Technical report for ISOLDE INTC 19 May 2007 Mats Lindroos.

Slides:



Advertisements
Similar presentations
Operational aspects 2008 run ISCOOL Isolde workshop Nov 2008 Erwin Siesling.
Advertisements

Technical studies for the HIE- ISOLDE Frontend upgrade Jacobo Montaño Marie Curie Fellow; CATHI Project * The research project has been supported by a.
SM18 Vertical/Horizontal Test Setup LHC Crab Cavity Engineering Meeting Session: Cavity Cryostat Testing & Integration in SM18Cavity Cryostat Testing &
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
HIE-ISOLDE Design Study and the CATHI Project Richard Catherall EN-STI ISOLDE Technical Coordinator HIE-EBIS Workshop 16 th -17 th October CERN.
HIE-ISOLDE contribution packages M. Pasini BE/RF.
Enhancement of the Resonance Ionization Laser Ion Source (RILIS) at ISOLDE - Setting up a complementary all solid-state laser system Sebastian Rothe Gentner.
Accelerators for ADS March 2014 CERN Approach for a reliable cryogenic system T. Junquera (ACS) *Work supported by the EU, FP7 MAX contract number.
CERN NuPAC meeting Dec 2005 The future of ISOLDE: accelerated radioactive beams Peter Butler 1.HIE-ISOLDE 2.EURISOL.
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
Mats Lindroos INTC Agenda 09:00 Introduction by the Chairman, J. Äystö 09:05 Report by the ISOLDE Technical Coordinator, M. Lindroos 09:25 Report by the.
CRYOMODULES High Beta Low Beta Approved by CERN Research Board in December 2009.
UKNF OsC RAL – 31 st January 2011 UKNF - Status, high lights, plans J. Pozimski.
Status of REX and Commissioning with Beam Dr. Jose Alberto Rodriguez, BE-OP-PSB (167538)
Results of the argon beam test at Linac3 D. Küchler BE/ABP/HSL Including feedback from R. Scrivens and M. Bodendorfer.
Mid Term Review Meeting, 26 September 2012D. Lanaia1 * The research project has been supported by a Marie Curie Early Initial Training Network Fellowship.
Mats Lindroos ISOLDE Technical report INTC 14/2/2007 Mats Lindroos.
The Stripping Foil Test Stand in the Linac4 Transfer Line
HIE-ISOLDE Project Y. Kadi (EN-STI) On behalf of the HIE-ISOLDE Coordination team.
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
K.Hanke – PS/SPS Days – 19/01/06 K.Hanke - PS/SPS Days 19/01/06 Recommissioning Linac2/PSB/ISOLDE from CCC  remote operation from CCC  upgrades & changes.
Technical report for ISOLDE Mats Lindroos on behalf of the ISOLDE team.
PSD upgrade: concept and plans - Why the PSD upgrade is necessary? - Concept and status of the PSD temperature control - Concept of the PSD analog part.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
12th February 2010David Mcfarlane EN-MEF-ABA1. History of Booster The accelerator was built in The Proton Synchrotron Booster is the first, in the.
ISOLDE Technical Report Richard Catherall ISOLDE Technical Coordinator 50 th INTC meeting 1 st July 2015.
Overview of new high level software applications developed for the HIE- ISOLDE superconducting linac D.Lanaia*, M.A. Fraser, D. Voulot *The research project.
Commissioning of REX Jose Alberto Rodriguez, BE-OP-PSB (167538) on behalf of the ISOLDE operations team.
EUROnu Costing Workshop May 2011 Beta-Beam Costing Exercise Elena Wildner, CERN 25/05/11 1 EUROnu Costing Workshop, CERN May 2011.
HIE-ISOLDE Project: Planning & Resources Y. Kadi (EN-HDO) and the HIE-ISOLDE Project team.
Technical Report for the ISCC Meeting 18 th May 2009 R. Catherall/ M. Lindroos.
Status of the PSD upgrade - Status of the PSD cooling and temperature stabilization system - MAPD gain monitoring system - PSD readout upgrade F.Guber,
High power RF tests places at CERN O. Brunner, CERN 4th SPL Collaboration Meeting jointly with ESS.
Mats Lindroos REX, ISOLDE and off-line controls Mats Lindroos on behalf of the ISOLDE team.
Riccardo Raabe (IKS, KU Leuven) for the Collaboration INTC 01/02/2012 INTC-O-014 Storage ring facility at HIE-ISOLDE: Technical Design Report.
A. Herlert, CERN PH-IS ISOLDE scientific coordinator’s report INTC meeting, May 19, 2008 ISOLDE scientific coordinator’s report INTC meeting, May 19, 2008.
Slide 1 of 10Matthew Fraser – CI MEW Meeting, 25 th October 2010.
ESS Vacuum Systems TAC 6 November 2012 Peter Ladd Senior Vacuum Expert.
ISOLDE Technical Report Richard Catherall EN-STI-RBS ISOLDE Technical Coordinator 52 nd INTC meeting 3 rd February 2016.
ESS Vacuum Standardization
Safety - Lessons learnt from the design, commissioning and operation of the HIE-ISOLDE cryomodules Safety overview ESS 8 June 2016 AP.Bernardes/EN on behalf.
CV works in the non- LHC accelerator complex during 2008 and plans for 2009 ATOP days 2009.
Programme for the Physics Start-up Stable and radioactive beams Jose Alberto Rodriguez, BE-OP-PSB (167538)
18/March/2008OP-days S.Mataguez / O.Hans1 Hardware Problems in the PS complex LINAC 2 BOOSTER PS AD Thanks to all that helped and provided information,
HIE-ISOLDE Workshop: The Technical Aspects Target Area Infrastructure Ventilation 29 November 2013 Andrea Polato* - CERN EN-CV-PJ * The research project.
Halo Collimation of Protons and Heavy Ions in SIS-100.
HIE ISOLDE Linac Short Technical Description W. Venturini Delsolaro Material from: L. Alberty, J. Bauche, Y. Leclerq, R. Mompo, D. Valuch, D. Voulot, P.
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
Technical Report for ISOLDE
Consolidation and Upgrade of the LHC Experimental Vacuum Systems
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
RF operation of REX-ISOLDE
How to run ions in the future?
STFC Contributions to the FCC Study
Alexander Herlert, CERN (PH-SME-IS)
HIE-ISOLDE Project: Planning & Resources
ISOLDE Technical report for INTC 21/5/2007
V. Fedosseev, R. Losito AB/ATB/LPE ISCC, 31/10/2005
HIE-ISOLDE Status & Summary of HIE-ISOLDE SC
Technical Report ISCC Meeting 16th February 2009
Magdalena Kowalska, CERN PH-SME-IS
Technical report for ISOLDE INTC 19 May 2007
HIE-LINAC status report
Technical Report for ISOLDE
Report on HIE-ISOLDE Status
Mats Lindroos for The ISOLDE team
HIE-ISOLDE contribution packages
Technical report Mats Lindroos.
The HIE-ISOLDE Design Study and the CATHI Fellow Participation
Presentation transcript:

Technical report for ISOLDE INTC 19 May 2007 Mats Lindroos

Outline Shutdown work –Planning –Ventilation –Water cooling system for Front-Ends –Front-End 6 –REX-ISOLDE HIE-ISOLDE –Where are we? Mats Lindroos

Shutdown planning Mats Lindroos

Start-up period Mats Lindroos

5 Major changes for 2008 Release of activated air HRS GPS Radiation monitor PMVG170C showing higher levels compared to 2 previous years Proton beam current to GPS limited to 1µA (norm. 2µA)

Modification of Ventilation System In order to reduce the activated air emissions encountered during 2007, the ventilation system has been reversed and measures have been taken to improve the air- tightness of the area. Tests to be carried out over the next few weeks. GPS HRS GPS HRS Actual situation Modification

Target Cooling Water Panel Orphan Dependant on vacuum controls. The failure of one affects the other Difficult to access (inside primary zone) No spares Maintained by ST-CV Completely independent from vacuum sequence Easily accessible during operation. Spares available Easy to operate user interface

Before > < After

Aluminium oxide blocking pneumatic systems 9 ‘Meyrin’ compressed air Isolde facility Compressed air system: Broken filter inside one of the air dryer tanks

Low energy shutdown works: main projects * REXTRAP - exchanged insulators etc at internal structure Done. Some discharges when starting up, but conditioning helps. REXTRAP - enlarge the internal differential pumping diaphragms Partially done. Preliminary test show an efficiency >60% Followed up with dedicated radioactive ion deposition test, e.g. 42K * REXTRAP - adjust and consolidate the RF excitation electronics Done, but still not possible to avoid antiresonance for all masses. -> adjust the amplifier for the desired mass range -> wait for a new version in connection with the REXTRAP upgrade * REXTRAP - proposal for complete trap consolidation Awaiting AB management decision * REXEBIS – find the reason for the LHe filling blockage Inspected inside. No blockage found. * REXEBIS – identify the reason for large N 2 peaks Much time invested. Gate valve exchanged. Peaks smaller but still present.

REX linac shutdown works IHS cavity stability above 50kW Coupling loop dismounted and cleaned, checked cavity adaptation, loop gain… -> Problem not fully solved, still too many interruption due to reflected power Linac water cooling circuits consolidation New interlocks, replacement of damaged pipes, maintenance of IHS closed circuit Amplifier cavities and RF tubes cleaning Long time without maintenance, insufficient air filtration RF room ventilation Changed to a close circuit ventilation Unfortunately the cooling unit is not adapted to this mode of operation -> Need a new cooling unit Replacement of magnetic steerers A project has been started for the replacement of the linac steerers during shutdown

REX status The whole REX machine is up running (diffciult startup as always) Tricky 9 C(O) and 10 C(O) beams first experiment -> After some struggle 10 C beam could be accelerated Linac well setup – scaleable: - A beam of 10 C was delivered at 2.9MeV/u during the first run - Sstripping foils were used 10 C 3+ -> 10 C 6+ (80% efficiency / background free) 1. Test mass separation inside the trap Improve the REX decay analyses prog. + verify this with tests 2. Beam (cw and pulsed) from RFQ cooler into REX dedicated tests necessary (no time during the startup) 3. 35Ar/35Cl suppression postponed no time before the C(O) run after the run the target ion source broke 4. Emittance measurements for linac started 5. Injection of Minimono (1 + ECRIS) into REXTRAP Diploma student A. Gustafsson Present status Immediate development projects

FE6 and Off-line Vacuum equipment installed Extensive testing of beam optics Preparation for installation –Specifications for software and hardware under way Beam energy measurement device installed for the precise measurement (+/- 0.1V) of secondary beams. Rapid gas leak valve integrated into off line to simulate effusion processes through target and ion source systems

Upgrade of RILIS lasers at ISOLDE Two dye lasers were applied at 1 st step of excitation - x 2.2 More power could be delivered to HRS target at the 2 nd step of excitation Ga ion beam has been produced with the SSL Diode Pumped Solid State Nd:YAG Lasers as replacement of Copper Vapor Lasers: Green Beams nm Yellow Beams nm CVL Green Beams nm UV Beam nm IR Beam nm SSL kHz 8 10 kHz 46% 54% 46% Improvement of ionization efficiency by SSL : And CVLs are still available for runs …

Total all parts of project

HIE-ISOLDE: Where are we? External grant from Belgium –1 engineer post – Matteo –1.3 MCHF for R&D on SC linac Second grant from Belgium approved for both physics programme and SC linac construction for HIE-ISOLDE –2.7 MCHF (540 kCHF per year for 5 years) for the SC linac construction WP in EUCARD proposal for R&D on thin film techniques –1.5 MCHF in total budget (30% from EU) –500 kCHF for HIE-ISOLDE relevant items (30% external) –Partners should be: IPJ-Polen, CI, LNL-INFN, IN2P3-IPNO, DESY Proposal in the UK to finance SC linac development and construction RFQ cooler WP and RILIS WP financed and (almost) completed Statement of Interest for proposal in the US to develop new high intenity EBIS/T for HIE-ISOLDE, FRIB, HRIBF and ISAC-II –Support letter ISC and ISOLDE UK Phd Student and Post-doc starting at ISOLDE in July Pre-study of new remote handling system in Finland, Univ. of Tampere Discussions with CERN Mgt on CERN contribution.

HIE-ISOLDE: Where are we?

HIE-ISOLDE R&D status Work has started on the main work packages, namely Cavity RF design, cavity manufacturing, cryomodule design, cryogenic system design and beam dynamics. Preparatory work on other work packages has started, we are still in line for the delivery of the Technical Design Report by end High  QWR with beam port corrected for steering effect Sputtering chamber