Criticality and Risk of Large Cascading Blackouts Ian Dobson PSerc, ECE Dept., University of Wisconsin, Madison, WI Benjamin A. Carreras Oak Ridge National.

Slides:



Advertisements
Similar presentations
NERC TPL Standard Issues TSS Meeting #146 Seattle, WA August 15-17, 2007 Chifong Thomas.
Advertisements

Marzieh Parandehgheibi
METHODOLOGY FOR IDENTIFYING NEAR-OPTIMAL INTERDICTION STRATEGIES FOR A POWER TRANSMISSION SYSTEM Vicki M. Bier, Eli Robert Gratz, Naraphorn J. Haphuriwat,
Preliminary Impacts of Wind Power Integration in the Hydro-Qubec System.
Framework for comparing power system reliability criteria Evelyn Heylen Prof. Geert Deconinck Prof. Dirk Van Hertem Durham Risk and Reliability modelling.
Reliability Software1 Reliability Software Minimum requirements & Best practices Frank Macedo - FERC Technical Conference July 14, 2004.
RISK INFORMED APPROACHES FOR PLANT LIFE MANAGEMENT: REGULATORY AND INDUSTRY PERSPECTIVES Björn Wahlström.
August 14, 2003 Blackout Final Report
1 Review of US Human Space Flight Plans Committee Evaluation Measures and Criteria for Humans Spaceflight Options 12 August 2009.
NRC Research on Digital System Reliability Modeling for Use in a PRA
BY THE NUMBERS Pennsylvania in FY 2012 $261 Million: NSF funds awarded 7 th : National ranking in NSF funds 82: NSF-funded institutions 1,137: NSF grants.
The Seminar is being held 11am to 12.30pm in Room 104 upstairs.
6/23/2015 Risk-Informed Process and Tools for Permitting Hydrogen Fueling Stations Jeffrey LaChance 1, Andrei Tchouvelev 2, and Jim Ohi 3 1 Sandia National.
SQM - 1DCS - ANULECTURE Software Quality Management Software Quality Management Processes V & V of Critical Software & Systems Ian Hirst.
Measuring the effectiveness of government IT systems Current ANAO initiatives to enhance IT Audit integration and support in delivering Audit outcomes.
Vulnerability Assessments and Adaptation to Climate Change Consultations on the Relationship between Climate and human rightsGeneva 22 October 2008 Festus.
Introduction To be an effective teacher it is essential to capture and maintain the attention of the student. Toward this end it is very helpful to find.
Introduction to Computer Technology
Electric Power Infrastructure: Status and Challenges for the Future Mark Lauby Director, Reliability Assessments and Performance Analysis.
Averting Disaster - Grid Reliability Issues and Standards National Energy Restructuring Conference April 1, 2004 Washington, DC.
Alexandra Savelieva, Sergey Avdoshin, PhD National Research University “Higher School of Economics” Alexandra Savelieva, Sergey Avdoshin, PhD National.
NREL is a national laboratory of the U.S. Department of Energy Office of Energy Efficiency and Renewable Energy operated by the Alliance for Sustainable.
System Operations Staffing Request Presented to the ERCOT Board Of Directors By Sam Jones, COO November 16, 2004.
Cascading Failure and Self-Organized Criticality in Electric Power System Blackouts Ian Dobson ECE, Univ. of Wisconsin David Newman Physics, Univ. of Alaska.
PROJECT NO PUCT STAFF WORKSHOP 11/19/14 Julia Harvey Kristi Denney Kevin Mathis Jasmin Thevaril.
Integration of Variable Generation Task Force Preliminary Conclusions and Actions.
Energy Industries of Ohio Southeast Energy-Water Interdependence Exercise Energy Assurance Program for the State of Ohio.
Roadmap for Real Time Control Transmission Reliability Program Peer Review Washington DC, 27 January 2004 Jeff Dagle, Pacific Northwest National Laboratory.
Page 0 Eastern Interconnection Phasor Demonstration Enhanced Wide-Area Visibility In the Eastern Interconnection for Reliability Management Transmission.
Peak RCCo Performance Metrics Draft –November 2013.
1 NEST New and emerging science and technology EUROPEAN COMMISSION - 6th Framework programme : Anticipating Scientific and Technological Needs.
CHECKPOINTS OF THE PROCESS Three sequences of project checkpoints are used to synchronize stakeholder expectations throughout the lifecycle: 1)Major milestones,
Government Procurement Simulation (GPSim) Overview.
Enhancing Reliability of the North American Transmission Grid Enhancing Reliability of the North American Transmission Grid Presented By Dejan J Sobajic.
Application and Implementation of State Estimator at Idaho Power Company S. Kincic and M. Papic.
Designing for Global Warming Orson P. Smith, PE, Ph.D. School of Engineering.
Overview of Real Time Grid Reliability Management Carl Imhoff Pacific Northwest National Laboratory January 27-29, 2004 Washington, D.C. Transmission Reliability.
©2004 PJMwww.pjm.com 1 PJM's Perspective on Reliability – Summer 2004 and Beyond Karl Pfirrmann President -- PJM Western Region FERC Summer Reliability.
Implementing Portfolio Management: Issues, Insights, and Answers? John I. Howell Portfolio Decisions, Inc. Roger N. Anderson Columbia Enterprise Systems.
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
1 Improving the Risk Management Capability of the Reliability and Maintainability Program An introduction to the philosophy behind the AIAA S-102 Performance-Based.
Initial evidence for self-organized criticality in blackouts Ben Carreras & Bruce Poole Oak Ridge National Lab David Newman Physics, U. of Alaska Ian Dobson.
Real Time Tools Outreach Carlos Martinez January 27-29, 2004 Washington, D.C. Transmission Reliability Research Review.
ENGR 107: Engineering Fundamentals Lecture 7: The Engineering Design Process: Making Design Decisions Using Tradeoff Analyses C. Schaefer September 29,
Engineering Design Process
Grid Reliability Metrics by Jim Dyer Electric Power Group, LLC January 29, 2004 Washington, DC Transmission Reliability Research Review.
Evaluate Phase Pertemuan Matakuliah: A0774/Information Technology Capital Budgeting Tahun: 2009.
IAEA International Atomic Energy Agency The Human and Organizational Part of Nuclear Safety Monica Haage – International Specialist on.
Impacts and Actions Resulting from the August 14, 2003 Blackout Minnesota Power Systems Conference November 2, 2003.
ECE 530 – Analysis Techniques for Large-Scale Electrical Systems Prof. Hao Zhu Special thanks to Dr. Kai Van Horn Dept. of Electrical and Computer Engineering.
Managed by UT-Battelle for the Department of Energy 1 United States Grid Security and Reliability Control in High Load Conditions Presented to Associate.
Safety of At-Reactor High-Density Storage of Fuel in Pools Steve Jones Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission International.
SOFTWARE TESTING AND QUALITY ASSURANCE. Software Testing.
Distributed Network Monitoring in the Wisconsin Advanced Internet Lab Paul Barford Computer Science Department University of Wisconsin – Madison Spring,
Criticality and Risk of Large Cascading Blackouts
GMD Research FERC Order No. 830 Research Work Plan Mark Olson, NERC
Lawrence Berkeley National Laboratory
ISO New England System R&D Needs
CASCADING FAILURE Ian Dobson ECE dept., University of Wisconsin USA
Transmission Planning in a Modern Market Environment
Benchmarking Quasi-Steady State Cascading Outage Analysis Methodologies IEEE Working Group on Understanding, Prediction, Mitigation and Restoration of.
Impacts and Actions Resulting from the August 14, 2003 Blackout
Cascading Failure Working Group of
Vicki M. Bier, Eli Robert Gratz, Naraphorn J
A Model of Power Transmission Disturbances in Simple Systems
ISTE Workshop Research Methods in Educational Technology
Architecture & System Performance
Implementing Portfolio Management: Issues, Insights, and Answers?
GMD Research FERC Order No. 830 Research Work Plan Mark Olson, NERC
Supplemental Project Planning Process Under Order 890 Within PJM
Presentation transcript:

Criticality and Risk of Large Cascading Blackouts Ian Dobson PSerc, ECE Dept., University of Wisconsin, Madison, WI Benjamin A. Carreras Oak Ridge National Laboratory, Oak Ridge, TN in collaboration with David E. Newman University of Alaska, Fairbanks, AK

Background Managing the risk of large blackouts is vital to the United States. Large blackouts typically involve complicated series of cascading rare events that are hard to anticipate in detail. We can now exploit the new models and ideas we have developed since 2001 within CERTS to address the risk of large blackouts caused by cascading failures from a global, complex systems perspective.

Project History FY01-02 Team: ORNL and PSERC (Wisconsin,Cornell) Budget: 100K per year FY03-04 Team: ORNL and PSERC (Wisconsin) Budget: 110K per year Close collaboration between national lab and universities LEVERAGE: Collaboration with University of Alaska Funding from NSF

Goal Contribute to transmission system reliability by Understanding large, cascading failure blackouts and providing tools for analyzing and monitoring their risk. In particular, the project will identify the threshold that leads to increased risk of cascading failure, express this threshold in terms of realistic power system parameters and develop monitoring tools and criteria to be applied in real power transmission systems.

Stakeholders and Impact DOE: risk analysis and tools to assist regulatory process Power industry: tools and operating criteria to help manage risk Engineering and science communities: problem formulation, insights, and analysis Business and the public: contribute to reliability, education Impact: Technical: 8 conference papers, 4 journal paper Public: Quotes and background provided to over a dozen newspaper articles; appeared on NPR radio and ABC Nightline. Project research results featured in Nature, National Post, Energia, and SIAM News.

NERC blackout data shows power tail Large blackouts more likely than expected Conventional risk analysis tools do not apply; new approaches needed Consistent with complex system near criticality Large blackouts are rare, but have significant risk

OPA Dynamical Model OPA is a power systems blackout model including cascading failure and self-organizing dynamics transmission system modeled with DC load flow and LP dispatch random initial disturbances and probabilistic cascading line outages and overloads underlying load growth + load variations engineering responses to blackouts: upgrade lines involved in blackouts; upgrade generation; “blackouts cause reliability”

Critical loading: threshold for cascading failure Mean blackout size sharply increases at critical loading; increased risk of cascading failure.

OPA can match NERC data probability blackout size (August 14 blackout is consistent with this power tail)

Significance of OPA Existence of critical loading with increased risk of cascading failure Engineering and economic forces can self-organize to near criticality Consistent with NERC data Sensible mitigation methods can reduce frequency of small blackouts while increasing frequency of large blackouts. Need to jointly manage both small and large blackout risk. ongoing and future work on OPA: Test bed for monitoring and understanding criticality and risk Improve power system and engineering/economic modeling

CASCADE model Probabilistic model of loading-dependent cascading failure. Captures salient features of cascading failure in an analytically tractable form. CASCADE shows a critical threshold loading with power tails, sharp increase in mean failure size, and an increased risk of cascading failure. Approximations to CASCADE give insights into failure propagation and criticality.

Current work Study OPA and CASCADE to gain a deeper understanding of the critical loading, the parameters controlling it and to monitor cascading failure propagation. Key idea: approximations to CASCADE suggest that failure propagation is governed by a parameter =1 gives criticality < safety margin < 1 gives reduced risk of cascading failure Current work aims to define and measure in OPA

Path to a practical monitoring tool to manage cascading failure risk Use OPA to thoroughly understand the critical loading threshold that causes increased risk of cascading failure. Test and refine metrics for monitoring closeness to criticality such as – Failure propagation parameter – Total load transfer for a failing line: where M is the fraction of line overload. – Loading margin to ∆L to critical loading Determine the secure conditions of operation. How close to criticality can one operate?

Path to a practical monitoring tool to manage cascading failure risk Use previous results to develop criteria and measurements applicable to real system. Explore the development of software tools to monitor power system security with respect to large cascading failures. First test these tools in simulated operation to assess their capabilities and limitations. Implement the tools and criteria to monitor power system status, and risk trade-offs and do “what-if” analysis. We will pursue collaborations within CERTS to develop these practical tools.

Summary Transmission reliability requires all aspects of cascading failure to be understood and appropriate criteria and tools to be developed. The sole use of the deterministic n-1 criterion is not enough. We need to find out “where is the edge for increased risk of cascading failure?” and need to manage risk tradeoffs. Our approach is global and top-down and is complementary to detailed analysis of particular blackouts. Our approach aims to provide practical tools and criteria for monitoring closeness to an increased risk of cascading failure.