ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.

Slides:



Advertisements
Similar presentations
ILCTA-MDB RF Power Status 9/21/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power Meson Detector Building 3.9 GHz RF Power A0 Building September 21, 2006 [John.
Advertisements

Muon Campus Projects Mary Convery 1. Background on Muon Campus plan Earlier Plan had 5 Common Projects:  MC1 Building (GPP)  MC Beamline Enclosure (GPP)
SRF Beam Test Facility at NML Jerry Leibfritz April 26, 2010.
SM18 Vertical/Horizontal Test Setup LHC Crab Cavity Engineering Meeting Session: Cavity Cryostat Testing & Integration in SM18Cavity Cryostat Testing &
RF Unit Test Facility at NML & CM1 Test Plan Bob Kephart Fermilab IWLC-10 October 20, 2010.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Engineering and Design Group Fermi National Accelerator Laboratory Cryogenic Department AAC Review, May , 2005 Jay Theilacker HPTFCRYOGENICS.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Overview of the ILC and SRF Program (With an emphasis on Px) Shekhar Mishra ILC & SRF Program Fermilab.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
Test Stands Roger Ruber Uppsala University ESS TAC4 16 Feb
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.
STF Plan & Schedule H. Hayano, KEK. Superconducting RF Test Facility Comprehensive Test Facility dedicated to ILC SC-RF R&D (expandable to FEL, ERL) for.
09/28/07Shutdown’07 Week 8 F.G. Garcia1 MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week.
STF status, April 2011 H. Hayano March 11, 2011: 14:46 Earthquake, AC power down. 16:00~18:00 visual check of STF infrastructure, no severe.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
F Project X Overview Dave McGinnis October 12, 2007.
ILC WG2 (Main Linac System) status & report H. Hayano, KEK.
Fermilab High Intensity Neutrino Source R&D Program - Mission, Status, Plans, and Support Needs - For AD Department Heads March 2007 Bob Webber.
Cryomodule Development at Fermilab Don Mitchell Representing the SRF engineering community at Fermilab April 20, 2009 Tsukuba, Japan TILC09.
SM18 INFRASTRUCTURE Crab Cavity CryoModule – Conceptual Design Meeting
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Americas Region: T4CM Status and Plans H. Carter TD SRF Dev. Dept. July 14, 2006.
April 19, 2006A.Klebaner Cryogenics for ILC TA Current Status Plans and issues.
1 Plan and Opportunities for Migration and Integration of the Photoinjector into New Muon Lab Mike Church AAC Review - 12/5/06.
F Photoinjector for the ILC test facility at Fermilab Sergei Nagaitsev Fermilab May 24, 2007.
MINU GPP WBS 1. Main Injector Neutrino Upgrades - Infrastructure Project Dixon Bogert APD Department Report – March 7, 2007 Russ Alber - FESS Engineering.
Aug 23, 2006 Half Current Option: Impact on Linac Cost Chris Adolphsen With input from Mike Neubauer, Chris Nantista and Tom Peterson.
Global design effort DOE meeting 8/10/06 Global design effort Americas 1 FY07 DOE ILC Budget recommendations G. Dugan ILC-GDE/Cornell University GDE Americas.
Horizontal Test Stands and CC2 Results Andy Hocker Testing an alternative ILC cavity design at USPAS (Q 0 =2.23E+02)
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
Overview and Status of the Fermilab High Intensity Neutrino Source R&D Program Giorgio Apollinari for Bob Webber.
F ILC Accelerator R&D and AAR&D at NML Sergei Nagaitsev FRA Visiting Committee Review April 20/
New plans for high power RF tests places at CERN O. Brunner BE/RF/KS – January ‘10.
Proton Driver Resources & Schedule (R&D Plan) Rich Stanek May 10, 2005.
Comparison of Fermilab Proton Driver to Suggested Energy Amplifier Linac Bob Webber April 13, 2007.
Current NML Layout.  Overall length of building is 72M 3 cryomodules with feed and end cans ~40M Not enough room for both photoinjector and downstream.
BEAMLINE HOM ABSORBER O. Nezhevenko, S. Nagaitsev, N. Solyak, V. Yakovlev Fermi National Laboratory December 11, 2007 Wake Fest 07 - ILC wakefield workshop.
F DOE Annual Program Review High Intensity Neutrino Source R&D in the Meson Detector Building Bob Webber & Giorgio Apollinari September 26, 2007.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
CMTF Infrastructure Jerry Leibfritz PIP-II Machine Advisory Committee 9-11 March 2015.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
Details on the Accelerator Installation Plan E. Sargsyan & L. Lari 20 April 2016.
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
SM18 Vertical & Horizontal Test 110/12/2013Mathieu Therasse CERN BE/RF A. Benoit, O. Brunner, E. Jensen, A. Macpherson, P. Maesen, K. Schirm, W. Venturini.
Project X Workshop - Cryogenics1 Project X CRYOGENICS Arkadiy Klebaner.
PXIE Layout and Infrastructure Building, Cryogenics, Utilities… Rich Stanek On behalf of the CMTF Team PXIE Collaboration Meeting November 28, 2012.
WBS – 30 Straight Section Reconfiguration g-2 Accelerator – 30 Straight Section Reconfiguration D. Still Fermilab Muon g-2 IDR, June 5-7.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
SRF Infrastructure Changes Required for a CW linac Robert Kephart FNAL AAC Meeting November 16, 2009.
Chapter Editor: John Weisend TDR Chapter 6 Cryogenic System, Vacuum System & Test Stands.
ILCTA-MDB RF Power Status 4/27/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power 3.9 GHz RF Power Meson Detector Building April 27, 2006 [John Reid]
Infrastructure status and plans at CERN 1) W. Weingarten/CERN TTC Milano 28 February - 3 March W. Weingarten/CERN 1)Most of the slides are based.
ASTA Latest Update E. Harms April Photoelectrons first produced at ASTA on 20 June 2013 –Molybdenum (uncoated) cathode ‘Routine’ Electron operation.
S1G Experiment Schedule Plan
Cryomodule test stand at ESS site
CBETA Technical Review
LERF as Cryomodule Testing Facility Set-Up and Installation Logistics
Uppsala Commitment to ESS and FREIA Planning
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
SPS cryogenic proximity equipment and SM18 validation
Chris Adolphsen Sergei Nagaitsev
Hosting Orsay Walid KAABI
ESS RF Development at Uppsala University
UK RFD Pre-Series cryomodule
Infrastructure and Test Facilities in the U.S.
Presentation transcript:

ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007

S. Nagaitsev2 Location New Muon Lab

S. Nagaitsev3 New Muon Lab Building

S. Nagaitsev4 Rough S2 Schedule

S. Nagaitsev5 NML plans The NML is being constructed to address primarily the S2 R&D list –However, our plans go beyond S2. We would like to include elements of S4 R&D tasks (crab-cavities), diagnostics development, personnel training, and accelerator R&D. –The NML facility is staged (1 CM, 2 CMs etc); when complete, it would include 1 (or 2) rf units running ILC-like beam at 5 Hz. The S2 schedule of having phase 1.3 complete at NML in 2011 is quite challenging –Only early stages of NML (up to 2 CMs) are well planned –3 CMs (1 rf unit) requires building an extension tunnel and a new cryo-plant –The progress is resource limited, thus the schedule has to stretch to accommodate the scope

S. Nagaitsev6 Outline of our plans Cryomodule delivery –1 st (Type 3+) cryomodule is planned to be delivered in fall, 2007 –2 nd (Type 3+) CM – summer 2008 –3 rd (ILC Type 4) CM – Mid FY09 –Replace all three CMs with ILC Type 4+ in FY2010 The NML facility will start as a Cryomodule Test Stand in FY07-08 FY08: add beam; start civil construction of the building extension Convert to an ILC RF Unit beam test facility in FY11

S. Nagaitsev7 NML Schedule (Phase-1) Phase - 1 (FY07 thru early FY08) –Prepare Facility for Testing of Capture Cavity II (CCII) and 1st Cryomodule (CM1) without Beam Building Infrastructure (AC Power, Water, Air, Mechanical) Electrical Infrastructure (Racks, Trays, Cables) Build Cave to Test these Devices (~ 3/4 of Full Cave) RF Systems (3MW for CM and 300kW for CCII) Cryogenic System (1st Refrigerator, Feed Can, Feed Cap, End Cap, Distribution) Control Room LLRF, Controls, Safety Systems, Instrumentation (non-beam) –Move CCII from Meson Detector Building (MDB) to NML Cool-down and Power Testing

S. Nagaitsev8 Phase 1: 1st CM (end of CY07) Capture cavity 2 in its final location for the injector Type 3+ cryomodule A used 3-MW Klystron, 10-MW, 1.5-ms modulator CC2 RF system

S. Nagaitsev9 NML Schedule (Phase-2 & 3) Phase - 2 (FY08) –Testing of 1st and 2nd Cryomodule without Beam, Prepare Facility for Beam Receive, Install, Power, Cool-down 1st Cryomodule Install New Gun and Relocate Injector to NML Extend Cave Install Beam Lines and Dumps Install Additional RF Systems needed for CCI and Gun Receive, Install, Power, Cool-down 2nd Cryomodule Begin Building Extension needed for Phase-3 Phase - 3 (FY09) –Testing of Full RF Unit with Beam Complete Building Extension Begin Testing with Beam Install 3rd Cryomodule Upgrade Cryomodule RF system to 10 MW

S. Nagaitsev10 Proposed NML Injector Layout P. Piot (CC-1, CC-2) (intended initially for ILC crab cavity tests) 22m

S. Nagaitsev11 Two CMs with beam The existing building is perfect for testing two cryomodules with ILC-like beam. The building can be extended to fit 3 cryomodules.

S. Nagaitsev12 Building extension Construct a new building ~50m away from NML. Connect by a tunnel when schedule allows. Move loading dock. ILC-like tunnel, space for 3 more cryomodules Room for a new cryo-plant

S. Nagaitsev13 New Cryo Plant Temporary cryo system (being installed now): New Cryo plant –Must be flexible to allow a wide range of heat loads, including 5-Hz operation –Must meet specifics of the ILC operating temperature levels of 2.0 K, 5 K, and K –Long lead time Requires a 15m x 25m building; the plan is to combine it with the NML extension. Engineering studies complete, have a quotation.

S. Nagaitsev14 NML FY07 Accomplishments Removal of CCM –Completed Removal of Chicago Cyclotron Magnet (CCM) –Filled in CCM Pit (~10’ deep) with Concrete Prepared Building Infrastructure –AC Power Distribution/Network Cabling –Relocated Piping, Cable Tray, Duct Work –Cleaned out Building, Epoxy Coated Floor –Began Preparation of Control Room (New ceiling, paint) Alignment –Installed Deep Rod Monuments (DRM’s), Established Align. Network –Began Installation of Water Level System Test Facility –Began Installation of Cave and Electrical Racks for Phase-1 Cryogenic System –Installation of Refrigerator-1 and Piping Continued –Installed Storage Tanks

S. Nagaitsev15 ILC Test Facility at NML NML During Removal of Chicago Cyclotron Magnet(CCM) (September, 2006) NML Facility after CCM Removal and Floor Painting (February, 2007)

S. Nagaitsev16 Remaining Work in FY07 Complete Installation of: –Cave –Electrical Racks, Cable Trays, Pull Cables –Cryogenic System for CCII –Control Room Install –RF Systems and RF Distribution for CCII and CM-1 –Water Cooling System –Safety, LLRF, and Control Systems Install Capture Cavity II –Move from Meson Detector Building (MDB) –Connect RF Power and Cryogenics –Begin Testing/Operation

S. Nagaitsev17 Current Picture of NML Facility