Status of SRF Modules, LLRF, RF Amplifiers & Network

Slides:



Advertisements
Similar presentations
Stochastic cooling and 56 MHz SRF update for Run-14 W. Fischer 21 January 2014.
Advertisements

Overview of SMTF RF Systems Brian Chase. Overview Scope of RF Systems RF & LLRF Collaboration LLRF Specifications for SMTF Progress So Far Status of progress.
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Areal RF Station A. Vardanyan RF System The AREAL RF system will consist of 3 RF stations: Each RF station has a 1 klystron, and HV modulator,
Areal RF Station A. Vardanyan RF System The AREAL RF system will consist of 3 RF stations: Each RF station has a 1 klystron, and HV modulator,
Progress of the sub-harmonic bunching system (i.e. upgrading progress of BEPCII present bunching system) Pei Shilun for the SHBS team Accelerator center,
Progress and Plan for Superconducting RF Cavity RF Group.
ANL HWR Cryomodule Status Update 27 January 2015 Zachary Conway On behalf of the ANL Linac Development Group Argonne National Laboratory Physics Division.
Possible Assembly and Test of the Crab cryomodule in SM18 at CERN P. Maesen LHC Crab Cav meeting, 17 Sep’ 09 LHC-CC09Cryomodule Assembly & Test Stand.
SLHC-PP – WP7 Critical Components for Injector Upgrade Plasma Generator – CERN, DESY, STFC-RAL Linac4 2MHz RF source Thermal Modeling Gas Measurement and.
Status of 325MHz coupler S. Kazakov 11/29/ MHz coupler structure.
Superconducting Accelerating Cryo-Module Tests at DESY International Workshop on Linear Colliders 2010 (ECFA-CLIC-ILC Joint Meeting) Denis Kostin, MHF-SL,
SRF Results and Requirements Internal MLC Review Matthias Liepe1.
TDR Part 2: 3.3 Cavity Integration (10 pages) H. Hayano Baseline Design based on the meeting discussion.
R&D Status and Plan on The Cryostat N. Ohuchi, K. Tsuchiya, A. Terashima, H. Hisamatsu, M. Masuzawa, T. Okamura, H. Hayano 1.STF-Cryostat Design 2.Construction.
201 MHz NC RF Cavity R&D for Muon Cooling Channels
RF power & FPC status Eric Montesinos, CERN BE-RF on behalf of all people involved, great thanks to all of them !
Cavity status; recent KEK activities : Hayano (1) STF CM-1 cavities are; MHI-014: 3-rd VT:36MV/m (finished) MHI-015: 3-rd VT: > 18.4MV/m.
Internal Cryomodule Instrumentation ERL Main Linac Cryomodule 10/10/2015 Peter Quigley, MLC Design Review.
201 MHz Cavity Status and Test Plans at MTA MICE Collaboration Meeting at RAL, UK October 22 ~ 24, 2005 Derun Li Center for Beam Physics Lawrence Berkeley.
XFEL SRF Accelerating Module Prototypes Tests at DESY Fermilab Seminar, July 21st Denis Kostin, MHF-SL, DESY.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Sergey Belomestnykh SRF and RF systems.
Americas Region: T4CM Status and Plans H. Carter TD SRF Dev. Dept. July 14, 2006.
Test plan for SPL short cryomodule O. Brunner, W. Weingarten WW 1SPL cryo-module meeting 19 October 2010.
Americas Cavity Specification C.M. Ginsburg (Fermilab) On behalf of the Fermilab cavity crew October 20, 2010.
1 K.Jensch, D.Kostin, DESY - Cryomodule components List S1 – DESY parts DESY parts for the S1 Cavity-String.
Eric Montesinos - CERN - First SPL collaboration meeting - CERN December 11th 2008 First SPL collaboration meeting Experience with the LHC Main power Coupler.
MICE RF Cavity Measurements Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory July 8, 2010 Rutherford Appleton Laboratory, UK.
Krzysztof Czuba1 REFERENCE FREQUENCY DISTRIBUTION SYSTEM FOR THE TESLA TECHNOLOGY BASED PROJECTS Krzysztof Czuba Matthias Felber.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
Preparation procedure and RF processining of cERL-ML power coupler at KEK Hiroshi Sakai, Takaaki Furuya, Masato Sato, Kenji Shinoe, Kensei Umemori, Kazuhiro.
Power couplers Timergali Khabiboulline (FNAL) FNAL-LBNL meeting on NGLS April 13, 2012.
FLASH RF gun developments. Sven Pfeiffer for the LLRF team FEL Seminar Hamburg,
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
RF Module Update MICE Collaboration Meeting 44 Andrew Lambert Lawrence Berkeley National Laboratory March 30 th, 2016.
RFQ Installation Status 10/27/2015 October 27, 2015 Jim Steimel & Curtis Baffes.
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
1 IPN Orsay / Division Accélérateurs The Spoke cryomodule Vacuum aspects P. DUTHIL on behalf of the IPNO team ESS Lund February 19 th 2013.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
325 MHz Superconducting Spoke Cavity Coupler status. T. Khabiboulline Power Coupler design for Superconducting Spoke cavities. Originally.
Guillaume Olry on behalf the IPN Orsay SPIRAL2 team TTC Meeting – Milan, 28 Feb-3 March 2011.
Areal RF Station A. Vardanyan
Status of the M-ECCTD F. Peauger - P. Bosland
Tongming Huang (IHEP) On behalf of the power coupler working group
Cryomdoule Test Stand.
S1G Experiment Schedule Plan
He Plant, LN2 Systems and Commissioing
WP5 Elliptical cavities
ILC-SCRF Test Facilities considerations
Power Couplers, HOM Couplers and Tuners for the XFEL
Power coupler at DESY & for XFEL
TTC Topical Workshop - CW SRF, Cornell 12th – 14th June 2013
An X-band system for phase space linearisation on CLARA
Test plan of ESS HB elliptical cavity
12 GHz High Power RF components requirements for CEA activities
Test plan of ESS HB elliptical cavity
SNS Fundamental Power Coupler History
Wolfgang Anders, BESSY, Berlin
CEPC RF Power Sources System
IMP Cryomodule Assembly and Alignment
First High Power Test of the ESS Double Spoke Cavity package
An Optimal Procedure for RF Conditionning at the FREIA Laboratory
Cryomodule Assembly Plan
Prototype cryomodule development
Cryomodule ESS FAT & SAT SRF meetinG on 07/11/2017
System tests at CEA O. Piquet 19/03/2019
V. Veshcherevich Cornell University
SNS PPU CRYOMODULE PDR Cleanroom Assembly Katherine Wilson
Higher power couplers at Helmholtz-Zentrum Berlin
Presentation transcript:

Status of SRF Modules, LLRF, RF Amplifiers & Network Dr. Ozlem KARSLI Ankara University On behalf of TARLA Team

OUTLINE Superconducting Modules Buncher Cavities RF Amplifiers & Network LLRF Conclusion

SRF cavities 1&2 TARLA-Cavities 1 and 2 were treated according to the XFEL-recipe (major steps mentioned only): Main EP (110µm removal) 800 °C hydrogen degassing Tuning of pi-mode and field flatness to >98% Fine EP (40 µm removal) Control of pi-mode and field flatness (>98%) Welding of ring & bellow Welding of helium vessel Leak check of helium vessel The cavities are currently undergoing the final surface preparation procedures: High pressure rinsing 120 °C bake Afterwards the couplers and components for the horizontal tests at HoBiCaT will be assembled to the cavities. The achieved RF parameters are listed after the next slide.

SRF cavities 3&4 TARLA-Cavities 3 and 4 were treated according to the XFEL-recipe (major steps mentioned only): Main EP (110µm removal) 800 °C hydrogen degassing Tuning of pi-mode and field flatness to >98% Fine EP (40 µm removal) Control of pi-mode and field flatness (>98%) The next steps will be welding of ring and bellow and helium vessel integration. The achieved RF parameters are listed on the next slide.

SRF cavities Cavity Serial # Status Pi-mode Field flatness TARLA #1 RI-PL01 In He-vessel FMS installed 1297,354 MHz 96,2 % TARLA #2 RI-PL02 1297,304 MHz 95,3 % TARLA #3 RI-CAV003 1297,398 MHz 97,5 % TARLA #4 RI-CAV004 1297,394 MHz 98,1 % FMS = Field Measurement System – allows measurement of field distribution in a clean cavity Target frequency with FMS installed: 1297,380 MHz (+/- 0,1 MHz) For reference: Frequency change from FMS to cavity under vacuum (warm): about 390 kHz -> 1297,770 MHz Frequency change during cooldown: 2 MHz -> 1299,770 MHz Remaining 230 kHz are required for tuner pre-tension.

RF input couplers The RF input couplers were manufactured at RI according to the ELBE-design. The required antenna length of the couplers were determined by RF measurements on the SRF cavities with a coupler and different antenna tips (different length). The couplers were equipped with the proper antenna tip and two couplers were assembled to a test waveguide. After bake out and leak check, the coupler pairs were moved to HZDR for high power testing. The warm windows were also preassembled and sent to HZDR for high power testing.

RF input couplers - test setup 1 Each pair of RF input couplers (cold part, coaxial transition, door knob) was integrated to the resonant ring test facility at HZDR. The test waveguide was connected to a clean pump stand and the vacuum was monitored. The power was raised in pulsed mode to a peak power of about 50 kW and in CW mode to about 16 kW. The couplers were protected by interlocks on: Coupler temperature (inner conductor at cold part) Arc detection Vacuum To improve the cooling, the outer walls and the cooling channel (fro LN2) were cooled with forced air. Both coupler pairs passed the test, the results are summarized on the next slides.

RF input couplers - test setup 2 Two warm RF windows were assembled to the resonant ring test facility at HZDR. The waveguide H-bends between the RF windows was evacuated and the vacuum was monitored. The power was raised in pulsed mode to a peak power of about 55 kW and in CW mode to about 10 kW. The windows were protected by interlocks on: window temperature (IR sensor) Arc detection Vacuum Warm windows 3&4 did pass the test without problems, windows 1&2 have to be retested due to a small leakage at an O-ring joint.

RF input couplers - test results pulsed Coupler pair 1&2 was tested in pulsed mode to a peak power of about 55 kW, corresponding to an average power of about 20 kW (duty cycle 36%). The temperatures of the inner conductor raised to arround 110 deg C (air cooling only). Vacuum activity was still visible, but can be improved by better cleaning. Coupler pair 3&4 was tested in pulsed mode to a peak power of about 50 kW, corresponding to an average power of about 40 kW (duty cycle 80%). The temperatures of the inner conductor raised to arround 110 deg C (air cooling only). Vacuum activity was still visible, but less than coupler pair 1&2 due to improved cleaning and bake out procedure.

RF input couplers - test results CW 8 kW Coupler pair 1&2 was operated in CW mode at a power of 8 kW for 6 hours. The temperatures of the inner conductors stabilized at arround 65 / 80 deg C (air cooling only). The imbalance is due to a slight mismatch of the couplers to the testwaveguide at 1,3 GHz. The vacuum stabilized at arround 1,5E-7 mbar. Coupler pair 3&4 was operated in CW mode at a power of 8 kW for 8 hours. The temperatures of the inner conductors stabilized at arround 65 / 70 deg C (air cooling only). The vacuum stabilized at arround 2E-7 mbar.

RF input couplers - test results CW 16kW Coupler pair 1&2 was operated in CW mode at a power of 16 kW for about 20 minutes. The temperatures of the inner conductors raised up constantly until the interlock threshold was reached. Operation was stopped by the temperatures reaching 110 deg C (limit). The vacuum was changeable arround at 3E-7 mbar and became unstable with temperatures > 80 deg C. Coupler pair 3&4 was operated in CW mode at a power of 16 kW for 55 minutes. The temperatures of the inner conductors raised up constantly until the interlock threshold was reached. Operation was stopped by the temperatures reaching 110 deg C (limit). The vacuum was stable arround at 2,6E-7 mbar.

RF input couplers - test results summary Coupler pair 1&2 showed stable operation at 8 kW CW. The operation at 16 kW CW was sufficient. Due to a short pumping time (the test was started immediately after arrival of the parts at HZDR), the vacuum still shows activity which could be reduced by a longer pumping time. Coupler pair 3&4 showed stable operation at 8 kW and 16 kW in CW mode. The vacuum was stable in both operating conditions, as the vacuum was pumped some days before the test was started.

Cryostat The cryostats are pre-assembled and ready for the integration of the cavity string. The thermal shield was re-designed to a more reliable welding design and build in RI.

Beamtube components The beamtube components have been manufactured and are ready for further assembly after the horizontal test. Beam entrance / exit section. Between outer gate valve and thermal shield. Section between thermal shield and inner gate valve. Section between inner gate valve and cavity flange (diameter reduction with Taper)

Gate valves The inner and outer gate valves have been delivered and are on stock, ready for string assembly. The outer gate valves are VAT DN40CF all metal (series 48, right). The inner gate valves are VAT DN40CF Viton sealed (series 01, bottom picture), but were specially manufactured at VAT with a permeability of less than 1.05.

Tuner The tuner levers, the flexible joints and the respective tuner rings have been manufactured and are ready for assembly.

Instrumentation The instrumentation of the SRF modules has been procured. All sensors like helium- and nitrogen level sensors, temperature sensors, photo multipliers, IR-sensorsare on stock and ready for integration. The heaters for helium vessel, helium port are on stock. The RF pick up and HOM antenna feedthroughs have been delivered and are on stock. The feedthroughs for sensors, heaters and RF signals have been procured and the required flanges were produced, preassembled and leak tested (see picture).

RF System Each SC and NC cavities will be powered by a SSPA. Amplifiers and cavities will be controlled by RF controllers. All RF system is driven by a single master oscillator (MO), thus each individual RF system is synchronized.

Buncher Cavities SHB FB Buncher cavities were delivered in December 2014. The acceptance parameters of the cavities are shown in Tables. Factory Acceptance Tests of buncher cavities were performed between July 1-3, 2014. Factory Acceptance Tests was including; Resonance Frequency Unloaded Q Tuning range Leak rate SHB FB Resonance frequency 260 MHz Theoretical Q ≥ 4.000 Tuning range 200 kHz Leakage rate < 1E-9 mbar l/s Resonance frequency 1.3 GHz Theoretical Q ≥ 11.000 Tuning range 2.2 MHz Leakage rate < 1E-9 mbar l/s

RF Measurements of Buncher Cavities RF measurements for buncher cavities : Leak rate Resonance frequency Power, Gradient & Field measurement tests Data will be taken by a network analyzer for several discrete positions along several paths parallel to the cavity axis for gradient measurements. Sample test measurement setup

RF Measurements of Buncher Cavities The requirements for the tests generally are; Vector Network Analyzer, RF power amplifiers, Directional Coupler, Powermeter, Open or close loop RF controller (LLRF) Auxilaries, (coaxial cables, etc.).. The technical spec. documents of these equipments are ready, sent to the Purchasing Department of AU and waiting for the tender.

RF amplifiers for Bunchers Parameter SHB FB Input Power 0 dBm O dBm Central Frequency 260 MHz 1300 MHz RF Output Connector N type Output Power (@1 dB compression point, cw) 1.3 kW @ 1 dB 500 W @1 dB We completed the parameter set of power amplifiers for bunchers. We are planning to make the acceptance tests including; Linearity, Efficiency, Coupling/Parameter & Stability tests, etc.

High Power RF Amplifiers & RF Network Design Parameters were completed in 2013. The technical specification document as well as the contract were done and sent to the SigmaPhi. The agreement on the contract was completed, however the procurement is waiting for the budget. Additionally, RF network design works are completed, the documents relating the procurement are at the Purchasing Department of AU, waiting for the tender.

LLRF Figure shows the block diagram of TARLA MO that we purchase for backup. It includes oven controlled quartz crystals. Several signals locked each other can be obtainable with this MO. The jitter of available TARLA MO output for LLRF is <~8 fs.

LLRF DESY μTCA.4 LLRF for TARLA

μTCA.4 Chassis Layout for TARLA LLRF Configuration MTCA-12S-RF2 MicroTCA.4 Chassis of powerBridge Computer Vertriebs GmbH The 12 slot crate that will be in use at TARLA and the RF backplane which is introduced by μTCA.4 standard. μTCA.4 Chassis Layout for TARLA LLRF Configuration

LLRF Server Architecture and Control System Integration

Conclusion Technical specifications of LLRF is ready. In this procurement; Hardware procurement is TARLA scope. LLRF can be delivered about a year after signing the contract which means at the 4thQ of 2016 , however stable/steady operation can be completed in a year after the delivery. RF amplifiers (260 MHz – 1.3 kW for SHB, 1.3 GHz-500 W for FB, 1.3 GHz – 4 kW for SRF modules testing) will be delivered at most in 10 months after signing the contract. Expected delivery date is 3rdQ of 2016. RF network is completed and waiting for the tender. The budget has been waiting for high power RF amplifiers. 1st SRF module has been waiting in the first half of the 2016, depending on the horizontal test timing. Cryomodule tests can be started at 4thQ of 2016.