Wednesday 24.11. ● 02h04: Stable beams #1514. 121b x 121b. – Peak luminosity 1.2e25 cm-2 s-1 ● 08h32: Beams dumped on request. – Length=6h28. Rampdown.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Feedback on phase adjustment with BPTX Using scope and LHCb BPIM boards to readout BPTX signal BPIM only used for triggering, phase measurements (BPTX1-BC1,
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
PROFIBUS controller problem (SEU) on cryo valve on DFBMH (600 A circuit RQ6.L7B1/2). Loss of cryo maintain ==> Beam dump. End of fill #1975 after ~2.5.
Hydrogen Recombination Time (µs) RF Envelope (V) Here So We get Calculated from # of protons per bunch Calculated from energy loss (voltage drop) in the.
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
LHC Wed 16 Sept 2015 Struggling with cryo o-night Tuesday - Wednesday 07:11 Injecting again 09:00 Dump on injection of train of 144 bunches, losses IP7.
First measurements of longitudinal impedance and single-bunch effects in LHC E. Shaposhnikova for BE/RF Thanks: P. Baudrenghien, A. Butterworth, T. Bohl,
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
07-JUL-2003LEADE / JW1 Satellite bunches in the LHC Satellite “definition” Satellite luminosity Satellite detection & tolerances J. Wenninger AB/OP.
Thursday 21/4 07:30: End of fill #1727. Beam dumped. ALICE compensator magnet fault. Delivered ~6.7 pb -1 in 7.5 h. 11:30 Stable beam # bunches/beam.
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
“we believe the reason why the first bunch is more intense than the following 3 is that it's on that one that the SPS RF loops are locked” Philippe & Django.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
LHC progress Report LHCC Wednesday 23 rd March 2011.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
00:15: Stable beams fill 1883, 1.1E33 cm-2s-1.  Seems the 144 bunches beam 1 doe not fit properly on the injection kicker waveform. Systematically the.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
Pevatron status Sunday 29 th November 2015 Coordination: John Jowett, Mike Lamont, Jan Uythoven Access Loss maps Physics.
From yesterday LHC status Wednesday 26 th Welcome Verena back on shift 07:08 Access in PM85 for piquet EPC (O.Fournier).  Fuse on RD2.R8 circuit.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
:00 meetingEBH 11 Saturday :00 meetingEBH 2  7:58 Fill 2483 (264 bunches) dumped by reference orbit set to zero in.
Lumi scan limits checked (in preparation for next fill VdM scans).  Trims of up to 150 um per beam in IP1 & IP2 both planes both beams were done (IP5.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
Injection issues overnight 10:50 Access  QPS & EPC  Vacuum leak SPS – magnet to be replaced Monday – cycling for FT and LHC only over the weekend 12:15.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
(Towards a) Luminosity model for LHC and HL-LHC F. Antoniou, M. Hostettler, Y. Papaphilippou, G. Papotti Acknowledgements: Beam-Beam and Luminosity studies.
Tuesday 3 rd October STABLE BEAMS until 12:25 when we switched to ADJUST for a EOF test for Tobias  dump B2 first and then B1.  Dump at EOF test because.
LHC Status Fri Morning 3-June
Floating MD week 28 summary
Monday – Morning L. Drosdal: Injection line TI8: IQC threshold for BPM H from 2mm to 2.5mm to avoid unnecessary latches due to variations.
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Sunday 28 Nov. 00h00: Stable beams # x 121 b. Peak lumi 2.0e e25 cm-2 s-1. 09h52: Dump fill # delivered 440 (mb)-1. RCBCH8.L5B1 trip.
Longitudinal beam parameters and stability
Friday 15th June 01:11 Injection.
Wednesday September 14th
Summary Week 47 + Start Week 48
Thursday 25/11/10 & Night Work on: 16:15 Inject fill #1520
Tuesday Nov 16th Fill 1492 into physics around 07.30
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Summary of Week 11: 14 – 21 March
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Tuesday Fill 1494 dumped by operations at (~ 0.25 ub-1 in ~6.5 h): LSS6 BPM interlock test 13:00 Fill 1495 dumped by RF dump (cavity quench) 14:00-17:30.
Friday 31st August & night
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Friday :00 machine setup for luminosity run. Better b-to-b stability from injectors. 01:58 stable run with 228 bunches 11:00 luminosity leveling.
Saturday – Morning 7:36 beams dumped
Tuesday 9th November 10:02 Fill beams dumped
Summary Thursday h21: Stable beams fill #1303.
Thursday morning 7:20 – 12:30 faults of BLM sanity check, RQX.L8 QPS trip and iris scanner in UJ47. Access: Pt 8 for ELQA on RQX.L8 (The voltage.
Thursday Fill 1364 (24 bunch) dumped at 07h
Saturday Nov Stop proton operation. Switch back to ions
Tue/Wed 12/ :00 Probe beam back again
Monday :00 – 15:00 : Stable beams 15:30 : Recover…
Wednesday 16th May 03:05 beam dump, RF fault crowbar problem on module M1B2 06:09 Another crowbar at injection. Access for RF; problem Beam Imminent Warning.
Fri :52 Stable beams fill #2536
Thursday 30th September De-bunching test
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Tuesday
Daniel, Gianluca and Belen (for the Collimator team)
Saturday Morning used to complete the loss maps and asynch dumps (with RPs). All loss maps OK (B. Salvachua), but the off-p cleaning for B1 (Lead) was.
Wednesday Following the struggle with the vacuum in IR2 over the night, drop intensity to 1.2E11/bunch. Fill first B1 – pretty quiet – then B2 – quite.
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Wednesday ● 02h04: Stable beams # b x 121b. – Peak luminosity 1.2e25 cm-2 s-1 ● 08h32: Beams dumped on request. – Length=6h28. Rampdown and precycle. ● 09h41: Injection. – Energy error (0.8%) from SPS suspected  OK – Emittances ~ 4 um, except B2V: 11 um ● 12h40: Start ramp. ● 14h01: Stable beams # b x 121b. – Turn-around: 5h29. – Peak luminosity 1.2e25 cm-2 s-1 ● 17h01: Beams dumped on request. – Length=3h00. Rampdown and precycle. 8:30 meeting 1

Fill :30 meeting 2

BCT Comparison 8:30 meeting 3 First plot shows a summary of fill 1515 injection. We see again the same thing, i.e. good agreement between DC and fast in the beginning, then some divergence building. This time, fast BCT sees around 6.5% (resp 2.5%) less than DC for beam 1 (resp beam 2).

Long. Density Monitor 8:30 meeting 4 Longitudinal density monitor = LDM (BI Resp: E. Bravin, A. Jeff) measurement integrated over 50 mn (from 15h46 to 16h36) during stable beam. We have a small residual phase shift, the last pulse on the right side is in fact the first bunch. We see that bunch peak is around counts.

BCT Same Time Window 8:30 meeting 5 BCT data during this time window. We see that the difference between the 2 BCTs remained stable to 6.5% and 2.5%.

Zoom Before Bunch 1  Ghost Bunches 8:30 meeting 6 zoom just before bunch 1 (ie the last one on the previous plot). We see there 'islands' of ions. These islands are separated by 2.5 ns. Their peak is around 30 (40-estimated noise baseline), i.e time less that real bunch peak.

Bunch in the Middle 8:30 meeting 7 zoom before a bunch in the middle (around us 50s). We see also there populated islands every 2.5 ns with peak around 30. Some of these beeing even more populated (~500 less than real bunch)

Last Bunch 8:30 meeting 8 surround of one of the last bunch injected. We see there no clear 400 MHz structure with an average level around 10 which is our estimated noise.

Abort Gap 8:30 meeting 9 zoom in the middle of the abort gap. Again there, mainly noise.

Ghost Bunches? 8:30 meeting 10 these 'islands' wanish but go quite far away when they exit. A simple calculation shows that we would need 2500 * = 60 such islands (at 40 peak) around each bunch to justify the 2.5% droop of the fast BCT with respect to the DC. This does not look so impossible.

Jean-Jacques Gras ● If we trust BCT measurements, a possible scenario could be: – ions escape slowly around the bunches during injection. The more bunch stays at injection, the more these ions spread. – after some time, some ions escape our 25 ns integration window. This explains that our fast BCT stay in line with DC for a while and then diverge (the cumulated escaped ions are bellow our noise threshold to be taken into account in the neighboring buckets). – finally, the situation seems to 'freeze' after ramping. i.e the difference between DC and fast do not increase anymore during stable beam. ● All this has to be analysed more carefuly but, unfortunatly, LDM is today only available on B2 and top energy for ions. This nice tool should be available on both beams next start-up with the protons. 8:30 meeting 11

Wednesday ● 17h01: Beams dumped on request. – Length=3h00. – Rampdown and precycle. ● 18h04: Injection. Correction injection oscillations. ● 18h40: Trip much of sector 81. Glitch on temperature sensor on RSS.A81.B1 (which is already superlock!). ● 19h56: Injection. ● 21h04: Start ramp. ● 22h03: Stable beams # b x 121b. – Turn-around: 3h46 (1h16 subtracted for S8 trip). – Peak luminosity 1.3e25 cm-2 s-1 ● 22h50: Lost QPS-OK on RCS.A45B1. 8:30 meeting 12

Yesterday Fills 8:30 meeting 13

Yesterday Fills 8:30 meeting 14

Something Wrong Here 8:30 meeting 15

Thursday ● 03h34: Beams dumped on request. – Length=5h31. Rampdown and precycle. ● 04h20: Injection. – Losses in SPS flat bottom reduced. – Now losses at acceleration had increased and source went down. – Once again lower bunch intensity ● 05h54: Start ramp. ● 06h58: Stable beams # b x 121b. – Turn-around: 3h24. – Peak luminosity 1.0e25 cm-2 s-1 ● 07h16: CMS sees cogging problem. Other experiments fine. Suspect threshold effect on BPTX signal (low bunch intensity). ● 08h06: Beam dump: Q9.R2  noise on long cables (seen that before). 8:30 meeting 16

Today 8:30 meeting 17

Today 8:30 meeting 18

Peak Lumi (ATLAS) 8:30 meeting 19

Integrated Lumi: Approaching 4 ub-1 8:30 meeting 20

Ahead ● Must now sort out injector intensity and transmission: change ion source, … ● Soon better to keep LHC beam than to refill (intensity from injectors dropping faster than the intensity of stored LHC beam)  refill does not pay off in luminosity ● Ahead: More stable beams ● See whether 2e25 cm-2 s-1 can be recovered. 8:30 meeting 21