LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, 2011 23 slides  Status of LHC: electrical connections  Description of shunt.

Slides:



Advertisements
Similar presentations
1. 2 LHC consolidation: tests completed in 2010 Projects completed in 2010 Test facility consolidation Where are we now? Planning Foreseen Activities.
Advertisements

February 2009 Summary of Chamonix 09 Steve Myers.
Sequence of QC steps for main bus bar splices Control of cables and stabiliser prior to connection by ICIT team Temperature control during soldering, visual.
ELECTRO THERMAL SIMULATIONS OF THE SHUNTED 13KA LHC INTERCONNECTIONS Daniel Molnar, Arjan Verweij and Erwin Bielert.
New HV test specification for the LHC N. Catalan for the EI section.
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Progress Report V. Kashikhin for Superconducting Magnet Team.
Coil working group video-meeting P. Ferracin, J. C. Perez, S. Izquierdo Bermudez, X. Sarasola February 4th, 2014.
Quality control of LHC electrical interconnections to be produced during the 2009 shutdown Since the functional properties of the LHC electrical interconnections.
TE-MPE –TM, 16/05/2013, Mateusz Bednarek, TE/MPE-EE ELQA testing during and beyond LS1.
Overview of SMACC-QA 1.Recall of SMACC-QA organization 2.Tuning the procedures 3.Main results from the QC teams 4.Auditors findings Ranko Ostojic 23 July.
Status of SMACC-QA 1.Recently resolved issues 2.Update from QC teams 3.Statistics S56 and S67 4.Auditors findings 5.4th Splice Review – 22/24 July Ranko.
REVIEW OF THE CRYOGENIC BY-PASS FOR THE LHC DS COLLIMATORS ELECTRICAL CIRCUIT MODIFICATION, INCLUDING OPERATIONAL CONSIDERATIONS PRESENTED BY A. SIEMKO.
Overview of the recommendation on LHC Splices Consolidation Frederick Bordry, head of the CERN Technology Department, has called for a series of three.
The Sector 3-4 incident at the LHC: fault tree and corrective measures Ph. Lebrun Risk Analysis Review Committee CERN, 5 March 2009.
LHC Splice Review, C. Scheuerlein, Local quality control of LHC electrical interconnections during the 2012 shutdown.
A. Verweij, TE-MPE. 3 Feb 2009, LHC Performance Workshop – Chamonix 2009 Arjan Verweij TE-MPE - joint stability - what was wrong with the ‘old’ bus-bar.
ATF2 quads status 22Nov05- Cherrill Spencer 1 Status Report on the Design and Fabrication of 29 quads for ATF2 By Cherrill Spencer, SLAC, for ILC-BDS weekly.
A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
LHC status & 2009/2010 operations Mike Lamont. Contents Consolidation – brief recall Splices Operational energies Potential performance Present status.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Technology Department 1 Visit to Hall 180: Presentation of the consolidation process Third LHC Splice Review, November 12, 2012.
1 A. Verweij, TE-MPE. LHC Performance Workshop – Chamonix Feb 2010 Arjan Verweij TE-MPE - type of defects - FRESCA tests and validation of the code.
1 Quality control of the LHC main interconnection splices before and after consolidation C. Scheuerlein and S. Heck 2 nd LHC splice review,
Measurement and data extraction. How to measure the splice and diode interconnections. Accuracy and issues of these measurements. Data extraction issues.
1 A. Verweij, TE-MPE. LHC Performance Workshop – Chamonix Feb 2010 Arjan Verweij TE-MPE - type of defects - FRESCA tests and validation of the code.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
Special interventions Status of production and QC Nicolas Bourcey TE-MSC-MDT Fourth LHC Splice Review November 2013.
MPE Workshop for LS1 / 22 & 23 Nov. 2012, G. D’Angelo TE/MPE-EE ELQA during LS1 train, Special measurements and NCs Magnet replacement: AIV Splices consolidations:
Work Organisation for Splice Consolidation Francesco Bertinelli 20 minutes presentation, 10 minutes discussion: 12 slides First LHC Splice Review, CERN,
1 LHC Status LHCC 23 rd September 2009 Steve Myers.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
LHC Machine Status Report Mike Lamont for the LHC team Acknowledgements: Mirko Pojer, Matteo Solfaroli, Katy Foraz et al.
HWC with nQPS Splice Monitoring Zinur Charifoulline & Bob Flora Real Time (~10 sec) BUS Voltage Energy Extraction Trip 300 µV threshold on Un-bypassed.
LHC circuit modeling Goal: Create a library of electrical models and results for each circuit Useful and usable for the next 20 years…… Web site cern.ch/LHC-CM.
ABTEF Meeting, V. Namora Quality Assurance in the Superconducting Magnets and Circuits Consolidation (SMACC) project.
Quality Assurance Overview Ranko Ostojic 12 Nov 2012.
Quadrupoles and orbit correctors bus bars routing along the inner triplet string MQXF Workshop at CERN– February the 3 rd 2016 H. Prin With acknowledgements.
MQXFB design, assembly plans & tooling at CERN J.C Perez On behalf of MQXF collaboration team MQXF Workshop on Structure, Alignment and Electrical QA.
TE-CRG Activities D. Delikaris, TE-CRG.
P. P. Granieri 1,2, M. Breschi 3, M. Casali 3, L. Bottura 1 1 CERN, Geneva, CH 2 EPFL-LPAP, Swiss Federal Institute of Technology, Lausanne, CH 3 University.
MSC Technical Meeting 29 August 2013 Overheated QBBI.A21L6 F. Savary with contributions from N. Dalexandro, H. Prin, C. Scheuerlein, P. Voisin.
Henryk Piekarz SC Magnets at Fermilab HTS Cable Test for a Fast-Cycling Accelerator Dipole Magnet E4R Test Goals and Arrangement Review September 10, 2009.
LHC Risk Review Installation Progress Francesco Bertinelli – TE/MSC 5 March, 2009 (20 minutes) On behalf of - and with several contributions from – the.
MQXFS1 Test Results G. Chlachidze, J. DiMarco, S. Izquierdo-Bermudez, E. Ravaioli, S. Stoynev, T. Strauss et al. Joint LARP CM26/Hi-Lumi Meeting SLAC May.
The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar ( )
Superconducting Cryogen Free Splittable Quadrupole for Linear Accelerators Progress Report V. Kashikhin for the FNAL Superconducting Magnet Team (presented.
News from the LHC J. Wenninger CERN Beams Department Operation Group
First LHC Splice Review Introduction
RB and RQ shunted BusBar current carrying capacities
Status of design and production of LEP connection cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Cutting and welding First internal LHC Dipole Diode Insulation Consolidation Review 10 Oct 2017 G. Favre / A. Amorim Carvalho G. Favre EN-MME.
LHC Interconnect Simulations and FRESCA Results
12 October 2009 RRB Plenary R.-D. Heuer
Cutting and welding First internal LHC Dipole Diode Insulation Consolidation Review 10 Oct 2017 G. Favre / A. Amorim Carvalho G. Favre EN-MME.
The LHC - Status Is COLD Is almost fully commissioned
FCC 16 T dipole 4578 dipoles + 5 % spares : 4807 dipole magnets
Splices in 13 kA circuits status of an ongoing work just started
Long Shutdown for the LHC: Vacuum Beam Pipes
Powering the LHC Magnets
SMACC local splice quality control
Functional specification for the consolidated LHC dipole diode insulation system and consolidation strategy C. Scheuerlein on behalf of the LHC dipole.
MBHSP02 test STATUS and first results
Consolidation of the dipole diode insulation Technical aspects
WP3 Meeting – December the 10th 2015 H. Prin
L. Bottura and A. Verweij Based on work and many contributions from:
Using the code QP3 to calculate quench thresholds for the MB
LHC status & 2009/2010 operations
Shortening the long RQF/RQD busbar segments in points 1 and 5
Presentation transcript:

LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, slides  Status of LHC: electrical connections  Description of shunt consolidation  Quality Control  Scenario for intervention  Missing resources Joint CERN-Pakistan Committee: 6 th meeting

LHC electrical interconnections 2 W bellows (see later…)

13 kA (“main”) busbar interconnection splices From L. Rossi, CERN Courier September

Poor copper to copper continuity. Provided by butt soldered joints, this electrical quality depends on the: -tolerances of the mating surfaces -relative tolerances between 2 paired bus bars -cleaning of the surfaces -capacity of the soldering to fill the gap providing good contact -correct execution of the soldering. Lack of internal contact SC cable to bus bar within the same cross-section: partial melting of the Sn-Ag in the bus bar during connection soldering, loss of solder Need simultaneous presence of two effects: 4

: new Quench Protection nQPS 5 Our new “eyes” !

LHC main IC splices today (SC) From Z. Charifoulline 301 ± 85pΩ R max = 2.7nΩ R max = 3.3nΩ 306 ** ± 313pΩ (**) number of splices in the quads segments corrected, 1.3 added Dipole Buses Quad Buses Main Dipoles&Quads Bus, sorted by position, 2048 segments All HWC pyramids and plus ~150 ramps to 3.5TeV analyzed Top 10 Splice Resistances 2nΩ 6

Dipole magnets internal splices From R. Principe, A. Zaghloul, P. Fessia 7

Dipole internal splices today (SC) From Z. Charifoulline ±1.2nΩ 8 splices (but not all the same type) 1.4±1.3nΩ 3 + 2* splices (* partially) Main Dipoles Main Quads 8

Courtesy R. Flora, C. Scheuerlein (C17-A17)L2 +36μΩ R16→+42μΩ (39.6μΩ, 26.6μΩ) (C30-A30)L2 +36μΩ R16→+29μΩ (41.3μΩ, 12.3μΩ) (B29-A30)R1 +45μΩ R16→+44μΩ (22.8μΩ, 28.5μΩ, 29.9μΩ) (B32-A33)R1 +39μΩ R16→+53μΩ (52.3μΩ, 24.9μΩ, 10.8μΩ) (A18-B17)L2 +35μΩ R16→+17μΩ (28.0μΩ, 11.2μΩ, 13.4μΩ) Biddle measurements: 1-2 main IC splices (NC) 9

The estimated R-8/R-16 random error is ±1 µΩ, and the systematic error is about +10 %. R8/R16 test: main IC splices (NC) Courtesy C. Scheuerlein 10

Shunts on dipole interconnect 11

Chosen soldered alloy: Sn60-Pb40 for – Melting temperature (< Sn-Ag) – Wetting capability – Mechanical and electrical properties Shunt description  Copper plate 15 mm wide, 3 mm thick.  Copper annealed at 400 ⁰ C for 2 hours to maximize RRR 12

 Total magnet to magnet interconnects in the machine:  Total 13 kA splices: ~  Number of splices to be redone: ~1 500 (15%)  Number of shunts to be applied: ~ Shunt work in numbers 13

Copper surface machining 14

The shunt soldering process 15

Isostatic assembly Mirror symmetry across H and V planes (assembly facilitate and cost saving) Allowed misalignment default V±5 mm, H±3 mm Second insulation skin Pre-stress adjusted with accurate tooling (5kg) Helium ducts in order to give good cooling for the bus bars (no thermal barrier) 1)Shunt soldering in position 2)Central insulation piece introduction between the bus bars 3)Lateral insulation pieces introduction 4)Polyimide foil wrapping around insulation pieces 5)316L collars tie clamping around Insulation box and assembly procedure MB 16

Quality Control of main IC splices  R_RT-top-side tests for the QC of individual solder contacts.  After repair the shunt contact on the wedge of M3-QRL-connection, R_RT-top-side is reduced from 10.5 µΩ to 2.1 µΩ. Comsol R_RT-top-side simulation for shunt with defect (courtesy S. Heck) R_RT-top-side measurement configuration 17

Examples of damaged cables found in 2009 by the personnel performing the interconnection work NCR : Entire cable squeezed between U-piece and wedge NCR , 2 strands cut NCR : Cable overheated (>580 °C) NCR : Entire cable was squeezed between U-piece and wedge 18 i.e. important to have experienced technicians, specifically for the most critical activities

What activities are involved for IC work? 19

Orbital machining to cut open TIG welds 20

Duration of IC work  at 50 IC/week (!!!) for critical activities,  14 weeks for 1 st sector, 5 weeks later for 2 nd sector, 49 weeks for 8 sectors  2 shift work (on different activities), some overlap: 6h–10h/break/11h-15h 12h-16h/break/17h-21h  no learning curve, no built-in contingency, no account for holiday/closure periods  must work sequentially to adjacent sector, without access constraints (i.e. first cool-down and HWC powering)  big concern is the “other activities” to be done in parallel: more realistic is to consider an additional 2-3 months 21

Estimate of IC resources needed 22 Pakistan Collaboration?

The current scenario  1 “train” only for standard activities  A Special Intervention team to prepare non-standard work before the arrival of the train  Long Shutdown starting January (April?) 2013  to replace F. Bertinelli as IC&Magnet Long Shutdown Project Responsible starting 1 July,