MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Andrew Moss ASTeC MICE Project Board 28 th June 2011 MICE RF System.
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Collaboration meeting, RAL, 4 th – 7th November 2009 Andrew Moss ASTeC Collaboration meeting, RAL, 10 th – 13 th november 2009 MICE RF Amplifier Status.
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
MOM Summary 11/01/10 Due to the Inclement Weather it has perhaps been quieter than usual Water - Tank has been holding water fine. Some ice has been forming.
MICE: Hall Infrastructure Chris Nelson CEng CM16 8 th Oct 2006.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
March 2003 Paul Drumm MICE Collaboration Meeting, CERN 1 Beam Line & Installation Plans Paul Drumm CLRC Rutherford Appleton Laboratory.
Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports.
Project Report Paul Drumm CM15, FNAL June MICE Schedule Overview First beam September/October 2007 –Shutdown from January 2007 –Eight months for.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
MICE Project Report Paul Drumm ~ Sunday August 1 st 2004.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 12, 2010.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Paul Drumm 30 March 2004 MICE at RF Power System: power source, distribution Paul Drumm RAL Ambitious title!
UK Funding PPRP Meeting on Monday 30 th June Accepted need for urgent work this year –no discussion on this –but also no indication of the level of funds.
1 Status of infrastructure MICE Video Conference, August 17, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department.
1 Implications Of Infrastructure Build The Infrastructure Project is bigger than anyone thought, but now it’s understood The cost was underestimated, but.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
Project report. Status: MICE Muon Beam Target: –Target presently installed ‘in-operative’: Optical connections removed (why?) –Implies realignment/set-up.
1 Hall & Beamline Installation Richard Apsimon, Andy Nichols, Willie Spensley MICE Collaboration Meeting, th Feb 2008.
1 Technical Co-ordination, Phase One The shared post of PM/TC has worked quite well Six months ago there was much for us to learn:  Revised the WBS 
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
MICE Status (with a UK slant) Paul Drumm, MICE Collaboration UK-NF June 2003.
MICE Magnetic Field Mitigation Review Potential impact on ISIS of MICE Stray Magnetic Fields 24 th September 2013 Martin Hughes.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
Project manager report paul drumm CM16 October 2006.
K. Long, 10 October 2015 Project Manager’s report Status/progress since CM18 Looking forward Organisation Conclusions.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
1 MICE CMPB Contents: Progress to date Project management things Plans for the May shutdown Steps towards Phase Two Problems and open issues summary Andy.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
Andrew Moss ASTeC CM32 9t h February 2012 RAL MICE RF System.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
PSI Contact PSI visit arranged for Feb 9th –Assessment of activity/contamination Possible remedial action –Seek additional equipment for solenoid Power.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
MICE RF Power Status Paul Drumm ~ Sunday August 1 st 2004.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
Malcolm Ellis – Brunel University – 8th April The International Muon Ionization Cooling Experiment.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling for all other quadrupole & dipole units –Houses.
MICE – UK Plan Roy Preece STFC RAL DOE Review of MAP Brookhaven National Laboratory 13 th August 2014.
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
MICE RF – Installation at RAL Tim Stanley RAL 7 November 2013.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
Andrew Moss ASTeC, Daresbury Laboratory October 2010 MICE RF Amplifier Status.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
MICE PM Report Progress with the Infrastructure A few problems
Introduction Jason Tarrant – Integration Engineering Step IV Removal
Presentation transcript:

MICE Project Report Alan Bross (for Paul Drumm)

Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around decay solenoid (DSA) must be completed; significant risk (high impact) ● concentrates the mind! – ISIS user runs - start up for production running 2nd October – These dates are subject to last minute changes

Strategy ● Schedule of work in the synchrotron in parallel with that in the MICE hall ● Work on the shielding, cryoplant and beam line within DSA broken into steps ● Parallel work in mice hall once solenoid is installed

Current events ● Shielding is being delivered from DL ● Next heavy-gang job is to pull out the existing shielding blocks - not under our control ● Preparations for final drilling in concrete roof ● Preparations for cutting solenoid trolley

Urgent needs ● many urgent items in time order: – Shielding design plan (steel plates); – Plinth; – Rails & extension frames; – Solenoid trolley mods; – Linde equipment installation; – Decay solenoid repair; – D2; – Q4-6;

Synchrotron components ● Dipole & Quadrupole stand parts now out for manufacture - delivery expected to drive schedule (for installation in May) ● Installation - people - may suffer clash

D2 is a copy of D1 stand Rebuild of Q in progress D2, Q-stands ● Engineering being finished off ● Rebuild of 1st Q35 is in progress – issue with coils - still being investigated – may need to remake some coils

Target ● Progress – Successful test in October – Didn’t manage a second go (for more statistics) ● Power supply operating at DL at higher amps – Power supply into a load > into target so far – One conclusion has been that the target controls are not fast enough – A plan has been evaluated & will be reviewed at beginning of March (TB + local review team) documents being prepared ● Risk: we need to “prove” reliability with time running out...

Milestones ~ ~ not critical Beam line - Synchrotron Review controls & EE (9th March) Orange: prove mechanism at low amps ~3 mo Red: prove at high amps ~3 mo On probation? To be discussed

Muon Solenoid few days late risk! Labour intensive! Have a plan with RAL+Ox+Lv+Imp

Beam line component Stands } Work in parallel to gain time! Just in time

Overall MICE BL Project Plan Schedule Our Risk Zero slack in a sequential work plan gain ~ 1 mo with || working

progressing ● Iron shields – control room side - engineering ~complete – linac side - simple wall – needs detailing ● MICE Plinth - concrete base under MICE – leave access clear for shielding installation – floor fixings need to be determined ● False floor - between linac wall and MICE plinth

Schedule Summary ● parallel work (plus a proportion of weekends) ● delays arise too easily – task review - anticipation ● dependent on delivery of items – north and south ● installation of items – more control – team of established – crane operators ● Can we do it! – yes we can!

Instrumentation & TOF0 & CKOV ● Still need to work out mounting scheme – follow from shielding design ● Need TOF for beam diagnostic ● installation in July? ● FNAL beam monitors – not yet clear how many needed – not yet clear on cost

RF Activities ● Important for Phase 2 - MICE-CERN-UK ● Tight schedule – 300kW power mid year ● waiting on final rebuild of amplifier – 4MW end of 2007 ● build HT rack ● control rack ● 4MW load? ● Conflicts of other activities – management issue in Daresbury

LH2 & Absorber ● Specification close to completion – sign off with MICE – sign off with RAL – tender - delivery in X months? – Overlap of MICE running & LH2 work ● LHe work will be important to learn safety implications ● Advise a mid point review before starting with LH2

ISIS Running in August [4] MICE beam can basically run any time synchrotron is running, provided beam losses in Straight 7 acceptable. But machine programme determined by ISIS operations, not MICE. Provisional – subject to change

ISIS user running ● Provisional dates s2c – Cycle starts Tuesday 2 nd October – ~60 days of user beam in 2007 Provisional – subject to change

Organisational & Safety Issues ● October collaboration meeting: – MICE management needs to re-organise itself into “an operational structure”, e.g. ● Physicist in charge (for weeks running) ● Engineer in charge (for weeks running) ● Shift teams (call up and rostering) ● weekly run planning meetings ● monthly safety review meetings – MICE Spoke/MICE EB should set up a team to deliver this structure, operating procedures, local rules need to be developed (raised at (see) CM16 October '06)CM16 October '06