1 PROJECT MONITORING & CONTROL. 2 Project Monitoring and Control Why do we monitor? What do we monitor? When to we monitor? How do we monitor?

Slides:



Advertisements
Similar presentations
Project Management Concepts
Advertisements

Project Cost Management
Project management Information systems for management1 Project Management.
1 SW Project Management (Planning & Tracking) Dr. Atef Z Ghalwash Faculty of Computers & Information Helwan University.
Monitoring and Information Systems
Monitoring and Control
1 TenStep Project Management Process ™ PM00.3 PM00.3 Project Management Preparation for Success * Manage the Workplan *
Project Control Techniques
© 2012 Cengage Learning. All Rights Reserved. This edition is intended for use outside of the U.S. only, with content that may be different from the U.S.
Project Management Techniques.
Monitoring and Control Earned Value Management (EVM)
Project Cost Management Sections of this presentation were adapted from A Guide to the Project Management Body of Knowledge 4 th Edition, Project Management.
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
Project Time Management
Lean Six Sigma: Process Improvement Tools and Techniques Donna C. Summers © 2011 Pearson Higher Education, Upper Saddle River, NJ All Rights Reserved.
Monitoring and Controlling
Earned Value Management
Chapter 10 Project Monitoring and Control
EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool
Project Monitoring and Control. Monitoring – collecting, recording, and reporting information concerning project performance that project manger and others.
Module 8: Risk Management, Monitoring and Project Control We would like to acknowledge the support of the Project Management Institute and the International.
May 12 th Monitoring and Project Control. Objectives Anticipated Outcomes Express why Monitoring and Controlling are Important. Differentiate between.
4th Phase : 4th Phase : CONTROL Why is control necessary? Because:  People make mistakes  External factors can have impact on the project  Requirements,
BSBPMG503A Manage Project Time Manage Project Time Unit Guide Diploma of Project Management Qualification Code BSB51507 Unit Code BSBPMG503A.
Chapter 4 INFORMATION SYSTEM PROJECT MANAGEMENT PREPARED BY : DIYANA BINTI KAMARRUDIN FARAH IZZATI BINTI MOHAMMAD NOR RAIHAN BINTI MD JOHARI.
CONTROLLING TIME. ”Remember that time is money” Benjamin Franklin 1748.
Software Project Management
Project Time Con trol. Control = Monitor + Compare + Analysis + Action  Definition: Controlling  Controlling involves making sure that the results achieved.
Ahmad Al-Ghoul. Learning Objectives Explain what a project is,, list various attributes of projects. Describe project management, discuss Who uses Project.
10/19/ :26 AM 1 Project Cost Control. 10/19/ :26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
Management & Development of Complex Projects Course Code MS Project Management Earned Value Concepts Lecture # 19.
Project monitoring and Control
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Day 23.
11/9/2015 9:42 AM 1 Project Time Control. 11/9/2015 9:42 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems.
Project Management Inspections and Reviews 1 February.
Information System Project Management.  Some problems that org faced with IS dev efforts include schedule delays, cost overrun, less functionality than.
Copyright 2009 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems.
Project Time Management Ashima Wadhwa. Schedule Development – Determining start and finish dates for project activities – Without realistic dates, project.
Project Time Management
Report Performance Monitor & Control Risk Administer Procurement MONITORING & CONTROLLING PROCESS.
Microsoft Project 2010 ® Tutorial 5: Tracking Progress and Closing the Project.
Project Management Information System What?? Objective: –Record & report relevant information and status of various components of project –Highlight the.
Financing & Budgeting in the Public Sector PP Instructor: Trebor Negron Unit 6 Seminar 6/24/12 7:00 – 8:00 PM, EST.
Project Management ISE 5101 Karl Smith Project Monitoring & Control I Project Meetings.
Information Technology Project Management, Six th Edition Kathy Schwalbe Copyright Disampaikan Oleh : Wiwid Dolianto S.Kom, MT Universitas Muhammadiyah.
Copyright 2015 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
1 Schedule Control with Microsoft Project 2003 P roject M anagement M ethodologies Laura Williams, PMP.
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
Project Cost Management
Project Monitoring
Monitoring and Information Systems
TOPIC-8B- PROJECT COST CONTROL
Project evaluation and control
TOPIC-8A- PROJECT TIME CONTROL
Earned Value - What is it
Project Cost Management
Monitoring and Reporting Project Progress
Financial Principles and Project Cost Management
Monitoring and Information Systems
In this tutorial you will:
Earned Value Management
Monitoring and Information Systems
PLANNING ENGINEERING AND PROJECT MANAGEMENT
Project Cost Management
Monitoring and Controlling
ENGINEERING MANAGEMENT (GE 404)
Managing Project Work, Scope, Schedules, and Cost
Presentation transcript:

1 PROJECT MONITORING & CONTROL

2 Project Monitoring and Control Why do we monitor? What do we monitor? When to we monitor? How do we monitor?

3 Why do we monitor? Simply because we know that things don’t always go according to plan (no matter how much we prepare) To detect and react appropriately to deviations and changes to plans

4 What do we monitor ? Men (human resources) Machines Materials Money Space Time Tasks Quality/Technical Performance

5 What do we monitor ? Inputs Time Money Resources Material Usage Tasks Quality/Technical Performance Outputs  Progress  Costs  Job starts  Job completion Also - Monitor Changes (design spec) - Quality performance

6 When do we monitor?  End of the project  Continuously  Regularly  Logically  While there is still time to react  As soon as possible  At task completion  At pre-planned decision points (milestones)

7 Where do we monitor? At head office? At the site office? On the spot? Depends on situation and the ‘whats’

8 How do we monitor Through meetings with clients, parties involved in project (Contractor, supplier,etc.) For schedule – Update CPA, PERT Charts, Update Gantt Charts Using Earned Value Analysis Calculate Critical Ratios Milestones Reports Tests and inspections Delivery or staggered delivery PMIS (Project Management Info Sys) Updating

9 Meetings – Some monitoring issues What problems do you have and what is being done to correct them? What problems do you anticipate in the future? Do you need any resources you do not yet have? Do you need information you do not have yet? Do you know anything that will give you schedule difficulties? Any possibility your task will finish early/late? Will your task be completed under/over/on budget?

10 Project Control Cycle PLAN Specifications Project Schedule Project budget Resource plan Vendor contracts MONITOR Record status Report progress Report cost COMPARE Actual status against plan -Schedule -Cost ACTION Correct deviations from plan RE-PLAN as necessary

11 Project Control Control – process and activities needed to correct deviations from plan Control the triple constraints –time (schedule) –cost (budget, expenses, etc) –performance (specifications, testing results, etc.)

12 Techniques for control Earned Value Analysis Critical Ratio

13 Earned Value Analysis One way of measuring overall performance using an aggregate performance measure - earned value Earned value of work performed for those tasks in progress obtained by multiplying the estimated percent completion for each task by the planned cost for that task If total value of the work accomplished is in balance with the planned (baseline) cost, then top mgmt has no particular need for a detailed analysis of individual tasks Earned value concept – combines cost reporting & aggregate performance reporting into one comprehensive chart next page)

14 Earned Value Chart – basis for evaluating cost & performance to date

15 Earned Value Analysis - Variances 4 types of variances; time variance – subtract the actual time from the time scheduled for the value completed spending variance – actual cost less value completed schedule variance – value completed less the baseline plan total variance – sum of the latter two;

16 Earned Value Variance - Calculations Spending variance = actual cost – value completed + Schedule variance = value completed – baseline cost = Total variance = actual cost – baseline cost

17 EXAMPLE A project at day 70 exhibits an actual cost of RM 78,000, a scheduled cost of RM 84,000, and a value completed of RM 81,000. What are the total variance, spending variance, and schedule variance. Estimate the time variance. Day 70 RM Baseline – scheduled cost – 84,000 Actual cost – 78,000 Value completed – 81,000

18 Solution Spending variance = actual cost – value completed + Schedule variance = value completed – baseline cost = Total variance = actual cost – baseline cost Spending variance = 78,000 – 81,000 = -3,000 (Cost under run) Schedule variance = 81,000 – 84,000 = -3,000 (behind schedule) Total variance = 78,000 – 84,000 = -6,000 Estimated Time variance = Schedule variance/(slope of Scheduled cost) = -3,000/ [84,000/70 days] = days (behind schedule)

19 Critical ratio Sometimes, especially large projects, it may be worthwhile calculating a set of critical ratios for all project activities The critical ratio is actual progress x budgeted cost scheduled progressactual cost If ratio is 1 everything is probably on target The further away form 1 the ratio is, the more we may need to investigate

20 Critical ratio example Calculate the critical ratios for the following activities and indicate which are probably on target and need to be investigated. ActivityActual progress Scheduled Progress Budgeted Cost Actual cost Critical ratio (CR) A4 days 6040 B3 days2 days50 C2 days3 days3020 D1 day 2030 E2 days4 days25

21 Critical ratio example Can be on schedule and below budget (Act A) Why so good? Cutting corners? Can be behind schedule but below budget (Act C) Can be on budget but physical progress lagging (Act E) Can be on schedule but cost running higher than budget (Act D) On budget ahead of schedule (Act B)

22 Summary Need proper project monitoring and control mechanisms Tools available to help in monitoring and controlling activities There are human control and management aspects not covered here