Update on X Band Klystron Modulator Installation.

Slides:



Advertisements
Similar presentations
11/27/2007ILC Power and Cooling VM Workshop Mike Neubauer 1 RF Power and Cooling Requirements Overview from “Main Linac Power and Cooling Information”
Advertisements

ILCTA-MDB RF Power Status 9/21/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power Meson Detector Building 3.9 GHz RF Power A0 Building September 21, 2006 [John.
Optical Manufacturing Solutions 1 Probe Assembly.
The pumps should be tightened about once a month. If a new pump is installed, the pump should be initially tightened and then re-torqued one week later.
Mar 13, Low-energy RHIC electron Cooler (LEReC) CRYOGENICS Mar 13, 2014.
Areal RF Station A. Vardanyan RF System The AREAL RF system will consist of 3 RF stations: Each RF station has a 1 klystron, and HV modulator,
Areal RF Station A. Vardanyan RF System The AREAL RF system will consist of 3 RF stations: Each RF station has a 1 klystron, and HV modulator,
Structure testing and RF tests stands Jan Kovermann CERN On behalf of the CLIC structure test team.
Observations and next works from the recent tests of the insertion tools of Mini-Drawers at CERN Roméo Bonnefoy and François Vazeille Tilecal Operation.
MICE Refurbishment of CERN RF equipment for MICE M. Vretenar, CERN AB/RF.
"AIR COOLER" Heat Exchanger
1 Operating Experience and Reliability Update on the 5 kW CW Klystrons at Jefferson Lab Richard Walker & Richard Nelson Jefferson Lab, Newport News VA.
Progress of the BEPCII Injection System Kang Wen.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.
Hydraulics For The Long Term
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
Front End Test Stand Klystron Commissioning Alan Letchford UKNF Plenary Meeting 22 nd April 2009.
GERDA collaborationmeeting, Ringberg castle Béla MajorovitsTG5 Review: Infrastructure on top of the tank1.
K. Alam, CLIC workshop, October 16-18, CLIC workshop, October 2007 Working group “ Two beam hardware and integration” Test module in the two.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
RF power & FPC status Eric Montesinos, CERN BE-RF on behalf of all people involved, great thanks to all of them !
CERN X-band Test-Stand CERN - CEA – PSI – SLAC High voltage modulator Klystron XL5 Directional coupler Circular waveguide  =50 mm SLED Pulse compressor.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
G.McMonagle, 8 th July 2011 CLIC Project Meeting X Band Stand Alone Power Source at CERN Stand Alone Power Source (SAPS) The story so far
PIP Update 3 September 26 th, L1 Future Plans  Installation is halted until further notice (plan for 2014 shutdown or when needed)  Substation.
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
Electrical & Control Power Supplies Trevor Hartnett.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Modulator and overmoded RF components status for the 12GHz Test Stand at CERN - RF meeting – 17/03/2010.
Baby MIND coil modules assembly the aluminium folded strip solution 1 Alexey, Philippe, Gabriella, Helder, Herman Baby Mind Magnet CERN June.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
Summary of progress towards CLIC goals and next steps for structure testing 6 th X-band collaboration workshop, April 18 th- 20 th 2012 Steffen Döbert,
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
EnEfficient RF Sources Workshop. June 2014 I. Syratchev X-band high RF power testing activity at CERN I.Syratchev.
12 GHz Stand alone power source at CERN G.McMonagle AB/RF.
12 GHz Stand alone power source. Provisional Klystron Parameters ParametersSpecificationsunitsObservations RF Frequency12 (11.4)GHz Peak RF power50 -75MW.
Direct Hot Water. What Cold Water System is Pictured? What hot Water System is Pictured?
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
Xbox and Structure testing news N. Catalan Lasheras, R. DeGiovanni, J. Giner-Navarro, G. Mcmonagle, I. Syratchev, B. Wooley, X. Wu
1 BNL LHC Hi-Lumi QXF Vertical Test Facility Status Update M. Anerella, H. Hocker, P. Joshi, P. Kovach, A. Marone March 28, 2016.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
DTL prototype summary and production sequence F.Grespan LNL _06_22 CDR.
Carlos A. Martins ESS – Accelerator Division - RF Electrical Power Systems June 2 th, 2014 Design, construction and measurement.
High Voltage modulators ESS developments Carlos A. Martins ESS Accelerator Division, RF electrical power systems.
Commercial high-power X-band experience: klystron/modulators, and waveguide vacuum flanges CLIC Workshop January 2016 G. McMonagle (on behalf of Xbox team)
WIR SCHAFFEN WISSEN – HEUTE FÜR MORGEN Steps towards beam commissioning: RF system group Paolo Craievich :: RF Section :: Paul Scherrer Institut SwissFEL.
Air condition installation
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
Franck PEAUGER – CEA SACLAY LCWS11 - Grenada 29 th September 2011 CEA SACLAY CLIC R&D Activities F. Peauger, A. Hamdi, M. Desmons, W. Farabolini, P. Girardot.
S A Griffiths CM42 June 2015 Electrical & Control.
Areal RF Station A. Vardanyan
ILC Power and Cooling VM Workshop
Cryomodule test stand at ESS site
CBETA Technical Review
Progress and Status of X Band Stand Alone Power Source (SAPS) at CERN
STATUS OF CIEMAT CONTRIBUTION TO CTF3 ( )
Francois and Lau EATM 17 July 2012
Dielectric Oil Installations
Complementary ISTC Projects #3888, 3889p
Cherrill Spencer, SLAC Member of ATF2 Magnet Team
on behalf of the RF group
Application of the moderate peak power (6 MW) X-band klystron’s cluster for the CLIC accelerating structures testing program. I. Syratchev.
352MHz Klystron Control for the 3MeV Linac test stand
Experience with X band klystrons and solid state modulators at CERN
General presentation about recent status of DRFS
IMP Cryomodule Assembly and Alignment
Status of RF at HZB: BESSY II, MLS, bERLinPro and BESSY VSR
Reader Swap out Guide.
STUB configuration Mats Pålsson
Presentation transcript:

Update on X Band Klystron Modulator Installation

Observations on certain issues raised with Scandinova during recent workshop at PSI Technical Specifications – Contractual issues, that were in the specification accepted by Scandinova that have not been met, but are in process of being resolved Quality Control – Some small issues – Adaptability of K2 basic design for different types of klystron Misinterpretation and ergonomics – Future technical specifications will need to be clearer and discussed before future contracts Miscellaneous Summary of these issues Plan of action to get modulator and klystron running

Technical Specifications The following points were stated in the technical specification that SN stated the would meet in the call for tender Rise / fall time of HV pulse, pulse width 2.3uS half height Scandinova accepted this specification and was one of the key elements to take award the contract. SN think now this is very technical challenging and may not arrive at this value. We have asked for a interlock to be integrated on the maximum pulse width. The fact that the pulse width during the tests at SLAC were larger is not an issue as a shorter pulse width will give a longer life expectancy for the tube

Technical Specifications (continued) Interlock on body interception, delta T and Flow rate of body needed No measurement possibility for either delta T or body water flow in modulator, this issue is being resolved by Scandinova and will be implemented on next visit

Quality control Water valve of solenoid circuit missing – Problem resolved by CERN Flow meter interlock missing – Will be resolved by Scandinova on next visit Leaking joints on oil pump – Solution to be implemented by Scandinova on next visit Some small pieces of burred metal found in tank when draining oil after dummy load tests, – Don't know where these came from was it in pulse Tx (cleanliness) Is there a tank deformation when klystron was put onto lid? – View ports were not flush to tank when we tried to put them back on after installing klystron, SN sais was like this in factor (this should have been resolved or at least have been notified to CEA) Deformation measurement will be made next time klystron is lifted from tank

Misinterpretation and Ergonomics Air tightness of tank was specified in specification – Not in K2 baseline design but XL5 tube different to Thales and higher oil level needed to cover tube ceramic – This means filling tank up to limit of lid, when oil expands and it seeps out of lid – Problem being resolved at the moment (details on later slide) Radiation shielding – SN provided lead shielding but was impossible to manipulate connections to klystron therefore not installed, maybe future tanks should be made bigger to implement shielding on walls of tank – Lead shielding being modified at CERN, should be finished next week

Miscellaneous We are worried about the non direct measurements of voltage and current of the klystron i.e. calibration – Current transformer on low side of pulse Tx, not a true indication of pulse shape in klystron due to stray capacitance – Voltage divider not directly on cathode of klystron (calibration) We also had a welding point on the water distribution that was not good, this was fixed at CERN Connectivity from Tx to klystron. We were not happy with the push in connectors decided to screw cables to sockets.. But the nuts were non metric ! Problem solved by drilling into the existing screws and tapping to M5

Klystron installation in modulator Oil was removed from tank after dummy load tests some very small metal pieces were noticed at the bottom of The tank. This worried our SLAC colleaguse

Summary We have only done a sing pulse at 40kV into klystron now waiting for some issues (as mentioned above) to be resolved before continuing the commissioning For future modulators based on K2 model some adaptability may be needed from SN – e.g. Bigger tank to allow for shielding and capacitive voltage divider directly on cathode – i.e. bigger footprint for modulator Clearer more precise specification needs to be made by purchaser clearly identifying what is required and what deviates from the basic K2 design

Plan of action All water connections have been modified including pipe work to allow CERN standard Pt100 temperature probes for body, collector and window (non compatibility between European and USA standards) Perspex screen installed to protect solenoid terminals Temporary cover for viewport with visualisation of oil level

Plan of action Before pulsing the lid of the tank on the transformer side must be raised by 4 cm to assure that the oil covers all klystron gun piece designed and manufactured delivered to CERN today Realignment of girder for crane will be done tomorrow (offset 5cm) company was not available until now due to LHC shutdown Installation of the shim plate to be done sometime in the next 2 weeks Dependant on how well the start up of CTF3 goes (manpower) and the availability of TS dep to retest crane

Plan of action Mid February, Scandinova will be present to continue commissioning of modulator – Installation of interlock for body power – Interlock testing – Initial adjustment of flat top of voltage pulse – RP measurements of installation End February – Start RF conditioning of existing network – 1,2, 3 weeks??? – Testing of RF interlocks etc

Plan of action March – Dismount waveguides – Dismount klystron – Lift pulse transformer to install final capacitive adjustment for flattop – Reinstall klystron connect to new waveguide network down to CTF2 (with or without pulse compressor?) – Bake-out – RF conditioning

Summary Optimistic estimate Installation of first x band structure some tme in May Conditional on many things