Interstate 15 North Phase 4 9/01/2015 VE Class. Background: I-15 North Environmental Document, Purpose & Project Elements I-15 North Environmental Assessment.

Slides:



Advertisements
Similar presentations
St. Anthony Falls Bridge Replacement Jon Chiglo, P.E., Project Manager.
Advertisements

Project Development Process (PDP) Structures. PDP – Three Project Levels Major Project ~ 14 Steps Major Project ~ 14 Steps Minor Project ~ 10 Steps Minor.
Project Description and Needs Lincoln Way Widening Addition of a center-turn lane and safety improvements to the grade and horizontal alignment. Needs.
Great Western Corridor Feasibility Study
I-96 Reconstruction/Bridge Repair Project City of Livonia and Redford Township Wayne County May 10, 2013 Association of the Council of Western Wayne Yankee.
Alachua County Board of County Commissioners NW 16 th AVENUE / NW 23 rd AVENUE FROM NW 57 th Terrace to NW 13 th Street.
City of Omak Central Avenue Bridge Replacement Project Prepared by Highlands Associates Photos by FlyBy Photos.
1 Loop 303 US 60 to Happy Valley Parkway Arizona Department of Transportation February 26, 2014.
County of Fairfax, Virginia Sully District Council Meeting November 19, 2014.
10 miles on I-80 from Robb Dr. to Vista Blvd. Reconstruction through congested downtown Installation of new 10-mile ITS system Preserved Operational Capacity.
New I-65 Interchange at Worthsville Road Welcome!.
JANUARY 9, 2002 SCAJAQUADA CORRIDOR STUDY Grant Street to Parkside Avenue City of Buffalo Fisher Associates Joseph Passonneau & Partners In Association.
South Side Red River Bridge Corridor Study Phase III Preliminary Geotechnical Study Phase IV New Alignment Alternatives Evaluation.
Environmental Assessment Public Meeting
Welcome to Pinal County. Greg Stanley Pinal County Public Works AACE Regional Conference Oct 1-3, 2008 The Three C’s of Hunt Highway.
Transportation Study for City of Bluffdale Porter Rockwell Boulevard is a planned, designed and partially built major arterial road that connects Mountain.
Public Location/Design Hearings November 17, 2010 Laughlin, Nevada November 18, 2010 Bullhead City, Arizona.
I-65 Added Travel Lanes Project in Tippecanoe County
2014 CONSTRUCTION ESTIMATES Estimates Estimates 3 Point of the illustration? Document your assumptions.
4 TH STREET BRIDGE Pueblo, Colorado December 2006 Project Overview.
Public Information Meeting Rehabilitation of Bridge No Flat Rock Hill Road over I-95 Old Lyme, Connecticut Rehabilitation of Bridge No Flat.
Chapter 2b Foundations Shallow & Deep Foundations.
Environmental Assessment Public Information Meeting – September 2010 Realignment of a Portion of a Utah Lake Drainage Basin Water Delivery System (ULS)
US 1 COLLEGE PARK – SEGMENT 1 FROM COLLEGE AVE/REGENTS DRIVE TO MD 193 (UNIVERSITY BLVD) Presentation to College Park City Council August 5,
Alameda Creek Bridge Replacement Scoping Meeting March 4, 2014.
Nick Johnson, PE Senior Project Manager October 1, 2012.
County of Fairfax, Virginia Department of Transportation Richmond Highway Transit Center Feasibility Study Briefing with the Fairfax County Transportation.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
Washington State Transportation Commission March 20, 2007 Jeff Monsen, PE Intergovernmental Policy Manager.
ILLINOIS ROUTE 23 (LaSalle St.) DOWNTOWN RE-ALIGNMENT December 2, 2008.
WELCOME! July 31, 2012 ODOT District July 31, 2012 PURPOSE OF TONIGHT’S MEETING Introduce the project –Reconstruct I-75.
Public Hearing PROPOSED HIGHWAY IMPROVEMENTS I-95 DEFENSE ACCESS ROADS RAMPS TO THE ENGINEER PROVING GROUND Fort Belvoir, Virginia AUGUST 20, 2008.
Introduction Session 01 Matakuliah: S0753 – Teknik Jalan Raya Tahun: 2009.
Presentation Outline  Recommendation  Project Background  Public Involvement  Proposed Design  Citizen Comments/Questions  Summary and Recommendation.
U.S. 150 / S.R. 56 Road Reconstruction Project in Paoli, Orange County Thursday, August 25, :00pm Presentation Orange County Community Center 1075.
Oregon Transportation Commission October 14, 2015 OR 99 Rogue Valley Corridor Plan.
I-95 Access Study Fredericksburg Area Project Status Update February 12, 2010.
USA Parkway Project Welcome Public Information Meeting to the
D.d. delivers district department of transportation d.d. delivers FAISAL HAMEED RONALDO T. NICHOLSON. P.E. Innovative Project Delivery Processes Innovative.
County of Fairfax, Virginia Department of Transportation Fairfax County Parkway Corridor Study Board of Supervisors Transportation Committee December 1,
Design Manager: Chris Thomas CEAL July 17, Interstate 8 (I-8) to Interstate 5 (I-5) Connector Widening and Auxiliary Lane Project.
COUNTY ROAD 517 Improvements from State Highway 172 to Howe Drive DECEMBER 16, 2015 At Tribal Multipurpose Facility.
U.S. 20 Intersection Improvement Project at Waverly Road Porter Town Hall Thursday, August 13, 2015.
Geometric Design: General Concept CE331 Transportation Engineering.
1 MD 5 (Point Lookout Road) Leonardtown (Phase 1) Intersection Reconstruction At Abell and Moakley Streets Informational Meeting January 19, 2016.
Major Project Scoping Committee.  Two previous studies to develop improvements for the I-35W Corridor ◦ Project Limits were from 42 nd to I-94 ◦ Project.
Secondary & Cumulative Effects Analysis Training Program Module 1: How to Determine Which Resources Should be Considered in a SCEA How to identify what.
Waterdown Road Corridor Class Environmental Assessment (Phase 3 & 4) Community Services Committee May 9, 2012.
I-75 Ramp Widening Project Scope of Project – Safety Project to Widen I-75 NB Exit Ramp (Ramp A) and I-75 SB Exit Ramp (Ramp C) at the I-75/US 25W Interchange.
Iron Range Tourism Bureau April 25, 2013 Hwy 53 Update.
PAC Meeting July 2, Agenda  Introductions and thanks  Project to date  Next steps  Questions.
Brookeville Bypass Final Design Presentation Initech May 6, 2004.
All information presented is preliminary and subject to revision I-515 Alternatives Development Study Public Information Meeting March 31, 2016 Welcome.
County Road 19(Manning Road) & County Road 22 Improvements Environmental Study/ Preliminary Design Report November 2008.
Interstate 15 North Phase 4 9/01/2015 VE Class
Interstate 15 North Phase 4 Cost Risk Assessment 9/03/2015
Existing Interchange CC 215 Single bridge I 15
I-15 North Phase 4 Project Scoping Overview January 28, 2016
Interstate 15 North 8/17/2015 Update
The I-465 West Leg Reconstruction Project
I-15 North Phase 4 Scoping & Project Management Assistance
Interstate 15 North Phase 4 Cost Estimates 09/03/2015
Interstate 15 North 4/09/2015 Update
Interstate 15 North Phase 4
I-15 North Phase 4 Scoping & Project Management Assistance
Interstate 15 North Phase 4 8/19/2015 Update
Construction Management & Inspection
I-85 Widening Project MM Cherokee County Public Hearing March 14, 2017.
Upcoming Major Projects Nevada Transportation Conference April 9, 2013
I-85 Widening Project MM Cherokee County Public Hearing March 14, 2017.
Presentation transcript:

Interstate 15 North Phase 4 9/01/2015 VE Class

Background: I-15 North Environmental Document, Purpose & Project Elements I-15 North Environmental Assessment –FONSI issued May 2007 Purpose: ●Improve Safety, Operations & Access ●Decrease Congestion ●Reduce Travel Times ●Accommodate Projected Traffic Elements ●Increase Capacity ●Interchange and ramp improvements ●Freeway Management System Planning/NEPA/PE cost to date $ 8 million includes all phases except some of Phase 1 (Design Build) Design Cost I-15 North Environmental Assessment –FONSI issued May 2007 Purpose: ●Improve Safety, Operations & Access ●Decrease Congestion ●Reduce Travel Times ●Accommodate Projected Traffic Elements ●Increase Capacity ●Interchange and ramp improvements ●Freeway Management System Planning/NEPA/PE cost to date $ 8 million includes all phases except some of Phase 1 (Design Build) Design Cost

Background: I – 15 North Phase 1 (Constructed) Widened I-15 to ten lanes from US 95 (Spaghetti Bowl) to Lake Mead Widened I-15 to eight lanes from Lake Mead Boulevard to Craig Road Reconfigured Lake Mead Interchange – realignment of the on-ramps and off- ramps Added Auxiliary Lanes Completed 2010, $ 270 million Cost to Construct via Design Build (DB). The DB Project included DB design cost as well as construction costs Widened I-15 to ten lanes from US 95 (Spaghetti Bowl) to Lake Mead Widened I-15 to eight lanes from Lake Mead Boulevard to Craig Road Reconfigured Lake Mead Interchange – realignment of the on-ramps and off- ramps Added Auxiliary Lanes Completed 2010, $ 270 million Cost to Construct via Design Build (DB). The DB Project included DB design cost as well as construction costs

Background: I-15 North Phase 2 (Package A & B) Package A to advertise in Federal Fiscal Year (FFY) 2016.The estimated cost to construct is between $ 38.7 to $ 40.2 million Design Bid Build. Includes: ●Widen I-15 from 4 to 6 lanes for 4.8 miles ●Add Aux. Lanes between interchanges ●Restore pavement condition ●Widen & Seismic Retrofit 4 Bridges over the UPRR ●Landscape and Aesthetic Improvements Package B -ITS completed construction in 12/2013 at a cost $ M Package A to advertise in Federal Fiscal Year (FFY) 2016.The estimated cost to construct is between $ 38.7 to $ 40.2 million Design Bid Build. Includes: ●Widen I-15 from 4 to 6 lanes for 4.8 miles ●Add Aux. Lanes between interchanges ●Restore pavement condition ●Widen & Seismic Retrofit 4 Bridges over the UPRR ●Landscape and Aesthetic Improvements Package B -ITS completed construction in 12/2013 at a cost $ M

Background: I-15 North Phase 3 Project Design to resume 2016 Construction Packaging to be determined Cost of Construction estimated to be between $ 75- $ 85 M First Construction Package to Advertise FFY 2019 Project elements ●Widen I-15 from 4 to 6 lanes (4.6 miles) ●Possible new interchange between Speedway and Apex ●Restore pavement condition ●Landscape and Aesthetic Improvements Project Design to resume 2016 Construction Packaging to be determined Cost of Construction estimated to be between $ 75- $ 85 M First Construction Package to Advertise FFY 2019 Project elements ●Widen I-15 from 4 to 6 lanes (4.6 miles) ●Possible new interchange between Speedway and Apex ●Restore pavement condition ●Landscape and Aesthetic Improvements

Overview: I-15 North Phase 4 Improve I-15 and CC 215 Beltway System to System Interchange ●Two concepts under consideration (Three level & Two level) ●Improve freeway safety and operations, and local connectivity by providing a new interchange Construction Packaging ●To be determined by March 2016 ●First Construction Package FFY 2018 Cost of Construction estimated to be between $ $ M Improve I-15 and CC 215 Beltway System to System Interchange ●Two concepts under consideration (Three level & Two level) ●Improve freeway safety and operations, and local connectivity by providing a new interchange Construction Packaging ●To be determined by March 2016 ●First Construction Package FFY 2018 Cost of Construction estimated to be between $ $ M

I-15 North Phase 4 – Site Review

I-15 North Phase 4 – Previous CRA Cost Risk Assessment on 9/15/14 ●Looked at previous 3-Level alternative ●Key Project Schedule Risks  Utility Relocations  Preliminary engineering/scoping takes longer than expected  Delay to start of preliminary engineering scoping  Deep Foundations  Other large events in the area ●Key Project Cost Risks  Addition ROW may be required to provide 12’ wide maintenance access along EB CC 215 to SB I- 15 ramp  Deep Foundations  Preliminary engineering/scoping takes longer than expected  Differing site conditions caliche  Utility Relocations  UPRR coordination delays construction start Cost Risk Assessment on 9/15/14 ●Looked at previous 3-Level alternative ●Key Project Schedule Risks  Utility Relocations  Preliminary engineering/scoping takes longer than expected  Delay to start of preliminary engineering scoping  Deep Foundations  Other large events in the area ●Key Project Cost Risks  Addition ROW may be required to provide 12’ wide maintenance access along EB CC 215 to SB I- 15 ramp  Deep Foundations  Preliminary engineering/scoping takes longer than expected  Differing site conditions caliche  Utility Relocations  UPRR coordination delays construction start

I-15 North Phase 4 – Previous CRA Cost Risk Assessment on 9/15/14 ●Cost and Schedule  Base Cost - $ M, Pre-Response 70 th percentile - $ M, Post-Response 70 th percentile - $ M, Project Cost Range - $ M to M  Base Completion Date – Dec 2021, Pre-Response 70 th percentile – Apr 2023, Post-Response 70 th – Dec 2022, Project Completion Date Range - May 2022 to May 2023 Cost Risk Assessment on 9/15/14 ●Cost and Schedule  Base Cost - $ M, Pre-Response 70 th percentile - $ M, Post-Response 70 th percentile - $ M, Project Cost Range - $ M to M  Base Completion Date – Dec 2021, Pre-Response 70 th percentile – Apr 2023, Post-Response 70 th – Dec 2022, Project Completion Date Range - May 2022 to May 2023

I-15 North Phase 4 – Crash History

I-15 North Phase 4 – Local Access

I-15 North Phase 4 – Utilities

I-15 North Phase 4 – Drainage Existing

I-15 North Phase 4 – Drainage Future Conditions

I-15 North Phase 4 – Bridges

I-15 North Phase 4 – Structures Existing Structures G-961S and G-961N (cast in place box girder structures) will be widened in Phase 2 and it is not presently anticipated that they will need to be widened again in Phase 4. However, there is sufficient width between the two bridges for additional capacity (HOV lanes). G-961R (ES2) (cast in place post tensioned box) widening proposed both alternatives, there are no factor that would preclude the use of the same structure at this location. I-2499 (TP) (cast in place post tensioned box girder) and it’s present width would accommodate one addition lane. Widening proposed in both alternatives, there are no known factors that would preclude the use of the same structure type. G2568E and G2568W (post tensioned box girder structures). The width of these structures will accommodate an additional lane in each direction. Widening of G2568W (UP1) is proposed as part of the Phase 4 project Existing Box Culverts Local drainage throughout the area of the proposed interchange is accomplished by several large box culverts. The proposed configuration of the interchange may create the need to lengthen some of the culverts and/or provide new ones Proposed Bridges The possibility of large flyover ramp structures is anticipated to complete the system interchange in both alternatives. Due to the required geometric curvature, structures of this type are most often constructed with steel plate girders. The use of cast-in-place concrete box girders is a possibility; however, the difficulty of providing the needed falsework is generally prohibitive. At the other bridge locations, there are no identifiable conditions that would preclude the use of post-tensioned, cast-in-place concrete box girder bridges, which are NDOT’s preferred structure type

I-15 North Phase 4 – Pavement I -15 Pavement ●The I-15 North Phase 2 – Is adding lanes and resurfacing the I-15 pavement  Mill and Overlay with 3” Plantmix Bituminous & ¾” PB Open- Grade  Widening and replacement areas - 10” Plantmix Bituminous & ¾” PB Open-Grade with 16” Type 1 Class B Aggregate Base CC 215 Pavement ●Most of the facilities on CC 215 will be removed and replaced due to realignment ●Main Beltway was constructed with 11” PCCP Range Road and directional ramps ●Plantmix Bituminous Surfacing – Typically 6” I -15 Pavement ●The I-15 North Phase 2 – Is adding lanes and resurfacing the I-15 pavement  Mill and Overlay with 3” Plantmix Bituminous & ¾” PB Open- Grade  Widening and replacement areas - 10” Plantmix Bituminous & ¾” PB Open-Grade with 16” Type 1 Class B Aggregate Base CC 215 Pavement ●Most of the facilities on CC 215 will be removed and replaced due to realignment ●Main Beltway was constructed with 11” PCCP Range Road and directional ramps ●Plantmix Bituminous Surfacing – Typically 6”

I-15 North Phase 4 – Geotechnical Native soils ●Surface fill - Sands & gravels of varying depths (1’ to 4’). Removal, testing, and re- compaction (if suitable) ●Native clay soils have low to high expansion potential. Highly expansive soils should be removed and replaced Caliche ●Significant layers of moderately hard caliche were encountered in some borings ●The summaries of caliche indicate a few thin layers near the surface with thickness of one to two feet ●Deeper layers, 30 to 100 feet deep, varied greatly in thickness ●Rock excavation & heavy duty excavation excavation/ripping techniques should be anticipated in areas with appreciable grading or relatively deep excavations High Sulfate content ●Sulfate resistant cement is recommended ●Corrosion reduction methods should be implemented for buried pipes Ground Water not reported on any of the boring logs with depths up to 100’ No know fissures or faults in immediate vicinity of the project Spread footings and drilled shaft foundations are generally found to be suitable Native soils ●Surface fill - Sands & gravels of varying depths (1’ to 4’). Removal, testing, and re- compaction (if suitable) ●Native clay soils have low to high expansion potential. Highly expansive soils should be removed and replaced Caliche ●Significant layers of moderately hard caliche were encountered in some borings ●The summaries of caliche indicate a few thin layers near the surface with thickness of one to two feet ●Deeper layers, 30 to 100 feet deep, varied greatly in thickness ●Rock excavation & heavy duty excavation excavation/ripping techniques should be anticipated in areas with appreciable grading or relatively deep excavations High Sulfate content ●Sulfate resistant cement is recommended ●Corrosion reduction methods should be implemented for buried pipes Ground Water not reported on any of the boring logs with depths up to 100’ No know fissures or faults in immediate vicinity of the project Spread footings and drilled shaft foundations are generally found to be suitable

I-15 North Phase 4 – Landscape Architecture General ●North Las Vegas Community Gateway as per the I-15 Landscape and Architecture Corridor Plan ●Up to 3% of overall construction budget for landscape and aesthetics Landscape – Dynamic Desert Metropolis ●Plants need to be drought tolerant with a cold hardy factor as low as 20 degrees F ●Landscape Materials – plant material from Mojave Desert, Sonoran Region and other dry land environments Aesthetics ●Bridge treatments, wall aesthetics, sculptural elements and color spectrums designed to be unique but unified with I-15 Corridor Master Plan General ●North Las Vegas Community Gateway as per the I-15 Landscape and Architecture Corridor Plan ●Up to 3% of overall construction budget for landscape and aesthetics Landscape – Dynamic Desert Metropolis ●Plants need to be drought tolerant with a cold hardy factor as low as 20 degrees F ●Landscape Materials – plant material from Mojave Desert, Sonoran Region and other dry land environments Aesthetics ●Bridge treatments, wall aesthetics, sculptural elements and color spectrums designed to be unique but unified with I-15 Corridor Master Plan

I-15 North Phase 4 – Environmental General ●Environmental Assessment (EA) in May 2007 for the I-15 Improvements, US- 95 to Apex (FHWA-NV-EA 06-01) concluded with a Finding of No Significant Impact (FONSI) Reevaluation ●Generally required when there has been a time lag or changes ●Changes to:  Project scope or concept  Study area conditions  Regulatory requirements  Local priorities ●NDOT has implemented a series of questions & established a template to prepare a written reevaluation of a NEPA document ●Why? - Any design alternative developed resulting in improvements to areas outside the 2007 right-of-way or that may result in impacts not studied in the 2007 EA may require a written reevaluation General ●Environmental Assessment (EA) in May 2007 for the I-15 Improvements, US- 95 to Apex (FHWA-NV-EA 06-01) concluded with a Finding of No Significant Impact (FONSI) Reevaluation ●Generally required when there has been a time lag or changes ●Changes to:  Project scope or concept  Study area conditions  Regulatory requirements  Local priorities ●NDOT has implemented a series of questions & established a template to prepare a written reevaluation of a NEPA document ●Why? - Any design alternative developed resulting in improvements to areas outside the 2007 right-of-way or that may result in impacts not studied in the 2007 EA may require a written reevaluation

I-15 North Phase 4 – Alternatives Alternatives - # 1(3-Level) & # 2(2-Level) ●Alternative #1 Preliminary Cost Estimate - $ 140 Million ●Alternative # 2 Preliminary Cost Estimate - $ 126 Million Design is at conceptual level for both alternatives Common Assumptions ●Tropical Parkway Connector will be constructed ●Range Road is not a thru Street; access is restricted within the National Guard property ●Centennial Parkway will be extended to Speedway Alternatives - # 1(3-Level) & # 2(2-Level) ●Alternative #1 Preliminary Cost Estimate - $ 140 Million ●Alternative # 2 Preliminary Cost Estimate - $ 126 Million Design is at conceptual level for both alternatives Common Assumptions ●Tropical Parkway Connector will be constructed ●Range Road is not a thru Street; access is restricted within the National Guard property ●Centennial Parkway will be extended to Speedway

I-15 North Phase 4 – Alternative 1

I-15 North Phase 4 – Alternative Traffic Forecasts

I-15 North Phase 4 – Alternative 1 Structures

I-15 North Phase 4 – Alternative 1 Advantages ●Minimal utilities relocation ●Some utilization of existing roadways ●Some ROW acquisition & construction could be deferred until Centennial Pkwy is constructed Disadvantages ●Higher cost of bridges, embankments & walls due to 3-level configuration ●Multiple heavy turning movements & diversion of Centennial traffic onto Range Advantages ●Minimal utilities relocation ●Some utilization of existing roadways ●Some ROW acquisition & construction could be deferred until Centennial Pkwy is constructed Disadvantages ●Higher cost of bridges, embankments & walls due to 3-level configuration ●Multiple heavy turning movements & diversion of Centennial traffic onto Range

I-15 North Phase 4 – Alternative 2

I-15 North Phase 4 – Alternative Traffic Forecasts

I-15 North Phase 4 – Alternative 2 Structures

I-15 North Phase 4 – Alternative 2 Advantages ●Lower cost of bridges, embankments & walls due to 2-level configuration ●Straight alignment of Centennial without heavy turning movements ●Stakeholders support Centennial being favored Disadvantages ●Utilities relocation cost at Range Road to accommodate bridge foundations ●ROW acquisition cost for Range Rd relocation & Tropical Pkwy Extension Advantages ●Lower cost of bridges, embankments & walls due to 2-level configuration ●Straight alignment of Centennial without heavy turning movements ●Stakeholders support Centennial being favored Disadvantages ●Utilities relocation cost at Range Road to accommodate bridge foundations ●ROW acquisition cost for Range Rd relocation & Tropical Pkwy Extension

I-15 North Phase 4 – Right of Way Existing

I-15 North Phase 4 – Right of Way Alternative 1

I-15 North Phase 4 – Right of Way Alternative 2

I-15 North Phase 4 – Right of Way Summary Alternative 1 ●Bureau of Land Management (BLM) – SF ●State of Nevada (National Guard) – SF ●Private Property – SF Alternative 2 ●Bureau of Land Management (BLM) – 444 SF ●State of Nevada (National Guard) – 8881 SF ●Private Property – SF Alternative 1 ●Bureau of Land Management (BLM) – SF ●State of Nevada (National Guard) – SF ●Private Property – SF Alternative 2 ●Bureau of Land Management (BLM) – 444 SF ●State of Nevada (National Guard) – 8881 SF ●Private Property – SF

I-15 North Phase 4 – Other Projects Sheep Mountain Parkway ●CLV, in cooperation with the CNLV, NDOT, and RTC, has proposed the preservation of a corridor for future development of this multimodal transportation facility. The proposed 22-mile-long corridor, located to the north of CC215 in the northern Las Vegas Valley ●Presently, it is not anticipated that this facility will be warranted until the 2040 – 2050 horizon years. Sheep Mountain Parkway ●CLV, in cooperation with the CNLV, NDOT, and RTC, has proposed the preservation of a corridor for future development of this multimodal transportation facility. The proposed 22-mile-long corridor, located to the north of CC215 in the northern Las Vegas Valley ●Presently, it is not anticipated that this facility will be warranted until the 2040 – 2050 horizon years.

I-15 North Phase 4 – Other Projects I-11 and Intermountain West Corridor Study

I-15 North Phase 4 – Other Projects I-11 and Intermountain West Corridor Study ●Is envisioned to be a continuous high-capacity trade corridor extending from Nogales, Arizona to Las Vegas and potentially on towards Canada ●Alternatives include a south-west route utilizing the I-215 Bruce Woodbury Beltway, a central route utilizing US 95, and an east-north route utilizing I-15, CC215, and a new alignment to be determined to the east of the valley ●If the east-north route alternative, is determined to be the preferred route, this would redistribute traffic and add a significant new component through the I- 15/CC215 interchange I-11 and Intermountain West Corridor Study ●Is envisioned to be a continuous high-capacity trade corridor extending from Nogales, Arizona to Las Vegas and potentially on towards Canada ●Alternatives include a south-west route utilizing the I-215 Bruce Woodbury Beltway, a central route utilizing US 95, and an east-north route utilizing I-15, CC215, and a new alignment to be determined to the east of the valley ●If the east-north route alternative, is determined to be the preferred route, this would redistribute traffic and add a significant new component through the I- 15/CC215 interchange

I-15 North Phase 4 – Issue Wall Costs vs Extending the length of the bridges ●Background: The conceptual plans, for both alternatives, show the layout of bridges and walls for the northbound I-15 ramp to westbound CC215 and Tropical Parkway. Along this ramp there are two new bridge structures, one over UPRR and Range Road and the other over I-15. Additionally, there are two retaining walls on the south side of the ramp. The terrain in this area generally slopes downward from north to south and I-15 is on an embankment for its overcrossing of the UPRR and Range Road. Because of the height of the I-15 embankment, the sloping terrain, drainage and right-of-way constraints, these retaining walls along the south side of the ramp are very tall, H max = 65'. ●Wall costs are estimated to be $10.5 million. Wall Costs vs Extending the length of the bridges ●Background: The conceptual plans, for both alternatives, show the layout of bridges and walls for the northbound I-15 ramp to westbound CC215 and Tropical Parkway. Along this ramp there are two new bridge structures, one over UPRR and Range Road and the other over I-15. Additionally, there are two retaining walls on the south side of the ramp. The terrain in this area generally slopes downward from north to south and I-15 is on an embankment for its overcrossing of the UPRR and Range Road. Because of the height of the I-15 embankment, the sloping terrain, drainage and right-of-way constraints, these retaining walls along the south side of the ramp are very tall, H max = 65'. ●Wall costs are estimated to be $10.5 million.

I-15 North Phase 4 – Issue

NDOT Project Management Division: Assistant Chief – Lynnette Russell – Phone – Project Manager – Dwayne Wilkinson – Phone – Project Contact & Questions?