LAV construction: Status and overview Matthew Moulson (Frascati) for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 25 May 2011 Overall.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
Date Instrument Systems ORNL SEQUOIA Overview Garrett Granroth (Instrument Scientist) David Vandergriff (Lead Engineer) ARCS/SEQUOIA IDT meeting March.
Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009.
AMS-02 tracker mechanics status of construction, assembly, integration Production: - Ladder integration - Installation on planes Inner tracker assembly:
Don Lynch 9/15/05 HBD Safety Review 1 Mechanical Design And Installation Hadron Blind Detector (HBD) Don Lynch.
LARG week 07/01 Paul Poffenberger University of Victoria Endcap Feedthrough Production at Victoria Status Summary.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
LBNL Test Cryostat Preliminary Design Review Tuning – Field Correction Soren Prestemon, Diego Arbelaez, Heng Pan, Scott Myers, Taekyung Ki.
Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 17 December 2013 LAV construction & installation status.
1 Stage 3 Peer Review October 26, 2006 T. Brown. 2 Field Period Assembly (FPA) 1.Make sure the requirements for the tooling is well defined (including.
LAV construction status Matthew Moulson (Frascati) NA62 Photon-Veto Working Group Meeting CERN, 27 May 2009.
LAV damage and repair – M. Moulson (Frascati) – Photon Veto WG – CERN – 5 April 2011 Damage to A3 during transport 2 10 blocks were broken during transport.
STF EP, VT commissioning by FNAL AES001 H. Hayano, KEK
Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.
News on mechanics Photon veto F. Raffaelli INFN – Sezione di Pisa CERN, January r 02 th, Status of tender Anti Status of the supporting.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
LAV construction: Status and overview Matthew Moulson (Frascati) for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 14 December 2010.
LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 23 May 2012 Notes on A8 transport 2 ShockLog malfunction: fresh batteries consumed.
Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting Liverpool, 28 August 2013 LAV construction & installation status.
Chiho Wang Duke University 1 TRT Barrel integration Status / Schedule Chiho Wang.
Matthew Moulson (Frascati) for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 17 July 2012 LAV construction & installation status.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 12 Jul 2011 LAV construction status: a snapshot 2 A1 Arrived at CERN 29 Jun.
Endcap Signal Feedthrough Overview Endcap Signal Feedthroughs are constructed and tested in Victoria by Victoria and TRIUMF staff. Each feedthrough unit.
EuCARD WP 7 – High Field Magnets Task – Radiation certification Status report EuCARD WP 7 – High Field Magnets Task 2 – Support studies Task
E.Guschin (INR) 21 November 2003Integration EDR PRS/SPD static envelop, assembly and installation Detector layout Static envelop along the beam Detector.
Status of Anti project. F. Raffaelli,A. Checchetti,C. Capoccia. INFN CERN, July 14 th, Status of the Anti construction test and schedule. -Status.
Lavs Issues Lav 12. Tube Planning future activities. Conclusions.
LMQXFA Cold Mass Assembly Antonios Vouris Fermilab February 3, 2016.
SBS Magnet and Support Status Robin Wines June 2013.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
LARP Collaboration Meeting Racetrack Coil Fabrication
1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009.
Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 4 June 2013 LAV construction & installation status.
A2-A5: The drawing has been revised (minor changes), the bid has been approved by INFN management and the invitation letter to the companies will be sent.
DOE-QRT Review 12 Feb2004 Joseph Rasson LHC Project Update1 Joseph Rasson LBNL DOE LHC Quarterly Status Meeting at FNAL 12 February 2004 US LHC ACCELERATOR.
Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 11 December 2012 LAV construction & installation status.
Chiho Wang ATLAS TRT Duke University CERN, Sep Barrel integration status.
Cloudland Instruments Hawkeye Mechanical Design Snapshot Compiled April 8th, 2016.
LAV construction status – M. Moulson (Frascati) – Photon Veto WG – Siena – 28 August 2012 A11 transport 2 Departure for CERN 24/07 with delivery originally.
LAV HV repair status – M. Moulson (Frascati) – Photon Veto WG – CERN – 09 February 2016 Vaqtec feedthoughs with PEEK base 2 Air side Vacuum side 3 prototypes.
PRELIMINARY VERSION Mechanical integration in the ESS Accelerator tunnel HENRY PRZYBILSKI.
6-Mar-2016 Dan Wenman | FC Installation 1 APA installation and integration at CERN Shipment of APAs APA handling Acceptance testing Tools needed.
Dan Cheng 8/27/2015 MQXFS1 Observations and Feedback from the Assembly Processes, Part II.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
Straw Working group Ferrara 4/9/2014. Outline Status and Plans Installation of Chambers 1-3 Chamber 4 Vacuum test SRB Readout, monitoring and software.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 5 January 2013 LAV construction & installation status.
Kitakami Side AHCAL Assembly or anywhere in any detector.
Cryostats for superconducting magnets
LAV HV repair plans Matthew Moulson
Installation of the T600 at Fermilab
ProtoDUNE – DSS Installation, Alignment and QA
Roadmap for triplet cryostats
BSS Prep work at CERN and Acceptance of Parts
HFM Test Station Main Cryostat
EHN1 Neutrino Installation Plans
Far Detector Activities Late 2017 – Early 2018
ActivRACTM 30P Mobilized Storage System
Cryomodule Assembly Plan
Senad Kudumovic Design engineer
SNS PPU Cryomodule Space Frame
SNS PPU Cryomodule Thermal Shield & MLI
SC1R Cold Box PDR Assembly Sequence
SNS PPU CRYOMODULE PDR Cleanroom Assembly Katherine Wilson
Presentation transcript:

LAV construction: Status and overview Matthew Moulson (Frascati) for the LAV Working Group NA62 Photon-Veto Working Group Meeting Brussels, 8 September 2010

LAV construction status – M. Moulson (Frascati) – Brussels – 8 Sep 2010 A2 finishing and handling 2 A2 rotated to horizontal 28 Jul and closed 29 Jul for final vacuum test Leak tested to 8 × 10 −10 mbar ℓ/s, P = 4 × 10 −5 mbar by evening of 30 Jul 28 Jul 03 Aug Rotated again to vertical 03 Aug for final packing ShockLog monitored throughout period of final handling

LAV construction status – M. Moulson (Frascati) – Brussels – 8 Sep 2010 A2 transport and handling 3 A2 shipped in vertical position with same packaging used for A1: mattress, foam inserts, thermal quilt Departure LNF:04 Aug 12:30 Arrival CERN T9:05 Aug 09:30 04 Aug 11:20 04 Aug 12:13 04 Aug 12:26

LAV construction status – M. Moulson (Frascati) – Brussels – 8 Sep 2010 Monitoring of A2 transport to CERN 4 03 Aug 07:00 03 Aug 21:00 04 Aug 11:00 05 Aug 00:00 05 Aug 14:00 02 Aug 17:00 transport Transport and handling monitored with ShockLog 298s 2 data recorders: # fastened to A2 1 event (1.8 g) during removal of flanges No events during entire period on the road! 1 event (2.2 g) during unloading of A2 from truck bed #20070 – bolted to truck bed Data useless - high-frequency vibration from motor saturated instrument Need to enable low-pass (40Hz?) hardware filter for future measurements A2 temperature during handling and transport

LAV construction status – M. Moulson (Frascati) – Brussels – 8 Sep 2010 A2 installation at T9 5 A2 unloaded and rotated 05 Aug, installed in T9 with final HV flange 09 Aug

LAV construction status – M. Moulson (Frascati) – Brussels – 8 Sep 2010 A2 storage at B Aug 11:00 30 Aug 16:30 30 Aug 22:00 31 Aug 03:30 31 Aug 09:30 A2 temperature during handling and transport 31 Aug 09:30 A2 removed from T9 to B Aug No packing before transport! Transported in horizontal position Maximum velocity 10 km/h No ShockLog events at all B185 storage area will be used for A3, A4… Need to monitor temperature? 16:20 16:50

LAV construction status – M. Moulson (Frascati) – Brussels – 8 Sep 2010 Block inventory and testing total in V. Palladino’s database 2095 inspected (incl. 412 top layer) 1382 not inspected (all from top layer) 225 bad 310 “on hold” criteria too strict? 1560 good 517 processed 1043 available New LabView interface for oven (see presentation by K. Schimert 14 Jul) Current and rate tests at 3 voltages integrated into production chain Will require: 1. Installation of new divider before status of block is known 2. Adapt oven to use new HV and signal connectors What to do about 1692 blocks of unknown status?

LAV construction status – M. Moulson (Frascati) – Brussels – 8 Sep 2010 Status of block/banana processing StationLayer 1Layer 2Layer 3Layer 4Layer 5Complete Block type A % A % A515 0% Bananas with long cables* Detail for A3415 cm cables 515 cm cables Old cables Total Type Type For A4: 17 blocks of type 13 tested; 24 reinforced, no dividers

LAV construction status – M. Moulson (Frascati) – Brussels – 8 Sep 2010 Inventory of other materials 9 Tyvek covers 1700 pre-cut sheets, good for all block types Banana plates 80 on-hand at LNF (done through A4) Banana hardware (brackets, columns) Supplies on hand at LNF to complete through A5 Voltage dividers on hand 179 with short cables, 61 with long cables Enough to finish A4 and start on A5 Of these, 116 dividers need to have cables soldered 300 additional dividers on fast order LED assemblies About 80 on hand at LNF (half of A3)

LAV construction status – M. Moulson (Frascati) – Brussels – 8 Sep 2010 A2 cable routing 10 Cable routing very messy at flanges Threaded holes exist to allow installation of additional support structures Solution under study Grille for cable routing is very crowded Height increased from 40 cm to 50 cm for A3 This uses all available space (considering clearance needed for block installation)

LAV construction status – M. Moulson (Frascati) – Brussels – 8 Sep 2010 A3 construction status 11 A3 vessel delivered and rotated into assembly position 06 Aug All needed blocks processed and bananas assembled As of 07 Sep, 7 of 8 bananas of layer 4 (type 14) installed Simultaneously processing blocks/bananas for A4 Goal is to ready A3 for shipping and finish A4 bananas by mid Oct A3 delivery, 06 Aug A3 rotated into position, 06 Aug

LAV construction status – M. Moulson (Frascati) – Brussels – 8 Sep 2010 A4 & A5 vessel status 12 Steel calendered and seam welded, flanges attached Successful preliminary vacuum and residual magnetic field tests Delivery expected 29 Sep (10 working days after original 15 Sep date) No substantial progress since F. Rafaelli’s 14 Jul presentation: Steel cut, edges bevelled, magnetic field mapped Delivery presumably by end Nov but date not yet specified A4 A5 A4 magnetic field mapping, 31 Aug A4 vacuum & leak test, 27 Aug

LAV construction status – M. Moulson (Frascati) – Brussels – 8 Sep 2010 Design and planning A6-A8, A11 13 Competitive bidding procedure (gara) currently open for vessels with technical specifications similar to A1-A5: Recall: A9, A10 have same dimensions as A11, but are made of stainless steel A12 has open geometry—design is totally different Costs considerably increase with size Flanges need to be made from single slab of steel—custom casting Increased transportation costs (wide load) Labor cost is relatively unchanged (same procedures, tools, etc.) Gara closes 15 Sep—result will be known by 21 Sep A6-A8 5 layers ∅ 259 cm A11 4 layers ∅ 299 cm

LAV construction status – M. Moulson (Frascati) – Brussels – 8 Sep 2010 Summary & timeline 14 A2 delivered to CERN for test beam at T9 on 05 Aug Currently in storage at B185 All transports smooth, no problems A3 vessel delivered to Frascati 06 Aug All blocks and bananas complete, 1 layer mounted Expect to finish by mid Oct A4 vessel under construction Expect delivery end Sep All bananas ready by mid Oct, can begin mounting when A3 ships A5 vessel delivery planned for end Nov