Service channels between Tracker and PP1 TK-PP1 Cable Channel Review 14 September 2007, Antti Onnela, CERN Installation order and Component status Mock-up.

Slides:



Advertisements
Similar presentations
AnaSonde Assembly. What is the AnaSonde? *Reads temperature, pressure, and humidity data from the atmosphere *After it is sent into the atmosphere, it.
Advertisements

Installation. Indoor Unit Installation Typical Installation.
Click on this image to open the full PDF document.
Wine Cellar Split System Basics. Definitions Split System – A cooling unit that “splits” the cooling coil and the condenser apart into two remote pieces.
MP Prototype 2 1IWF-EXP/ÖAW GRAZ  Smaller Size  Outcome of the test results with MP-P1 was the need for a reduced cross section  Rectangular Shaped.
Procedures during Tracker Connection WPA meeting 3 rd December 2007, Michael Eppard, CERN Installation sequence Manpower needs for installation work.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
AMS-02 tracker mechanics status of construction, assembly, integration Production: - Ladder integration - Installation on planes Inner tracker assembly:
Installation. Indoor Unit Installation Typical Installation.
Presentation on Installation of a Domestic Cold Water Storage Cistern
SpectraSonde Assembly. What is the SpectraSonde? Reads temperature, pressure, and humidity data from the atmosphere. The SpectraSonde doesn’t fly like.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
ATLAS SLHC UPGRADE ENGINEERING – LIST OF DECISIONS which will affect the design of auxiliary systems layout and routing BASIC LAYOUT FOR BARREL and WHEELS.
Setting up the Ricoh C305 Press F5 to start the Presentation
18 November 2010 Immanuel Gfall (HEPHY Vienna) SVD Mechanics IDM.
ATLAS Upgrade ID Barrel: Services around ‘outer cylinder’ TJF updated According to the drawing ‘Preparation outer cylinder volume reservation’
Electrical and Optical Cables Installation at P5 What When How H. Breuker
Ron Madaras, LBL U.S. Pixel Meeting, SCIPP, July 9-10, 2003 Patch Panel 1 (PP1) Brief Review Cost and Effort Estimate.
AnaSonde-3M Assembly. What is the AnaSonde-3M? The AnaSonde-3M reads temperature, pressure and humidity data from the atmosphere. After the AnaSonde is.
November 16, 2001 C. Newsom BTeV Pixel Modeling, Prototyping and Testing C. Newsom University of Iowa.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
CMS ECAL End Cap Meeting CERN 19 June to 23 June 2000 A.B.Lodge - RAL 1 ECAL End Cap High Voltage Cards and 2000 Electrical/Thermal Model. Progress on.
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 June 2006 No 1 /17 LARP Phase II Secondary Collimator RC1 Collimator Test Program Plan Forward Revised.
18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page
ATLAS Pixel Detector February 2002 Cooling Services Connections N. Hartman LBNL Cooling Connections Status Report: LBNL Effort February, 2002 N. Hartman,
November 12, 2001 C. Newsom BTeV Pixel Modeling, Prototyping and Testing C. Newsom University of Iowa.
Neil JacksonUK-V RAL 8th September Module to Disc Assembly Infrastructure –Services and test box –Evaporative cooling system –Disc Handling Tests.
LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,...
Chiho Wang Duke University 1 TRT Barrel integration Status / Schedule Chiho Wang.
1 Outer Barrel, Phase 2 Mech Review 26 Aug 2013, indico: Antti Onnela, CERN Tracker Phase 2 Mechanics Review, 26 August 2013 Status of the Outer.
The HCAL barrel absorber structure
TOB meeting, TOB meeting 20 September 2005, Antti Onnela: TOB mechanical integration status and plans n TST-TOB-TIB integration exercise n.
Update on Micro Channel Cooling Collaboration Meeting , G. Nüßle.
Build a Simple Electric Motor Uses a stator made of windings, an armature with two coils, and a commutator.
Jan. 28, 2014W. Bertl, PSI BPIX Cooling Status W. Bertl, PSI.
Direct Hot Water. What Cold Water System is Pictured? What hot Water System is Pictured?
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
V. Bobillier1 Cable installation status.
S. ZelepoukineECAL DCS status, ECAL TCG 17.Jun ECAL DCS status: Sensors, probes and cabling (SM/Dee) S. Zelepoukine IHEP Protvino/ETHZ
Status of the ATLAS ID Evaporative cooling system JCOV 25 Nov P. Bonneau TS/CV/Detector Cooling CONTENTS Overall statusOverall status Cooling plant.
Tracker Goals o Main issue is to be able to run cold as more radiation is accumulated. o Due to “uncontrolled” humidity behavior, our present limit is.
Cooling Loop Update ATLAS W4 Sheffield Richard French The University of Sheffield + all UK contributors.
Year 8 Fuse Tester Design & Technology PCB Information Fixed value resistors 470R = Yellow, Purple, Brown This component is soldered directly onto the.
Rapid Change Technology The following is a presentation to aid Technicians in the replacement of the Rapid Change Technology Block.
B [OT - Mechanics & Cooling] Stefan Gruenendahl February 2, 2016 S.Grünendahl, 2016 February 2 Director's Review -- OT: Mechanics &
USCMS Pixel PMG, Nov 29, Mechanics Status Disks, ½ Service Cylinders Installation USCMS FPIX FNAL PMG Joe Howell Bruno Gobbi Nov. 29, 2006.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
24 September 2012 Immanuel Gfall (HEPHY Vienna) SVD Status of Mechanics PXD-SVD Meeting Göttingen.
24 September 2012 Immanuel Gfall (HEPHY Vienna) Annekathrin Frankenberger (HEPHY Vienna) SVD Status of Mechanics PXD-SVD Meeting Göttingen.
Permanent Joining Nails: come in different shapes and sizes. Nails are much cheaper than screws and quick to put in. You do not need to drill holes in.
S A Griffiths CM42 June 2015 Electrical & Control.
Florian Buchsteiner (HEPHY Vienna)
Panda Solenoid Content Interface Box Cold Mass Layout Cooling Lines
Service channels between Tracker and PP1
Ti/SS transitions A.Basti INFN-PISA*
Service channels between Tracker and PP1
- STT LAYOUT - SECTOR F SECTOR A SECTOR B SECTOR E SECTOR D SECTOR C
Tracker Outer Barrel COOLING Antti Onnela, CERN.
Far Detector Activities Late 2017 – Early 2018
2S module geometry updates Module positioning concepts
Rod adaptors for module tests Module positioning studies
MICE Coupling Coil Update
Module/Ladder Assembly
PLUMBING MATERIALS, PIPE BENDING AND PRESSURE TESTING
Making a simple steady hand game
as a prototype for Super c-tau factory
Presentation transcript:

Service channels between Tracker and PP1 TK-PP1 Cable Channel Review 14 September 2007, Antti Onnela, CERN Installation order and Component status Mock-up plans

Summary of installation order and component status Installation order per PP1 ComponentStatus and remaining preparations 1Cable channels All channel pieces available at CERN ( spares of each type). Channel 1-2: HCAL attachments and fiber supports welded and ready. Copper plate attachment screws being prepared (drilling + welding). Cutting of channel 1 tip edges to be done. Edges to be taped. Channel 3: Fiber supports made, currently being welded. Cooling pipe support design ready, to be produced, and attachments to be made in channel 3. Passage slots for ECAL optocables need to be cut bigger. Edges to be taped. Channels 4 and 5: Edges taped. READY FOR INSTALLATION. Channel covers: All pieces available. Channel 1, 3, 5 covers need shortening / bending. Other: All screws and washers available, channel 1-2 modified screws are ready. Shims for channel 1-2 ready. Aluminum tape being procured. Note on the installation order: Installation of cable channels + water cooling much simpler and safer if done before Tracker installation. But bottle-neck and uncertainty: When will ECAL + HCAL allow installation of TK channels?

Summary of installation order and component status Installation order per PP1 ComponentStatus and remaining preparations 2Water cooling circuit Preparations (Meyrin site): 10 mm pipe material available at CERN. Copper plates produced. Assembly jig ready. First assembly starting “now”. Main challenge: Soldering between copper pipe and plates. Estimated production rate (2 pers.): 2 units per day, ~1 month for all. Installation (Point 5): Transport and handling tools still to be developed and made. For installing need good access to cable channel and PP1 (important!). Pipe connections in batches. Feeding pipes must be emptied of water! Use normal soldered capillary fittings, 2 per PP1. Fitting pieces ready. Soldering equipment ready. Leak tests to be done with pressure water? Can test only in groups.

Summary of installation order and component status Installation order per PP1 ComponentStatus and remaining preparations 3Temp + humidity sensors Sensors and cable material ordered. Sensor protections being designed, and need to be produced. Cabling of the sensors to be done. Installation in channels simple and fast (1-2 days, speed dictated by access). PP1 connectors and connectorisation How is the testing done? 4Cooling pipes + leak test (Includes special pipes from PP1 to TK end) 3D-design ready, except for last specials (pixel + thermal screen). 2D-drawings made for TEC pipes, all others made from 3D-coordinates. 3D-coordinates ready for 75% of Barrel and TEC pipes. Order placed to pipe bending company. 14 pre-production pipes (one PP1) should be available by 20 September. Pieces for ceramic PP1 fittings received. Vacuum-brazing done for first 50 connectors. Production speed 50 connectors per week (9 weeks to finish the production) Argon leak testers (2) received, and currently under testing with prototypes. Argon battery to be bought and installed in UXC. Argon feed-lines and valves to be installed to reach the cooling manifolds at balconies. 5*Barrel optoribbons Optoribbon supports made + installed on TK. Optoribbons regrouped and coiled on the supports. Assembly help tooling being developed and tested on mock-up. READY FOR INSTALLATION. * After removal of the nose cone the barrel optoribbon installation can be done in parallel with pipe and barrel cable installation.

Summary of installation order and component status Installation order per PP1 ComponentStatus and remaining preparations 6Pipe insulation Armaflex AF approved in June by CERN safety. All material available for PP1’s and TK ends. Material for cable channel to be ordered. Insulation in PP1 Y-pieces: all standards done, some specials remaining. 7PP1 heating cable Cable roll and end plugs received at CERN. Cutting and connectorisation to be done. Connector choice to be made! Support clamps to be ordered. 8Barrel MS & Ctrl –cables Barrel cables labeled with PP1 connector names and bundled by ½- channels on nose cones. READY FOR INSTALLATION. 9TEC MS & Ctrl –cables Cables in production. 10TEC Optoribbons Reference point (channel 1-2 junction) marked on TEC ribbons. TEC optoribbons regrouped and coiled in the boxes at bulkhead. READY FOR INSTALLATION. 11Other: Short pipe sections from TK end to PP0; Heating wires and cables in special sectors; Bulkhead covers; Proto Pixel; Beam-pipe supports

Cabling mock-up plans Step TaskWhen? 1Dismounting of present setup Remove cables and cooling pipes from both ½ channels. 3 rd week of September 2Test installation of water cooling (2 nd option: this is done directly at CMS) Replace channel pieces where needed, to allow attachment of water cooling. Install water cooling set. Install temp sensors in the channel and PP1 4 th week of September 3Test with pre-production standard pipes Install pipes Use final type of pipe supports (to be made) Install insulation Install cables (all available) End of September 4ATest with special channel pipes (one ½ channel) Install pipes in one ½ channel Install insulation Pipe supports in the channel and at PP1 ? Thermal tests? October 4BTest with special channel cables (one ½ channel) Install cables in the other ½ channel (enough of cables available?) Cable connections at PP1 ? October

Installation steps 1: Cable channels + 2: Water cooling STEP 2: Install 10 mm water cooling pipe, one loop around channels “A” and “C” with its copper cooling plates (not shown here) Copper plates attached to channel pieces with screws Braze connections in PP1 and leak test water circuit STEP 1: Install cable channel, made of 5 sections (sections 1 and 2 are one unit) All attached to HCAL with screws Section 3 Section 4 Section 5 Section 1 Section 2 Tracker PP1

Installation step 3: Temperature and humidity sensors “Min-max against ECAL”: 1 sensor at far corner away from water cooling 1 sensor next to water cooling Per PP1 sector the sensors are only in one ½ channel In top and bottom sectors the sensors are in the special ½ channels Route sensor wires along 10 mm cooling pipe up to connector in PP1

Installation step 3: Temperature and humidity sensors Wires from ECAL area run along the 10 mm water pipes up to the connector (Note: Per channel only “A” or “C” side, never both) D-SUB connector (with humidity sensor) and pre-installed cable to racks “Hot at cable entry”: Tight packing of cables entering PP1 “Cold against ribbons”: On the inside wall below multi-ribbon cables Total amount of sensors per channel: 2 temp sensors at ECAL + 2 in PP1 1 humidity sensor in PP1

Installation step 4: Pipes 1.Install male Lancasher fitting + first bend piece 2.Measure the correct length of the copper pipe end 3.Remove Lancasher fitting, cut the pipe and solder them together 4.Install the pipe definitively 5.Attach the pipe to the temporary mid-support (subsequent pipes attached to previous ones) 6.Cut the pipe to correct length 7.Solder the pipe with ceramic fitting 8.Clamp the pipe with support block (every 2 pipes) 9.Leak test with Argon (every 2 pipes)

Installation step 5: Barrel optoribbons (after removal of nose cone) Ribbons have been pre-bundled in TIF to match the channel shapes

Installation step 6: Pipe insulation, from TK to mid-support 2 layers of 9 mm Armaflex AF insulation, with joining tape In channels 1 and 2 must reduce insulation to allow space of cables. Where possible use 3 mm tape in addition Insulation of individual pipes at TK end is still to be studied: 3 mm tape? Tubular insulation?

Installation step 6: Pipe insulation at mid-support Mid-path support with this element. During pipe installation use temporary support This support shall be slightly closer to optoribbons, to provide space for cables next to water pipe. This support shall also be a bit further away from the pipe bend, to ease insulation joint.

Installation step 6: Pipe insulation from mid-support to PP1 From mid-supports to PP1 use 18 mm insulation or 2 layers of 9 mm.

Installation step 6: Pipe insulation in PP1 Inside PP1 use precut flat pieces, glued together Glued junction from tubular to rectangular section at PP1 entry Insulation of Y-section being done alreardy now!

Installation step 7: Heating cable in PP1 connection 30 W/m heating cable, length ~7 m / standard PP1, Routed on outer surfaces of the pipe channel

Installation step 7: Heating cable in PP1 Aluminium or plastic clamps and aluminium tape on top of the cable Heating cable follows the Y-piece (not present in this photo)

Installation step 8: Barrel MS & Ctrl cables Here we have installed 7 cooling pipes 40 multi-service cables This represents the biggest channel occupancy, which is 7 cooling pipes 38 multi-service cables 6 ctrl-cables (≈ 2 MS-cables) Channel sections 1-4 Channel section 5

Installation step 8: Barrel MS & Ctrl cables The covers fit, tightly Edges of covers 2 and 5 need to be slightly bent, to avoid scratching cables

Installation step 9: TEC optoribbons All pipes, including TEC pipes, must be in place and insulated before installing optoribbons Installation step 10: TEC cables Installation step 11: Special cables, etc. Channels for these ribbons to reach the PP1 are at these phi-locations 1 cm Last 1 cm of TK volume for TEC cables