Change Excel Excel Proprietary Software Proprietary Software  Above Commercial Packages Do Not Do It All

Relationship Types Minimize Use Of Non-Conventional Logic Minimize Use Of Non-Conventional Logic  Aim For Majority of Logic To Be Finish To Start. oFinish To Start (FS) = An Successor Activity Cannot Start Until Its Predecessor Activities Finishes

Relationships Types  Finish to Start  Start to Start  Finish to Finish Form Slab Pour Slab Wall Layout Masonry Walls Wall Layout Drywall Framing

Relationship Lags Finish to Start, with Positive Lag Finish to Start, with Positive Lag Finish to Start, with Negative Lag Finish to Start, with Negative Lag Finish to Finish, with Positive Lag Finish to Finish, with Positive Lag Creates Gaps in Logic Chain

Float vs. Lag A Logic Tie Lag is Not Float A Logic Tie Lag is Not Float  Lags Can be Used to Sequester Float Who Owns the Float? Who Owns the Float?  Normally Project Owns the Float  You Can Allow for Owner to Retain Float for Their Time Savings, but This Must be In the Contract.

Unconventional and Unbalanced, or Uncoordinated Logic

Install Drywall – 10 days Tape & Float – 10 days Prime Walls – 10 days Paint Walls – 10 days Install Drywall – 10 days Tape & Float – 10 days Prime Walls – 10 days Paint Walls – 10 days Day 1 Day 25 Day 30 Day 35 Day 40 Day 45

Day 25 Day 30 Day 35 Day 40 Day 45 Install Drywall – 30 days Tape & Float – 10 days Prime Walls – 10 days Paint Walls – 10 days Install Drywall – 30 days Tape & Float – 10 days Prime Walls – 10 days Paint Walls – 10 days Day 1

Reverse Critical Path With Unconventional Logic, Even If The Logic Is Properly Coordinated Its Use Can Have Drastic Effects When Original Durations Are Revised With Unconventional Logic, Even If The Logic Is Properly Coordinated Its Use Can Have Drastic Effects When Original Durations Are Revised

Install Drywall – 30 days Tape & Float – 10 days Prime Walls – 10 days Day 1 Day 40 FF Logic Anchors Finish Of Successor To Finish Of Predecessor Pulling The Successor Forward In Time

Install Drywall – 30 days Tape & Float – 5 days Prime Walls – 10 days Day 35 Day 40 Day 45

Install Drywall – 30 days Tape & Float – 30 days Prime Walls – 10 days Day 1 Day 35Day 40

Date and Float Constraints

Opinion On Constraints “In General The Baseline Schedule Should Only Contain Two (2) Constraints; The Notice To Proceed And The Project Completion Date.” Use of Constraints Other Than These Requires Careful Consideration

Identifying Constraints In P6 and P3 – When You Calculate The Schedule It Provides Options For Identifying Constraints In P6 and P3 – When You Calculate The Schedule It Provides Options For Identifying Constraints  Tools / Schedule In SureTrak - You Will Need To Filter On Constraints In SureTrak - You Will Need To Filter On Constraints

Sample Constraint Window (P3 and SureTrak, In P6 Appears Under Status Tab)

Date Constraints

Mandatory Start and Finish Constraints Mandatory Start and Finish Constraints Override CPM Calculation Mandatory Start and Finish Constraints Override CPM Calculation They Can Truncate the Longest Critical Path They Can Truncate the Longest Critical Path They Can Render a False Total Float Calculation They Can Render a False Total Float Calculation

Install Drywall – 10 days Tape & Float – 10 days Prime Walls – 10 days Paint Walls – 10 days Day 1 Day 25 Day 30 Day 35 Day 40 Day 45

Install Drywall – 10 days Tape & Float – 10 days Prime Walls – 10 days Paint Walls – 10 days Day 1 Day 25 Day 30 Day 35 Day 40 Day 45

Zero Float Constraints Float Constraints Force Criticality Without Reference To Start and Finish Dates. Float Constraints Force Criticality Without Reference To Start and Finish Dates. P6 Does Not Provide For Float Constraints P6 Does Not Provide For Float Constraints

Milestones Milestones Are Treated As Constraints By Most Scheduling Software Milestones Are Treated As Constraints By Most Scheduling Software Milestones With Date Or Float Constraints Should Not Be Allowed In The Schedule Unless Contractually Called For Milestones With Date Or Float Constraints Should Not Be Allowed In The Schedule Unless Contractually Called For Internal Milestones Should Not Be Called For Unless LD’s Are Assigned Internal Milestones Should Not Be Called For Unless LD’s Are Assigned

Resource Constraints (Not Normal Constraints) The Relationships Between Like Activities In Different Project Areas The Relationships Between Like Activities In Different Project Areas These Relationships Are Resource Driven These Relationships Are Resource Driven These Resources Can Be Manpower, Equipment, Or Process Limitations These Resources Can Be Manpower, Equipment, Or Process Limitations

Resource Constraints Their Role In The Schedule Install Drywall – Bldg 1 Install Drywall – Bldg 2 Install Drywall – Bldg 3 Install Drywall – Bldg 1 Install Drywall – Bldg 2 Install Drywall – Bldg 3

Resource Constraints – Their Role in the Schedule Install Drywall – Bldg 1 Install Drywall – Bldg 2 Install Drywall – Bldg 3 Install Drywall – Bldg 1 Install Drywall – Bldg 2 Install Drywall – Bldg 3

Bar Charts – The Early Dates

Bar Charts – The Late Dates

Bar Charts – The Bigger Picture

Update Reviews Assure Updates Reflect Actual Progress and Match Payment Applications Assure Updates Reflect Actual Progress and Match Payment Applications Review Updates Promptly and Analyze for Abuses Review Updates Promptly and Analyze for Abuses Don’t Allow Mass Unilateral Changes to Schedule Updates Don’t Allow Mass Unilateral Changes to Schedule Updates If Schedule Significantly Changes Require Statused Only Copy Plus Revised Copy If Schedule Significantly Changes Require Statused Only Copy Plus Revised Copy

Retained Logic Retained Logic Schedules an Activity With Out of Sequence Progress According to the Network Logic. It Allows an Activity to Begin Out of Sequence, but the Remaining Duration for the Activity Cannot be Completed Until It’s Logical Predecessors Complete. Retained Logic Schedules an Activity With Out of Sequence Progress According to the Network Logic. It Allows an Activity to Begin Out of Sequence, but the Remaining Duration for the Activity Cannot be Completed Until It’s Logical Predecessors Complete.

Progress Override Progress Override Ignores Network Logic and Treats Out of Sequence Activities as Though They Have No Predecessors and Can Progress Without Delay. Progress Override Ignores Network Logic and Treats Out of Sequence Activities as Though They Have No Predecessors and Can Progress Without Delay.  This Can Hide Delays To The Project.  Does Not Reflect Contractor’s Current Work Plan.

Act A – 1 day Act F – 2 day Act B – 2 day Act G – 2 day Act C – 2 day Act H – 3 day Act D – 2 day Act I – 2 day Act J – 2 day Act E – 2 day Act K – 1 day Act A – 1 day Act B – 2 days Act C – 2 days Act D – 2 days Act E – 2 days Act K – 1 day Total - 10 days Act A – 1 day Act F – 2 days Act G – 2 days Act H – 3 days Act J – 2 days Act K – 1 day Total - 11 days Act A – 1 day Act F – 2 days Act G – 2 days Act I – 2 days Act J – 2 days Act K – 1 day Total - 10 days Critical Path Act A – 1 day Act F – 2 days Act G – 2 days Act H – 3 days Act J – 2 days Act K – 1 day Total - 11 days Act A – 1 day Act F – 2 day Act G – 2 day Act H – 3 day Act J – 2 day Act K – 1 day Calculating the Critical Path

Removing a Successor Relationship Act A – 1 day Act F – 2 day Act B – 2 day Act G – 2 day Act C – 2 day Act H – 3 day Act D – 2 day Act I – 2 day Act J – 2 day Act E – 2 day Act K – 1 day

Act A – 1 day Act F – 2 day Act B – 2 day Act G – 2 day Act C – 2 day Act H – 3 day Act D – 2 day Act I – 2 day Act J – 2 day Act E – 2 day Act K – 1 day Removing a Successor Relationship

Act A – 1 day Act F – 2 day Act B – 2 day Act G – 2 day Act C – 2 day Act H – 3 day Act D – 2 day Act I – 2 day Act J – 2 day Act E – 2 day Act K – 1 day Removing a Successor Relationship

Recovery Options Increase Manpower Increase Manpower Increase Work Hours and Workdays Increase Work Hours and Workdays Add Addition Shifts Add Addition Shifts Re-sequence Work Activities Re-sequence Work Activities  Meeting Of Minds Required Here Increase Equipment Or Material Increase Equipment Or Material

Dealing With Change Construction is a Dynamic Process, Change Will Occur Construction is a Dynamic Process, Change Will Occur  Updates Should Accommodate Changes Contract Should Require Notification of Change Contract Should Require Notification of Change Contract Should Require Submission of Time Impact Analysis Contract Should Require Submission of Time Impact Analysis Contract Should Require Recovery Options be Submitted Contract Should Require Recovery Options be Submitted

Dealing With Change (Continued) Analyze to Assure Changes are Impacting Critical Path Analyze to Assure Changes are Impacting Critical Path Determine Cause of Change Determine Cause of Change Determine if Delay Due to Change is Reasonable Determine if Delay Due to Change is Reasonable

Dealing With Change (Continued) Determine if Delay is Excusable and Compensable Determine if Delay is Excusable and Compensable  Weather Delays are Typically Excusable, But Not Necessarily Compensable Determine if There is Concurrent Delay Determine if There is Concurrent Delay Resolve Delays Promptly and Fairly Resolve Delays Promptly and Fairly

Wrap Up Discussion

Contact Information Leo F. Sumner II Principal The Tiburon Group, LLC Cell: (707) Mandeville, LA OfficeVallejo, CA Office 3433 Hwy. 190, Suite Springstowne Center, Suite 162 Mandeville, LA 70471Vallejo, CA (985) Phone(707) Phone (985) Fax(707) Fax