16 - 1 Time Phasing Development and Production Chapter 16.

Slides:



Advertisements
Similar presentations
Systems Analysis and Design 9th Edition
Advertisements

Chapter 12 Systems Development Three common methods for MIS development: The systems development life cycle (SDLC) Prototyping End-user development Five.
SCEA June 2000 JRS, TASC, 5/7/2015, 1 BMDO Cost Risk Improvement in Operations and Support (O&S) Estimates J. R. Summerville,
Project Planning Dr. Jane Dong Electrical and Computer Engineering.
Lab/Sessional -CSE-374. SYSTEM DEVELOPMENT LIFE CYCLE.
May 11, 2004CS WPI1 CS 562 Advanced SW Engineering Lecture #5 Tuesday, May 11, 2004.
Fundamentals of Information Systems, Second Edition
Project Time Management
Objectives Explain the purpose and various phases of the traditional systems development life cycle (SDLC) Explain when to use an adaptive approach to.
Engineering Design Development. Turner College and Career High School.
Jump to first page 30/06/ Chapter 1 System Development Environment.
Estimating Project Times and Costs CHAPTER FIVE Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Design, Implementation and Maintenance
Gantt Chart Engineering Design Development. Turner College and Career High School.
10/25/1999(c) Ian Davis1 Software Project Planning © Ian Davis.
 2004 Prentice Hall Business Publishing, Accounting Information Systems, 9/e, by Bodnar/Hopwood 11 – 1 Chapter 11 Systems Implementation, Operation,
Initiating and Planning Systems Development projects
1 Software Quality Engineering CS410 Class 5 Seven Basic Quality Tools.
4 -1 Data Normalization Chapter Data Normalization One of the most challenging and perennial problems confronting the cost analyst is the identification.
BSBPMG402A Apply Time Management Techniques 1 Apply Time Management Techniques Week 6 Project Time Processes – Part 2 C ertificate IV in Project Management.
Work breakdown structure
“WHY AFFORDABILITY IS A SYSTEMS ENGINEERING METRIC” Quentin Redman Director – Solutions Architect PRICE Systems L.L.C.
Copyright ©2009 by Pearson Education, Inc. Upper Saddle River, New Jersey All rights reserved. Engineering Economy, Fourteenth Edition By William.
PPMT CE-408T Engr. Faisal ur Rehman CED N-W.F.P UET P.
Hartley, Project Management: Integrating Strategy, Operations and Change, 3e Tilde Publishing Chapter 5 Time Management Developing and controlling the.
Cost Factors Chapter Introduction We tend to think of cost estimating relationships (CERs) as complex equations with a number of independent.
4 -1 Data Normalization Chapter Data Normalization One of the most challenging and perennial problems confronting the cost analyst is the identification.
Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management.
Lecture 3 Scheduling CSCI – 3350 Software Engineering II Fall 2014 Bill Pine.
Project Management 101 CS3300 Fall Generic Management Planning Organizing Staffing Leading / Directing Controlling To accomplish goals of an organization.
Financial Project Metrics in Feasibility Study
Lecture 7. Review of Lecture 6 Project Scheduling: The process of defining project activities, determining their sequence, estimating their duration Scheduling.
Managing Project Resources. Project Resources Human Resources Project stakeholders: – Customers – Project team members – Support staff Systems analyst.
Project Planning & Control 1 ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 3.
Management & Development of Complex Projects Course Code - 706
Eleventh Lecture Hour 9:30 – 10:20 am, Saturday, September 16 Software Management Disciplines Iterative Process Planning (from Part III, Chapter 10 of.
© 2010 Innovation and Business Industry Skills Council Ltd. BSBMKG506B Plan market research Session 4 Develop market research plan.
Copyright 2002 Prentice-Hall, Inc. 1.1 Modern Systems Analysis and Design Jeffrey A. Hoffer Joey F. George Joseph S. Valacich Chapter 1 The Systems Development.
Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Management Chapter 5 Project Integration Management.
After years of decline, education’s share of the state budget leveled off in ; actual dollars allocated to education continued to fall, however.
 2001 Prentice Hall Business Publishing, Accounting Information Systems, 8/E, Bodnar/Hopwood Systems Implementation, Operation, and Control Chapter.
Systems Analysis and Design in a Changing World, Fourth Edition
Project Management All projects need to be “managed” –Cost (people-effort, tools, education, etc.) –schedule –deliverables and “associated” characteristics.
Fundamentals of Information Systems, Second Edition 1 Systems Development.
NASA/Air Force Cost Model presented by Keith Smith Science Applications International Corporation 2002 SCEA National Conference June
Chapter 6 CASE Tools Software Engineering Chapter 6-- CASE TOOLS
CSE SW Project Management / Module 15 - Introduction to Effort Estimation Copyright © , Dennis J. Frailey, All Rights Reserved CSE7315M15.
Yazd University, Electrical and Computer Engineering Department Course Title: Advanced Software Engineering By: Mohammad Ali Zare Chahooki The Project.
Unit – I Presentation. Unit – 1 (Introduction to Software Project management) Definition:-  Software project management is the art and science of planning.
Engineering Economics Lecture 18 Project Management 6 January 2010.
Copyright , Dennis J. Frailey CSE7315 – Software Project Management CSE7315 M15 - Version 9.01 SMU CSE 7315 Planning and Managing a Software Project.
(6) Estimating Computer’s efficiency Software Estimation The objective of Software Estimation is to provide the skills needed to accurately predict the.
1 TEAM BUILDING & MANAGEMENT. 2 CONTENTS Generalities The individual The individual in the group To manage the group The group manager The group facing.
ALI SALMAN1 LECTURE - 05 ASST PROF. ENGR ALI SALMAN ceme.nust.edu.pk DEPARTMENT OF ENGINEERING MANAGEMENT COLLEGE OF E & ME, NUST DEPARTMENT.
Information Technology Project Management, Six th Edition Kathy Schwalbe Copyright Disampaikan Oleh : Wiwid Dolianto S.Kom, MT Universitas Muhammadiyah.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
1 Phasing the Cost Estimate OS Phasing the Cost Estimate At the end of this presentation we will have covered: –Various methods used to phase.
Software project management 3rd Umer khalid Lecturer University of Lahore Sargodha campus.
Chapter 3: Cost Estimation Techniques
Introduction to Project Management Chapter 7 Managing Project Resources Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George.
Chapter 3: Cost Estimation Techniques
Business Management Techniques
Object-Oriented Software Engineering Using UML, Patterns, and Java,
2nd Task of Your Project „All you have to decide, is what to do with the time that is given to you.“ J.R.R. Tollkin Prof. Dr. Christian Bleis 1 Interaktionskompetenz.
Chapter 3: Cost Estimation Techniques
Chapter 3: Cost Estimation Techniques
System Analysis and Design:
Chapter 3: Cost Estimation Techniques
Presentation transcript:

Time Phasing Development and Production Chapter 16

Time Phasing Development Say you are estimating the cost of the next Navy long- range, carrier-based bomber. Your development program is projected to last 8 years, and the production run is expected to occur over 12 years. Your development CERs have provided you with the total development cost. Now, for programming and budgeting purposes, you must identify your resource requirements by fiscal year. How will you allocate the development costs over the eight years? Note: Whenever dollars are being spread across two or more fiscal years, the calculations must be performed in base year or constant year dollars.

Incremental Funding While PRODUCTION can be said to be product oriented in its funding approach, DEVELOPMENT is more process oriented. This means cost has to be tied to the process of development which includes system requirements review, preliminary design review, critical design review, software coding, system tests, etc. Incremental Funding is the process of breaking a development effort down into fiscal year increments and funding one increment at a time.

Fiscal Spread Procedures Assume we want to estimate the Engineering and Manufacturing Development (EMD) cost for the Automated Information Management System (AIMS). Using CERs, analogies, etc., we have come up with a point estimate representing the cost of the system. This may be exactly what is needed to allow the decision maker to select an alternative, but in order to be useful as a management tool it is necessary to spread the cost across the applicable fiscal years of the effort. We will look at various techniques for the fiscal year spreading of incremental costs. We begin with the WBS indicated on the next page. The estimate was arrived at using CERs and cost factors.

Work Breakdown Structure

Fiscal Spread by Program Schedule This technique involves the following process of developing schedules and milestones: – Determine the milestones. – Time phase milestones based on the program schedule. – Estimate percent of total cost required to complete each milestone. – Allocate cost to appropriate fiscal year(s).

Step 1 - Determine Milestones Select those milestones which are most quantifiable. In our example we will use:

Step 2 - Time Phase Milestones

Step 2 - Time Phase Milestones

Step 3 - Estimate Cost Percentages

Step 4 - Allocate Costs by Fiscal Year

Results of Fiscal Spread Procedure Since this method is tied to the program schedule it can be fairly easily defended. However, if the program is not yet developed to any level of detail, then the analyst must either pursue development of the schedule or look for another methodology.

Time Phasing Production Until now we have focused on time-phasing an estimate in the development stage. The next step is to address spreading the production estimate over time. The production CERs yield a T1 for recurring hardware. In addition, you have factors for data, support equipment, training and other non-recurring costs. If production spans 12 years, where in the 12 year production schedule do you allocate costs for data or support equipment?

Outlay Profile Method The outlay profile method can be used to fiscally spread a cost estimate for a production program. In a production program where multiple lots are being produced over multiple years, this has the effect of converting a cost estimate into a budget estimate. Consider a missile production program which produces 1000 air-to-air missiles over five years. Historically, it takes six years to spend all of the funds obligated in a missile production contract. So, for a five year production run, the program office can plan on providing funding for 11 years. See example, next page.

Outlay Profile Method

Outlay Profile Method