LMC 27 November 2013 Status of LBDS LS1 activities and plans for 2014 reliability run Jan Uythoven for the many, many people working on the mentioned equipment
New TCDQ absorber Protects the machine in case of asynchronous dump Upgraded version robust to 2.5× ns The cross section of the upgraded TCDQ is identical to the present system. The graphite absorber is being replaced by a sandwich of graphite and carbon reinforced carbon fibre (CfC) New VMTAB bellows to allow large movement (TE/VSC) Production started 2 Jan Uythoven, Status LBDS LS1 & plans LMC, 27/11/2013 Old sandwich vs. new sandwich M. Atanasov, J. Borburgh
New TCDQ and related All 6 tanks are installed and aligned Modification of measurement tables ongoing (01/2014) Spare tank will be finished by the end of 2014 Related to asynch dump protection The new TCDQ position will be interlocked by the BETS (N.Voumard) New BPMS electronics (T. Lefevre, C. Boccard) Installation of TCSGP – jaw BPMs (S.Redaelli & project) 3 Jan Uythoven, Status LBDS LS1 & plans LMC, 27/11/2013
Abort Gap Cleaning Automatic procedures of the BSRA to make the system more reliable To be launched automatically by sequencer or ‘internal timer’ when in physics Aim is to automatically start the abort gap cleaning or dump the beam, without intervention of the operator Re-assessed quench levels of Q4 and Q5 with new TCDQ Improvements cleaning by the ADT New cables and hardware New cleaning algorithms being studied 4 LMC, 27/11/2013 Jan Uythoven, Status LBDS LS1 & plans See MPP 25/10/2013 S. Mazzoni, E.Bravin, S.Bart-Pederson W. Hofle, D.Valuch, E. Gianfelice-Wendt
Direct link BIS – LBDS re-triggering 5 LMC, 27/11/2013 Jan Uythoven, Status LBDS LS1 & plans BIS CIBM BIS CIBG Loop A Loop B Courtesy E. Carlier, S. Gaboruin BIS CIBDS RTB User permit (B1 config) 200us 250us Presented MPP 19/07/2013 S.Gabourin, R.Denz, E.Carlier, N.Magnin, M.Zerlauth, D.Wollmann, A.Apollonio Asynchronous trigger
Direct link BIS – LBDS re-triggering False Asynchronous beam dumps Specified: 2 in 10 years Calculated: in 10 years False Synchronous beam dumps Specified: 2 per year Calculated: per year Status Ordering components VHDL test bench ‘now’ Series of 5 boards to be launched December Install machine March Jan Uythoven, Status LBDS LS1 & plans LMC, 27/11/2013 V. Vatansver S. Gabourin
Dilution kickers MKB Installation of the nominal system (staged to spread costs) Add two MKB magnets per beam = 1 tank: 4 H + 6 V magnets 7 LMC, 27/11/2013 Jan Uythoven, Status LBDS LS1 & plans V.Senaj, L.Ducimetière
Extraction kicker MKD - Generator During LS1 operational energy was limited to 5 TeV Installation of HV insulators between GTO switches HV deflectors and return current rods 8 LMC, 27/11/2013 Jan Uythoven, Status LBDS LS1 & plans V.Senaj, L.Ducimetière
Add shielding to MKD & MKB cable ducts Additional shielding between UA and RA for MKD and MKB systems 9 Jan Uythoven, Status LBDS LS1 & plans LMC, 27/11/2013 V.Senaj
Extraction kicker MKD Power Trigger Unit Increase PTU maximum voltage from 3 kV to 4 kV (replacement of HVPS) Replace 1.2 kV IGBT with equivalent 1.7 kV type => better resistance to SEB Operate PTU at ~3500 V constant voltage, => Increase GTO gate current => Increase GTO lifetime => Reduce kicker rise time => Stabilise pulse delay over energy range 10 Jan Uythoven, Status LBDS LS1 & plans LMC, 27/11/2013 V.Senaj, M. Stjepic, E.Carlier
LBDS Controls Upgrade of Trigger Synchronisation Units cards (TSU) Distribute TSU over three different crates Motivation External review of TSU v2 cards (2010) Internal review of LBDS Powering (2012) VME crate +12V problem (2012) CIBU powering filters problems (2011) Improvement of surveillance & diagnosis 11 LMC, 27/11/2013 Jan Uythoven, Status LBDS LS1 & plans A. Patsouli, A. Antoine, N. Voumard
LBDS Powering Modifications Third UPS (backup) added everywhere Added a separated connection to a second UPS (US65) for LBDS Individual circuit breaker for each crate PSU Software monitoring of crate redundant PSU The aim is to improve safety 12 Jan Uythoven, Status LBDS LS1 & plans LMC, 27/11/2013 Tests to take place at end of AUG tests Prefer to test before starting run with local BIS loop -> end of May Test option with F3 and F4 off simultaneously V.Chareyre, H.Thiesen, I.Romera, M.Zerlauth E.Carlier, N.Magnin, A.Antoine Split in three crates
MKB Vacuum Number of ‘false beam dumps’ due to LBDS in 2010 – 2012 Too many dumps triggered by MKB vacuum, without having a real vacuum problem Problems with noisy vacuum signals 13 Jan Uythoven, Status LBDS LS1 & plans LMC, 27/11/2013
MKB Vacuum MKB vacuum gauges being replaced Problems with regular vacuum spikes (every 7 / 9 minutes) being investigated in detail Installation of test gauge outside beam vacuum Effect not visible outside the vacuum chamber Seems to be real and not a controls issue inside the chamber Source to be identified at start-up ABT prefers to maintain present 2 oo 3 interlock logic per individual MKB tank 14 Jan Uythoven, Status LBDS LS1 & plans LMC, 27/11/2013 Not only this device ! F. Antoniotti, JP. Boivin, P. Gomes
LBDS Reliability Runs Local Reliability Run 12 weeks, system in local Test the voltage holding of generators and magnets, erratic switching (without radiation), switch surveillance, cooling, stability, energy scans Remote Reliability Run 6 weeks, system in Remote Run sequencer for arming, local BIS loop and BETS-SIM Including energy ramps etc. Test new link between BIS – LBDS: get statistics Test operational software and diagnostics, XPOC etc. Risks to be a moving target with developments of FESA3, CMW etc. Followed by regular running until first beams Tests with beam (2015) Standard commissioning tests with beam Effective rise time measurement of the MKD (never done) Test dump with BLMDD (never done) 15 Jan Uythoven, Status LBDS LS1 & plans LMC, 27/11/2013
Commissioning / Reliability Runs / Dry runs 16 Jan Uythoven, Status LBDS LS1 & plans LMC, 27/11/2013 Nov – Dec 2013 Commissioning individual MKDs and MKBs Local (ABT) 06/01/2014– 14/02/2014 System tests LBDS Beam 1 and Beam 2 Local (ABT) 17/02/ /05/2014Reliability runLocal (ABT) March 2014Install new BIS – LBDS link(MPE) March – April 1/day week Tests from CCC, parallel to reliability run Remote 1 day/week (OP) 12/05/2014 – 23/05/2014 Install new TSU on LBDS & tests in local and from CCC (MPE / ABT / OP) 26/05/2014 – 04/07/2014 Reliability run in remote, local BIS loop and BETSIM. From CCC. UPS tests. Remote 07/07/2014 Weekly testing during dry runs / check on FESA(3) updates and added functionalities Remote Date to be determined by OP Remove local BIS and BETSIM, start testing machine wide and close BIS loop. Weekly testing. Remote End 2014 (OP)BIS loop closed, inject and dump under real machine conditions Remote Safety OK before summer Keep system working / software
Conclusions Many important changes to the LHC Beam Dumping System and related equipment To allow for higher beam energies and intensities To improve safety To increase availability Extensive testing is required to guarantee safety Reliability run in local, 12 weeks: generators and magnets Reliability run in remote, 6 weeks: BIS-LBDS, TSU To be finished before the summer holidays: back to bussiness Tests with beam at start-up Running in remote involves many equipment groups and requires coordination by the OP group 17 Jan Uythoven, Status LBDS LS1 & plans LMC, 27/11/2013