BDS: 1 October 13, 2007 BDS KOM EDR planning discussion Andrei Seryi October 13, 2007.

Slides:



Advertisements
Similar presentations
February 7, 2007-Beijing (Zisman-DR) Global Design Effort 1 Damping Ring EDR Plans Michael S. Zisman, Jie Gao, Susanna Guiducci, Andy Wolski DR Area System.
Advertisements

11-13/10/2007 ILC BDS Kick-Off Meeting, SLAC, US 1 BDS Vacuum System Dr. Oleg B. Malyshev ASTeC Daresbury Laboratory.
Global Design Effort Goals and Introduction Andrei Seryi, SLAC, September 17, 2007.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
Global Design Effort Beam Delivery System & Machine Detector Interface Andrei Seryi, SLAC Annual DOE HEP Program Review June 11-14, 2007.
Summary of wg2a (BDS and IR) Deepa Angal-Kalinin, Shigeru Kuroda, Andrei Seryi October 21, 2005.
BDS GDE context LC-ABD2 : WP4 - Beam Line Design 12 th April 2007, LC-ABD Plenary, RHUL Deepa Angal-Kalinin ASTeC, The Cockcroft Institute.
1 Low-energy RHIC electron Cooler (LEReC) Update November 17, 2014.
NLC - The Next Linear Collider Project IR Working Group Summary Tom Markiewicz LC R&D Workshop, UCSC June 29, 2002.
European Design Study Towards a TeV Linear Collider WP 2 : Beam Delivery System Co-ordinator: Deepa Angal-Kalinin CCLRC, Daresbury Laboratory.
MuCool RF Status MICE Collaboration Meeting June 7-10, 2006, Fermilab A. Moretti June 9, 2006.
July 7, 2008 SLAC Annual Program Review Page 1 Andrei Seryi, SLAC American Regional Team leader for BDS Deputy of ATF Spokesperson for ATF2 Global Design.
Beam Delivery System Review of RDR(draft) 1.Overview 2.Beam parameters 3.System description 3.1 diagnostic, tune-up dump, machine protection MPS.
November 07, 2006 Global Design Effort 1 Beam Delivery System updates BDS Area leaders Deepa Angal-Kalinin, Hitoshi Yamamoto, Andrei Seryi Valencia GDE.
Personal strategy for ATF2 beam operation in 2009 Toshiyuki OKUGI 2009 / 7 /22 ATF2 weekly meeting.
Global Design Effort Push-pull studies How to proceed LCWS07 June 1, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi.
February 26, 2007 Global Design Effort 1 Most recent in Beijing BDS/IR talk, February 4, 2007:
Fred Asiri1 Conventional Facilities and Siting Global Group (CFS) SLAC Update Conventional Facilities and Siting Global Group (CFS) SLAC Update November.
BDS Magnet-Power System-Facility Optimization1 ILC BDS Kickoff Meeting Basis for Magnet, Power System and Cooling Facility Optimization Discussion Paul.
Global Design Effort Beam Delivery System design and EDR, Introduction Andrei Seryi, SLAC BDS Kick-Off meeting, October 11-13, 2007.
PD5: Detector Integration / Machine Detector Interface T. Markiewicz/SLAC 15 May 2014 SiD Meeting / AWLC Fermilab Summary.
Global Design Effort Beam Delivery System => EDR LCWS07 June 2, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi Yamamoto.
D. Angal-KalininEUROTeV Annual Meeting, DESY WP2 : Beam Delivery System D. Angal-Kalinin ASTeC, STFC, Daresbury Laboratory 4 th EUROTeV Annual.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
DESY_ILCW07 Global Design Effort-CF&S 1 Beam Delivery System & Interaction Region Fred Asiri CF&S Point of Contact.
ILC Beam Delivery System / MDI Issues for LCC-phase (~
Global Design Effort Critical Interaction Region Issues, Report from the IR engineering workshop Andrei Seryi, SLAC October 24, 2007.
11th December 2007 LET workshop, SLAC 1 Beam dynamics issues in Beam Delivery System Deepa Angal-Kalinin ASTeC, Daresbury Laboratory.
1 Tim Michalski October 6, 2015 Engineering Issues in MEIC.
BDS Andrei Seryi, Deepa Angal-Kalinin, Emmannual Tsesmelis, Rogelio Tomas, Andrea Latina, Daniel Schulte Detectors Civil engineering.
Interaction Region Issues and Beam Delivery R&D Issues & IR Design Status R&D Plans T. Markiewicz Klaisner Review 4/15/1999.
ATF2 Commissioning Toshiyuki Okugi 2008 / 7 /9 ATF2 beam commissioning meeting, KEK.
Global design effort DOE meeting 8/10/06 Global design effort Americas 1 FY07 DOE ILC Budget recommendations G. Dugan ILC-GDE/Cornell University GDE Americas.
Interaction Region & IR integration EDR Planning Tom Markiewicz/SLAC SLAC BDS Kick-Off-Meeting 13 October 2007.
October 20, 2006 Global Design Effort 1 ILC Interaction regions : The GDE perspective Talk based on several talks presented by BDS area leaders Andrei.
February 05, 2007 Global Design Effort 1 Beam Delivery System R&D S4 Task Force Chris Damerell, Hitoshi Hayano, Marc Ross Deepa Angal-Kalinin, Andrei Seryi,
Global Design Effort Introduction and goals of the meeting Andrei Seryi, Toshiaki Tauchi Fifth ATF2 Project Meeting December 19-21, 2007.
1 V. Kashikhin for ILC ALCPG 2007, FNAL Meeting October 23, 2007 Ring to Main Linac Magnets.
CLIC Machine-Detector Interface Working Group (MDI) Emmanuel Tsesmelis CERN TS/LEA CLIC-ACE of 3 September 2008.
Global Design Effort CLIC-ILC BDS & MDI work Materials for discussion Daniel Schulte, Rogelio Tomas and Emmanuel Tsesmelis for CLIC team Andrei Seryi for.
1 The ILC Control Work Packages. ILC Control System Work Packages GDE Oct Who We Are Collaboration loosely formed at Snowmass which included SLAC,
11/15/20051 Radiation Protection Issues for ILC (not exhaustive) A. Fassò, N. Noriaki, H. Vincke Radiation Physics.
October 25, 2007 A. Brachmann Slide 1 ILC polarized Electron Source EDR Work Packages ALCPG/GDE Meeting Fermilab, October 25, 2007 Axel Brachmann.
HL-LHC Crab Cavity Review Debriefing Comments from LARP June 30, 2014.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
BDS Lattice Design : EDR plans GWP03 Meeting 04/12/2007.
Global Design Effort Beam Delivery System Summary Andrei Seryi, SLAC ALCPG/GDE meeting October 25, 2007.
Beam Delivery system design and plans Andrei Seryi SLAC on behalf of BDS design team ILC08 and LCWS08 17 November 2008 Illustration of beam dump with double.
Beam Delivery (wg4) update since Snowmass Andrei Seryi for WG4 GDE meeting December 8, 2005 Snowmass 2005 GDE Meeting at INFN-LNF.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
Beam Delivery configuration materials to start discussion Andrei Seryi, Deepa Angal-Kalinin, Hitoshi Yamamoto BDS area GDE meeting at KEK, January 19-20,
Interface of FP420 to LHC FP420 meeting 28-Sep-2006.
1 CTF3 CLEX day July 2006 CLEX day 2006 Introduction G.Geschonke CERN.
BDS/MDI Deepa Angal-Kalinin Andrei Seryi AD&I Meeting, DESY, May 29, 2009.
Beam delivery and ATF2 Andrei Seryi SLAC October 1, 2008.
February 4, 2007 Global Design Effort 1. February 4, 07 Global Design Effort IR&MDI: 2 Tuesday’s discussion EDR organization Work Package distribution.
Eric Prebys, Fermilab Program Director, LARP July 10, 2012.
Positron Source Report Jim Clarke STFC Daresbury Laboratory/Cockcroft Institute.
November 12-13, 2007 Super-B Factory: Accelerator Costing, PEP-II Hardware and Schedule J. Seeman SLAC International Review Committee meeting November.
Mandate Priorities Other tasks Membership Forthcoming reports to CTC
Plans towards CC in the LHC a US – centric perspective
KEK news ( ) S.Tanaka.
The ILC Control Work Packages
Beam Delivery update Andrei Seryi December 12, 2005
CLIC-ILC BDS & MDI work.
Andrei Seryi Materials for discussion TILC-08
CLIC damping rings working plan towards the CDR
Undulator Cost & Schedule Patric Den Hartog, ANL April 24, 2002
ThomX – Commissioning Meeting – 25/01/2018
BDS EDR Discussion EDR Organisation? Discussion of WP distribution
Presentation transcript:

BDS: 1 October 13, 2007 BDS KOM EDR planning discussion Andrei Seryi October 13, 2007

BDS: 2 October 13, 2007 BDS KOM BDS Sys.eng. office Detector liaison Suggested “generic” work packages (GWP) for EDR Beam Delivery at Level 4 assisting

BDS: 3 October 13, 2007 BDS KOM GWP.2ATF2 construction, commiss. & operation –Includes ATF and ATF2 work related to BDS. The work-package, the ATF2, is of special kind, because it contains similar branches as BDS area itself and is in large parallel to BDS structure. GWP.3Acc. & det. ph. reqts. and design integration –This work package is a crucial place where system optimization and interfaces to CFS and detector will be done. On the following level, this work will include sub-work-packages for Optics, tolerances, tuning & feedback (apertures & magnet types standardization; setting specifications for all sub-systems); Backgrounds, other detector requirements (field homogeneity, IR apertures, alignment, etc.); CFS interfaces & optimization (air, water T, stability, vibration, tunnel & cavern sizes, penetrations, etc.); Installation model for BDS (magnet sizes, shafts, elevators, detector & machine interference, etc.); Design study of alternatives (0&2mrad designs, gamma-gamma, e-e-, entrance intratrain feedback; etc.). GWP.4Interaction Region and IR integration –This work package is the one very tightly connected to detector hardware design. It includes, on the sub-WP level, the IR system engineering and integration, IR magnet design and its prototypes, IR cryogenics, IR shielding design, Detector moving system, stability study of IR magnets, alternative magnet solutions for IR, etc. Leaders of this sub-work-package will work closely with representatives of two emerging detector proto-collaboration to create an optimal IR design.

BDS: 4 October 13, 2007 BDS KOM GWP.5Crab cavity system –The Crab cavity system work package will include optimization of RF design of cavity & couplers, development of phase stable RF power system, designing the cryostat for crab cavity, prototyping the crab cavity and couplers, studying the phase stability with two cells, prepare crab cavity beam tests and performing them. GWP.6Beam dump system –The Beam Dump system work package will include designing widow & remote replacement mechanism, engineering of the beam dump radiation water system, engineering the beam dump shielding, designing the beam dump vessel, performing irradiation tests of dump window prototype, optimizing physical design of beam dump, prototyping beam dump window, building the window remote replacement front-end. GWP.7Collimation system –The collimation system work-package will include optical, physical and engineering design of collimators, performing beam damage tests of collimators, verifying collimator wakefields in beam measurements.

BDS: 5 October 13, 2007 BDS KOM GWP.8BDS magnets and power supplies –The Magnet and Power Supply work-package will include conceptual design of DC magnets and more detailed design of pulsed magnets, design of BDS specialties the muon walls, magnet movers, and beam sweepers, septa and kickers, design and prototyping of low field dipoles, design and optimization of DC and pulsed power supply system, development and possible prototyping of HS power supply module, in particular the bipolar one. GWP.9BDS instrumentation –The BDS Instrumentation work-package would mostly focus on defining specifications, sizes, apertures, interfaces, etc. The Development part will focus on E-spectrometers, feedback hardware, laser wires and large aperture BPMs. GWP.10BDS vacuum system –The Vacuum System work-package would include developing the general layouts with locations of ports, bellows, valves, gauges; the conceptual schemes of RF shields, chambers in moderately complicated areas such as laser wires and Y-s (BSY); and more detailed schemes of chambers in very complicated areas such as IR. The work will also include optimization of vacuum chamber aperture, pressure; physical design of vacuum system in terms of SR, beam- gas, desorption and impedances; engineering integrated design of vacuum system; and detailed design of IR vacuum chamber.

BDS: 6 October 13, 2007 BDS KOM Charge for BDS GWP chairs and deputies –interact with BDS manager to form the detailed work- packages for EDR phase and to form the teams –perform the coordinating role of the work in particular, run EDR meetings (schedule on next page), starting from beginning of November –personally drive the design work

BDS: 7 October 13, 2007 BDS KOM BDS EDR Meetings: ATF2 construction, commissioning & operation –Ongoing weekly, late evening SLAC time. Cycle through different time? Acc. & physics requirements and design integration –Primarily: late afternoon UK, ~8am SLAC. Bi-weekly. Cycle ~monthly: UK morning Interaction Region and IR integration –Bi-weekly and cycle through morning & late afternoon of SLAC time Crab cavity system –Ongoing monthly, late afternoon UK, ~9am SLAC. => Bi-weekly, & focus on EDR BDS beam dump system –Cycle: am UK & India, pm SLAC – pm UK & India, am SLAC. Bi-weekly. BDS Collimation system –Primarily: late afternoon UK, ~8am SLAC. Bi-weekly BDS magnet & PS –Cycle: late afternoon SLAC - morning in Japan; evening SLAC morning in Moscow BDS instrumentation –Primarily: late afternoon UK, ~8am SLAC. Bi-weekly BDS Vacuum system –Primarily: morning in UK, late afternoon in Japan BDS WP coordination & management meeting –Cycle: morning-evening in SLAC

BDS: 8 October 13, 2007 BDS KOM GWP02&03&04&09_BDS_EDR_EOI_FONT_UK.doc GWP02&03&09_BDS_EDR_EOI_Kolomensky.doc GWP02&03&09_BDS_EDR_EOI_MONALISA_UK.doc GWP02&03_BDS_EDR_EOI-Santana.doc GWP02&03_BDS_EDR_EOI-kkubo.doc GWP02&03_BDS_EOI_AccPhys_appleby_UK.doc GWP02&03_BDS_EOI_Accphys_DAK_UK.doc GWP02&04_BDS_EDR_EOI-1_lanfa.doc GWP02&09_BDS_EDR_EOI_BPM_UK.doc GWP02&09_BDS_EDR_OTR_ODR_UK.doc GWP02_ATFCommissioningEOI_PT.doc GWP02_ATFExtractionEmittanceEOI_PT.doc GWP02_ATFFlightSimulatorEOI_PT.doc GWP02_ATFInjectorTuningEOI_PT.doc GWP02_ATFJitterStudyEOI_PT.doc GWP02_ATFOrbitStudyEOI_PT.doc GWP02_ATFTuningStrategyEOI_PT.doc GWP02_ATFTuningToolsEOI_PT.doc GWP02_BDS_EDR_EOI.CFS.doc GWP02_BDS_EDR_EOI.QBPM.doc GWP02_BDS_EDR_EOI.alignment.doc GWP02_BDS_EDR_EOI.commissioning.doc GWP02_BDS_EDR_EOI.honda.doc GWP02_BDS_EDR_EOI.reconfigure.doc GWP02_BDS_EDR_EOI.shintake_ATF2.doc GWP02_BDS_EDR_EOI.tuning.strategy.doc GWP02_BDS_EDR_EOI.tuning.tools.doc GWP02_BDS_EDR_EOI.vacuum.doc GWP02_BDS_EDR_EOI_Iw2.doc GWP02_BDS_EDR_EOI_Iw3.doc GWP02_BDS_EDR_EOI_Korea.doc GWP02_BDS_EDR_EOI_Sanuki.doc GWP02_BDS_EOI_AccPhys_GAB_UK.doc GWP02_BDS_EOI_SpinDyn_UK.doc GWP02_BDS_EOI_laserwire_UK.doc GWP02_IROpticsDesignEOI_PT.doc GWP02_IRVibrationDesignEOI_PT.doc GWP03&09_BDS_EDR_EOI_Alignment_UK.doc GWP03_BDS1TeVEOI_PT.doc GWP03_BDSApertureStandardizationEOI_PT.doc GWP03_BDSExtLineEOI_PT.doc GWP03_BDSFieldStabilityEOI_PT.doc GWP03_BDSHighLumiEOI_PT.doc GWP03_BDSIROrbitEOI_PT.doc GWP03_BDSIRWFEOI_PT.doc GWP03_BDSLStarEOI_PT.doc GWP03_BDSMagnetStandardizationEOI_PT.doc GWP03_BDSOpticsEOI_PT.doc GWP03_BDSTuningEOI_PT.doc GWP03_BDS_EDR_EOI_sanami.doc GWP04&07_BDS_EDR_EOI_Levchenko.doc GWP04&08_BDS_EDR_EOI-Romanov.doc GWP04_BDS_EDR_EOI-Kostromin.doc GWP04_BDS_EDR_EOI-cryo.doc GWP04_BDS_EDR_EOI.background.doc GWP04_BDS_EDR_EOI_Extr.doc GWP04_BDS_EDR_EOI_IRQ_DS_cor.doc GWP04_BDS_EDR_EOI_Iw_R1.doc GWP04_BDS_EDR_EOI_PM_14mr_quads.doc GWP05_BDS_EDR_EOI - Crab system R1_UK.doc GWP05_BDS_EDR_EOI _FNAL_Crabs.doc GWP05_BDS_EDR_EOI_crab_cavity_modeling.doc GWP06_BDS_EDR_EOI_Dumps_UK.doc GWP07_BDS_EDR_EOI_Coll.doc GWP07_BDS_EDR_EOI_collimators_UK.doc GWP07_CollWakeComputerEOI_PT.doc GWP07_CollWakeTheoryEOI_PT.doc GWP08_ BDS Magnet Power System Design EOI Draft 2.doc GWP08_BDS_EDR_EOI-JINR-1-2.doc GWP09_BDS_EDR_EOI-JINR-2-1.doc GWP09_BDS_EDR_EOI.shintake_ILC.doc GWP09_BDS_EDR_EOI_EO_UK.doc GWP09_BDS_EDR_EOI_FNALInstr_mw.doc GWP09_BDS_EDR_EOI_Gam_Cal.doc GWP09_BDS_EDR_EOI_IOWA-polarimetry[1].doc GWP09_BDS_EDR_EOI_SLACpolarimetry.doc GWP09_BDS_EDR_EOI_spectrometer_hildreth.doc GWP09_espect_EOI-torrence.doc GWP10_BDS_EDR_EOI_suetsugu.doc GWP10_BDS_EOI_Vacuum_UK.doc EOIs as of October 12, 2007 Does not include expressions of interests discussed at SLAC, BNL, FNAL, for ongoing work planned via ART The ART funded work is included in the charts shown on next pages

BDS: 9 October 13, 2007 BDS KOM WP allocation There is no universal rule In some cases some labs are expressing interest In most cases, connections already exist, and one need to work to adjust them to EDR phase In other cases, need to search for interested labs The Beam dump, Magnets & PS, and Vacuum systems are under-subscribed / under-funded GWPs

BDS: 10 October 13, 2007 BDS KOM Distribution of resources on GWP funding uncertain TENTATIVE

BDS: 11 October 13, 2007 BDS KOM Distribution of resources on GWP funding uncertain TENTATIVE

BDS: 12 October 13, 2007 BDS KOM Distribution of resources on GWP TENTATIVE Numbers are subject to funding approval funding uncertain

BDS: 13 October 13, 2007 BDS KOM Let’s discuss each GWP one by one …