Sonoma County Community College District Santa Rosa Junior College Educational/Facilities Master Plan Progress Report: October 2002 M AAS C OMPANIES
Overview 40% Through the Educational Planning Effort 20% Through the Facilities Planning Effort Progress and Findings to Date Parallel Paths: Educational Plan Component Facilities Component Previews for the Future M AAS C OMPANIES
Educational Master Plan Component M AAS C OMPANIES
Key Educational Planning Elements M AAS C OMPANIES Enrollment Generation of WSCH Curriculum Health Prospects for Growth Possible Potholes
Enrollment M AAS C OMPANIES
WSCH M AAS C OMPANIES
Credit WSCH Generation M AAS C OMPANIES
Non Credit WSCH Generation M AAS C OMPANIES
Credit/Non Credit WSCH Breakdown M AAS C OMPANIES
Santa Rosa Curriculum Key Elements M AAS C OMPANIES
Santa Rosa Curriculum Overview M AAS C OMPANIES
Petaluma/TA Curriculum Key Elements M AAS C OMPANIES
Petaluma/TA Curriculum Overview M AAS C OMPANIES
WSCH Per Enrollment M AAS C OMPANIES
Key Findings From Curriculum Analysis M AAS C OMPANIES 82.5% of all District generated WSCH is on SR Campus 11.5% of all District generated WSCH is at Petaluma/TA 97% of WSCH at SR & Petaluma/TA is “credit” WSCH Most all of the District’s non-credit WSCH (83.8%) is generated via the SR Off-Campus Program
Key Findings From Curriculum Analysis M AAS C OMPANIES Each semester 3,500 to 4,000 students attend multiple Campuses/Centers and/or are otherwise duplicated “enrollments” Credit WSCH per enrollment is greater than initially projected at SR and lower than initially projected at Petaluma/TA WSCH per FTEF needs to be addressed due to impact on facilities planning
Previews for the Future M AAS C OMPANIES Where will the District grow? How will the District grow? Key Growth Factors Challenges
Growth in the College Environment M AAS C OMPANIES
Enrollment/WSCH Forecast M AAS C OMPANIES From: 31,000 Students To: 60,000 Students From: 267,900 WSCH To: 515,000 WSCH
Facility Efficiency & Capacity Load Ratios M AAS C OMPANIES
Capacity Load Ratios M AAS C OMPANIES
Facilities Planning Component M AAS C OMPANIES
Facilities Planning Activities M AAS C OMPANIES Discussion with the President and Component Administrators Collection of Data for Review (on-going) Initial On-Site Facilities Assessments Preliminary CAD Mapping On-Campus Interviews
Facilities Planning Activities M AAS C OMPANIES Meetings with… Board Facilities Committee Academic Affairs Council Student Services Council TLCD Architecture Walker Parking Consultants City Schools Brelje and Race 3DI
Initial Facilities Assessments M AAS C OMPANIES Santa Rosa Junior College Main Campus Petaluma Campus
Initial Recommendations M AAS C OMPANIES Pursue Joint-Use Facilities with City Schools Pursue and Finalize the Purchase of Additional Land for the Petaluma Campus Re-visit the Scope of Work for the Plover FPP Obtain Additional Engineering Studies and Survey Data Review the Procedure for Space Inventory Reporting Maximize Scheduled Maintenance Proposals
Santa Rosa Junior College Educational/Facilities Master Plan A blueprint for action that is sufficiently flexible to accommodate changes that will occur. The Future of Success M AAS C OMPANIES
Michael Maas Ron Wigginton Ann Kennedy Ken Cereghino Joyce Black Kris Fox Hugh Brownlee October 3, 2002 M AAS C OMPANIES Project Team