LHC CMS Upgrade Project CD-1 Alternative Selection and Cost Range Steve Webster Federal Project Director August 26, 2013 CD-1 Executive Session.

Slides:



Advertisements
Similar presentations
Planning, Budgeting, Acquisition & Management of Capital Assets Capital programming is an integrated process within an agency for planning, budgeting,
Advertisements

OFFICE OF SCIENCE Kurt W. Fisher Review Committee Chair Office of Science, U.S. Department of Energy 1 Closeout Report.
Contract and Project Management: A Field Perspective Moderator Michael Peek, PE CCE CFM Office of Engineering and Construction Management.
NSF Experience with Management of Research Infrastructure
US CMS DOE/NSF Review: May 8-10, US CMS Cost & Schedule Mark Reichanadter US CMS Project Engineer DOE/NSF Review 8 May 2001.
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
Mu2e WGM 2/22/2011 R. Ray Mu2e Project manager. CD-1 Our sole focus is on CD-1 and in particular, the Director’s Review scheduled for April 3-5. To be.
1 BROOKHAVEN SCIENCE ASSOCIATES Procurement Dave Paveglio, Contract Administrator NSLS-II PAC Meeting May 25, 2007.
Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 1 DOE/NSF Review of the Dark Energy Survey (DES) Project SC 6/7 Cost, Schedule.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science OECM Limited-External Independent.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
The SLHC and the Challenges of the CMS Upgrade William Ferguson First year seminar March 2 nd
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
FY2010 PEMP Notable Outcomes October 15, FRA, LLC Board of Directors 10/15-16/2009 Office of Quality and Best Practices Performance Evaluation Management.
1 BROOKHAVEN SCIENCE ASSOCIATES Authorization Basis Plan Steven Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting December 10 – 11, 2009.
U.S. Department of Energy Project Management: Communicating Progress – Celebrating Success Paul Bosco, PE, PMP, CFM, LEED-AP Director, Office of Procurement.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck NLSL II Deputy Director (Project Management)
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
7/26/2006 Wyatt Merritt 1 DECam Preparations for Critical Decision 2/3a Preparations for CD2 Preparations for CD3a DECam MOUs.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Slide 1 6-Nov-98PHOBOS Review: Cost & Schedule Cost & Schedule S. Steadman, MIT PHOBOS Cost & Schedule Review Technical Advisory Committee BNL November.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
Executive Session Director’s CD-1 Review of the Mu2e Project April 3, 2012 Elaine McCluskey.
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
DOE Order 413.3A Program and Project Management for the Acquisition of Capital Assets Catherine Santana Deputy Director, Project Management Systems, OECM.
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
24-Aug-11 ILCSC -Mumbai Global Design Effort 1 ILC: Future after 2012 preserving GDE assets post-TDR pre-construction program.
Fermilab Presentation Greg Bock, Pepin Carolan, Mike Lindgren, Elaine McCluskey 2014 SC PM Workshop July 2014.
1 US Cost & Schedule Summary W. R. Edwards US Project Manager CD-2/3a Review January 8, 2008 BNL.
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
DUSEL Beamline Working Group Meeting March 09, :00 AM – Snake Pit (WH2NE) By Dean Hoffer - OPMO.
OFFICE OF SCIENCE 1 Closeout Report on the DOE/SC CD-3b Review of the Utilities Upgrade Project (UUP) Fermi National Accelerator Laboratory August 11-12,
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
Closeout Report on the Review Committee (CD-1) for the Long Baseline Neutrino Experiment (LBNE) Project at Fermi National Accelerator Laboratory October.
1 Ventilation Systems Capital Asset Projects Safety Significant Confinement Ventilation System (15-D-411) Exhaust Shaft (15-D-412) Ronald.
CMS Trigger Upgrades Phase-I (1) Muon Trigger Upgrades: – CSCTF (CSC TrackFinder) – MPC (Muon Port Card) Calorimeter Trigger Upgrades: – HCAL TPG – Calorimeter.
OFFICE OF SCIENCE Closeout Report by the Review Committee for the LHC-CMS Detector Upgrade Project Fermi National Accelerator Laboratory August 27, 2013.
Fermilab Project Overview Michael Lindgren 2014 EVMS Surveillance Review 10-Dec-2014.
1 st of April st LS2C LS2 Committee Mandate and Organization 2 Chairman:Jose Miguel JIMENEZ Deputy:Jean-Philippe.
Office of Baseline Change Proposal (BCP) Approval or Brief Presented by: Draft version Jun 16, 2015.
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
Office of Critical Decision-1 Approve Alternative Selection & Cost Range or Brief Presented by:
Project Delivery Working Group FY2016 EFCOG Annual Meeting Robert P. Miklos Idaho National Laboratory Battelle Energy Alliance Working Group Chair June.
Risk Management Lucas Taylor Fermilab Risk Manager 3 rd February Director's Review -- Risk Management L. Taylor, 3rd February 2016.
P02 – U.S. CMS Contributions to the CMS HL-LHC Upgrades (402) Vivian O’Dell, HL-LHC USCMS Project Manager September 17, Director's Progress Review.
CERN Steve Kettell DUNE Collaboration Meeting January 12, 2016.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
OFFICE OF SCIENCE DOE/SC CD-3c Review of the Muon to Electron Conversion Experiment (Mu2e) Project Fermi National Accelerator Laboratory June 14-16, 2016.
1 DOE Independent Project Review Critical Decision-3a Long-Baseline Neutrino Facility/ Deep Underground Neutrino Experiment (LBNF/DUNE) Project DOE Executive.
Office of Project Management Oversight and Assessments Office of Critical Decision-3 Approve Start of Construction or Brief Presented by:
CMS HL-LHC Detector Upgrades Project Planning Workshop, 26th – 30th Sept 2016, Fermilab Lucas Taylor Associate PM (for Cost, Schedule, Risk) Overview and.
Camera PDR/CD1 Planning 19 September 2008
NNSA Project Reviews NNSA Office of Project Analysis, Oversight, and Review (NA-APM-1.1) June 7, 2017 Dwight Henderson, Director
LHC Science Goals & Objectives
Project Management W. J. Foyt
Risk Identification HL-LHC Detector Upgrades Project
U.S. CMS HL-LHC Project Report
Milestone A to Milestone B Requirements Management Activities
Preparations for a Lehman Review
Management Breakout: MREFC Budget Summary Victor L
PULSE Building Renovation
Details supporting the increase
Preliminary Project Execution Plan
Conventional Facilities
Presentation transcript:

LHC CMS Upgrade Project CD-1 Alternative Selection and Cost Range Steve Webster Federal Project Director August 26, 2013 CD-1 Executive Session

2 Outline Alternatives Analysis ES&H Key Performance Parameters Project Management Organization Work Breakdown Structure Cost, Funding & Schedule Integrated Project Team CD-1 Prerequisites Project Complexities Conclusion

Alternatives Analysis Alternatives are Limited LHC is the only collider with sufficient energy and luminosity to create Higgs Bosons The detector need to be upgraded The Mission Need Alterative Analysis focused on Funding Alternatives: DOE and NSF continue to work together, with DOE/HEP as the lead agency DOE/HEP engage in a partial and independent support of the effort No action 3

Environment, Safety & Health The Project has assigned a ES&H manager A safety assessment was performed and it was determined that work done at Fermilab will be covered under the existing ISM Program A Preliminary Harard Analysis Report has been prepared for work performed at Fermilab All equipment delivered to CERN will comply with applicable CERN requirements 4

Draft Key Performance Parameters 5 HCAL Threshold KPPObjective KPP Complete production of the HCAL Front End and Back End electronics. Installation of the HCAL Back End electronics and connection to the Calorimeter trigger. Test stand integration of the HCAL electronics and demonstration of the full design functionality. Demonstration that the HCAL Front End Electronics is ready to install. Complete production of the HCAL Front End and Back End electronics. Complete installation and checkout of the HCAL Front End electronics in the CMS detector. Installation of the HCAL Back End electronics, connection to the calorimeter trigger, and integration with the CMS data acquisition system. Demonstration of the full design functionality.

Draft Key Performance Parameters(Cont.) FPIX Threshold KPPObjective KPP 6 Complete four half cylinders, each with three disks. System is demonstrated by read out in test stand at CERN and turned over to CMS Technical Coordination to install. Four half cylinders, each with three disks and mechanical components for a spare half disk. System is demonstrated by read out in test stand at CERN and turned over to CMS Technical Coordination to install.

Draft Key Performance Parameters(Cont.) Trigger Threshold KPPObjective KPP 7 Demonstration of 98% agreement between upgrade trigger electronics at CERN and software emulation of this electronics through test pattern injection based on data taken after LS1, followed by demonstration of reduction of calorimeter and endcap muon trigger rates for electrons, photons, muons and taus with respect to the present system by a factor of two for a reduction of less than 15% in efficiency using the trigger emulator run on data taken after LS1. Incorporation of unganged ME1/1a data into the endcap muon trigger logic. Demonstration of 99.5% agreement between upgrade trigger electronics at CERN and software emulation of this electronics through test pattern injection based on data taken after LS1 followed by demonstration of reduction of calorimeter and endcap muon trigger rates for electrons, photons, muons and taus with respect to the present system by a factor of two for a reduction of less than 10% in efficiency using the trigger emulator run on data taken after LS1. Calorimeter Trigger electron and photon position resolution improved. Incorporation of unganged ME1/1a data into the endcap muon trigger logic.

Project Mgmt Organization 8

Work Breakdown Structure 9 WBS#WBS NAME 1 Large Hadron Collider (LHC) Compact Muon Solenoid (CMS) Detector Upgrade Project 1.1Project Management 1.1.1Project Milestones and Interfaces 1.1.2Project Management and Administration 1.1.3Project Controls and Finance 1.1.4Project Office Support 1.2Hadron Calorimeter (HCAL) 1.2.1HCAL Milestones and Interfaces 1.2.2HCAL Management 1.2.3HF Frontend 1.2.4HB/HE Frontend 1.2.5HCAL Backend 1.3Forward Pixel Detector (FPIX) 1.3.1FPIX Milestones and Interfaces 1.3.2FPIX Management 1.3.3FPIX Components 1.3.4FPIX Assembly and Testing 1.3.5FPIX Pilot System 1.4Trigger 1.4.1Trigger Milestones and Interfaces 1.4.2Trigger Management 1.4.3Muon Trigger 1.4.4Calorimeter Trigger

Planned Funding (AY $M) 10 Fiscal Year FY 12 FY 13 FY 14 FY 15 FY 16 FY 17 FY 18 Total ($M) OPC Design TEC (MIE) PED Construction Total Project Cost ($M) Contingency is $9.0M, 37% (39% of work remaining)

Proposed CD Schedule 11 MilestoneTypical Float CD-4 14 months (25%) Level 1 milestones—Acquisition Executive2 months for the CDs Level 2 milestones—Federal Project Director6 months Level 3 milestones—Project Manager3 months Level 1 MilestoneSchedule CD-0 Approve Mission Need9/18/12 (actual) CD-1 Approve Alternative Selection and Cost Range1 st Qtr FY14 CD-2 Approve Performance Baseline2 nd Qtr FY14 CD-3 Approve Start of Construction 4 th Qtr FY14 CD-4 Approve Project Completion (defined as delivery of components) 1 st Qtr FY20

Integrated Project Team 12 IPT established and functioning Membership –Simona Rolli, DOE Program Manager –Saul Gonzales, NSF Program Manager –Steve Webster, Federal Project Director, Chair –Alan Harris, Deputy Federal Project Director –Joel Butler/Steve Nahn, Project Manager –Erik Gottschalk, Deputy Project Manager –Aaron Dominguez, NSF Principle PI/Deputy PM –Others as needed, for example: ES&H, contracting & procurement

CD-1 Prerequisites 13 Acquisition Strategy—submitted for signature Preliminary Project Execution Plan—submitted for signature Integrated Project Team—chartered and functioning, led by FPD Risk Management Plan—completed One-for-one Replacement for Building square footage—NA Preliminary Hazard Analysis—completed Conceptual Design/Report—completed High Performance & Sustainable Building—NA Environmental documents/permits—Categorical Exclusion signed Independent Project/Design Review—July Integrated Safety Management Plan—completed Quality Assurance Program Plan—completed Safeguards and Security Requirements—included in PPEP

Project Complexities DOE/NSF/CERN Coordination CERN Schedule DOE Funding Profile 14

Conclusion 15 ESH&Q being integrated into design Project management team is in place 37% contingency in DOE TPC point estimate Current cost estimate from resource-loaded schedule is within cost range DOE TPC CD-1 cost range is $29.2M to $35.9M (CD-0 cost range was $22M to $34M) CD-1 prerequisites met Roadmap to CD-2 developed and progress will be reported at IPT and other project meetings Recommend CD-1 Approval