● Main goals for week 33: – Luminosity production; – First 150 ns bunch train attempts; – Roman Pots: check movement at 3.5 TeV, with 1b; – Off momentum.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC progress week 19 Monday 11 th May 2015 Coordination: Jan Uythoven, Massimo Giavannozzi, Mike Lamont.
LHC progress Saturday 2 nd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
LHC progress Thursday 30 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Monday 4 th to Friday 8 th Technical stop  Coordination: Katy Foraz  Machine back to Operations Friday evening on schedule Major cryogenics intervention.
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
Weekly summary Summary Week /19.07 M. Lamont & J. Wenninger for the OP team and for all colleagues from the various groups 8:30 meeting 1.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
LHC progress Report LHCC Wednesday 23 rd March 2011.
LHC Status Mo Morning 20-June Bernhard Holzer, Gianluigi Arduini et al 7 runs The Week.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Monday h34: beam (1020b) lost after 10 Hz RF trim. Fill h56: XPOC to be reset by expert. 08h18: Masked QPS_STATE SIS interlocks for RB.A12.
● 08h00: Adjust mode for end-of-fill study. Scraping test for determining transverse beam profile (beam 2, vertical). As expected, beam dumped with BLM.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
● Morning: Physics fill with 25 bunches: – 07:00: Injection; – 07:25: Start ramp; – 09:00: End of squeeze and stable beams; – Emittances:  x1 = 3.0 
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Goal of the week: Stable beams with trains of 200 & 248 bunches 1 OP summary of week 40 R. Bailey, J. Uythoven & J. Wenninger.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
:00 meetingEBH 11 Saturday :00 meetingEBH 2  7:58 Fill 2483 (264 bunches) dumped by reference orbit set to zero in.
– Machine closed. Ramp for powering tests & pre-cycle – Pilots through nominal cycle up to collisions. Measure chroma during squeeze. Check dump of pilots.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
Production running 1 pb-1Lost to Mon h2062e32EOF studies Tue h17.152e32UFO Q8.L5 Tue h e32OP request Thu h e32OP.
04h36: Cryo problem in arc 81. Access. 09h14: Injection.  TI8 injection collimator setup.  Testing new sequence.  New version of vacuum application.
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
LHC Status Sat Morning 30-June Bernhard Holzer, Jan Uythoven Status Friday Late: preparing restart some issues... LHCb dipole tripped / router problem.
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Wednesday 21 March 2012.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Summary Friday h38: Ramp down and pre-cycle.
Saturday 30th June - Sunday: Rocky !
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Summary week 31 Week 31 G. Arduini & O. Brüning
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Thursday morning – optics correction
Summary of Week 11: 14 – 21 March
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Week 35 – Technical Stop and Restart
Monday Morning – recovery from cryo.
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Friday morning 10:30 Optics measurements and corrections.
Wire almost entirely through beam before BLM triggers dump
LHC Morning Meeting - G. Arduini
Friday Morning 7:30 injection for fill 2908
Saturday 7th May Sat – Sun night
Summary Thursday h21: Stable beams fill #1303.
Aims for the week Recover from technical stop and precycle at 10A/s
Thursday 26th July 13:21 Fill 2880 beam dumped
Thursday – Morning Energy matching at injection with H CODs
LHC Morning Meeting - G. Arduini
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Thursday
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Another Immortal Fill….
Wednesday 26 October 2011.
Wednesday 6.10 Morning: Quench test at 450 GeV
Tuesday
Presentation transcript:

● Main goals for week 33: – Luminosity production; – First 150 ns bunch train attempts; – Roman Pots: check movement at 3.5 TeV, with 1b; – Off momentum loss maps for Beam2 in collision configuration; – Moving to 48bx48b Week :30 meeting

● Operation with 25 on 25 and 48 on 48 bunch configurations: – 3 fills with up-to 240 nb -1 per fill  36.5 h of luminosity production  ca. one fill every other day; peak luminosity: L = cm -2 sec -1 – average fill time above 12 hours (10.5, 12, 14, [>7]) – integrated luminosity: 640 nb -1 (105, 105, 240, [190]) –  ca. 22% efficiency (wrt to scheduled time = 1 week); 48% machine availability Week :30 meeting

Week :30 meeting

Week :30 meeting ca. 45% efficiency relative to available beam time ca. 22% efficiency per scheduled time

● Started the day with physics fill from previous night. ● Morning: End of fill studies – Damper studies. ● Afternoon: Access for various interventions: – Among others: BLM updates; – Finished access at 00:30 at night. ● Night: – Some delays due to problems with PC trips and QPS; – Then BLM validation test with beam after firm ware update. Monday: 5 8:30 meeting

Damper used at 3.5 TeV with different gains (horizontal plane) red: beam 2 kicked gain beam 2 damper increased x16 in steps of x2 blue: beam 1 kicked gain beam 1 damper increased x16 in steps of x2 Data from bunch 1 oscillations (8192 turns), Qkicker used at full strength gain setting: -25 dB to -1 dB in steps of 6 dB (-19 dB used operational)

Time domain data (-25 dB and -7 dB gain) horizontal plane, beam 1 data from bunch 1 oscillations (8192 turns), Qkicker used at full strength gain setting: -25 dB and -7 dB, beam 1 kicked, horizontal plane factor 8 gain increase on one beam does not lead to a factor 8 increase of damping  beams coupled, gain for damper on other beam was kept constant -7 dB -25 dB beating of two modes, both well damped Damper used at 3.5 TeV with different gains (horizontal plane)

● Morning: Bunch Train Studies: – Ready for other systems (ADT, RF…) to make test on 1 train of 4 bunches ( B1); – Non closure of LHCb spectrometer bump after polarity inversion; ● Afternoon: – Dispersion measurements and Loss map measurement for Beam2 at 3.5 TeV:  Hierarchy not satisfied for off momentum particles (-1kHz RF shift) – Issue with Q-feedback and damper cohabitation during ramp: feedback system locks onto Hump signal. ● Night: – Struggling to prepare new fill for physics with 25 bunches (QPS; trips & SPS). Tuesday: 8 8:30 meeting

Orbit in the LHC for injection with bunch trains: Orbit after LHCb spectrometer polarization change: Top: initial orbit for new polarity Bottom: After correction.

Tune and Hump with damper on: Beam 2: Vertical tune and Hump signal are approximately equally strong with damper on.

1bx1b, Physics conditions Hz RF trim Collimators – Loss maps on momentum Stefano Redaelli, Walter Venturini, Joerg Wenninger BLACK = collimators RED = warm elements BLUE = cold elements TCTs see about ~0.01 of the primary loss spike and the cleaning efficiency to the cold elements is 99.25% (4 stage hierarchy is respected). Operation with 25 bunches can continue in these conditions To be repeated for B2

Beam Losses in the LHC during injection with bunch trains Daniel Wollmann: The hierarchy is violated in this case: The TCSG.B5L3.B2 acted as primary collimator. One can also see, that the losses on the TCLA.A5L3.B2 are quite high (~64% of the losses at the TCSG).

● Morning: Physics fill with 25 bunches: – 07:00: Injection; – 07:25: Start ramp; – 09:00: End of squeeze and stable beams; – Emittances:  x1 = 3.0  m;  y1 = 3.0  m;  x2 = 3.4  m;  y2 = 4.0  m; – Initial peak luminosity: L = cm -2 sec -1 ;  total delivered luminosity after 12 hours: 90nb -1 ; (105nb -1 with eof studies ) – 19:00: Start moving Roman pots in steps:  30  to 25  ; 20  ; – 21:00: Luminosity scan in IP1 to verify optimized collisions point; – 21:30: Beam dump & ramp down ● 22:00: Access for quench heater power supply problem on RB.24L2: Wednesday :30 meeting

● Morning: Machine in access: – BLM crate in Pt7 (broken power supply); – RQT12.R1B1 repair of FGC: access in PM15; – 09:00: RCBCH6.R8B1 tripped  access required in Pt8; – ATLAS asked if they could have short access in shadow of Pt8 intervention; ● 13:00: LHC ready for beam but now we have problems in the SPS: – MST extraction septum in fault; – Problem with the access chain. ● 15:00: Beam back in the SPS: – Injection setup in the LHC; – Loss map studies in IR3  looks good at 450 GeV; – Tested Radial-Loop using external RF frequency trims; Thursday :30 meeting

● 16:45: MPS fault in the SPS: – No beam for 1 hour; – Second loss map measurement; – Dispersion measurement at 450 GeV for Beam2; ● 18:15: Inject nominal bunches for Q-feedback & Damper studies: – Initial problems with BQM (SPS used old bunch structure); – Observe some ‘odd’ excitations in horizontal BBQ for B2; – Measure PLL and BBQ spectra with different damper gains  good result for PLL measurements; ● 19:10: Dump beams to prepare new fill: – XPOC error due to losses at TCDS Beam1  BLM thresholds for new – shorter bunch spacing?; Thursday :30 meeting

● Horizontal BBQ for Beam2: Thursday :30 meeting

● Thursday: First physics fill with 48 bunches per beam: – 20:30: Injection finished  protons per beam in 48 bunches;  x1 = 2.9  m;  y1 = 2.9  m;  x2 = 3.3  m;  y2 = 3.5  m; – 21:00: Start ramp; – 21:40: End ramp; – 22:20: Start Squeeze Initial luminosity: L = cm -2 sec -1 ; – 23:30: Stable physics; L = cm -2 sec -1 ;  fitted average emittances for bunch current of N b = :  = 4.05  m; with  * = 3.6m (average of three 1/  * measurement in IR5)  integrated luminosity = 240 nb -1 after 16 hours; Thursday – Friday :30 meeting

giulia papotti (BE/OP/LHC) Fill 1295 IPs: LR in 2 (33m) 1 LR in 8 (33m) 1 LR in 2 (22m) no Long Range interactions with Long Range giulia papotti (BE/OP/LHC)

● End of Fill studies: – Luminosity scans in all IPs (large scan in IP1); – Damper studies; – Orbit feedback test for radial loop correction; – 16:15: Beam dump; very clean & without any unusual losses ● Afternoon: – Cryo problem in Pt6 right after the beam dump. Friday :30 meeting

● Lumi scans in IR1:  average beam emittances:  x = 4.4  m  y = 4.9  m  growth of 10% to 20% over the fill! Friday :30 meeting

● Morning & Day: Recovery from Cryo problems: – 20:00: Cry recovered for pre-cycle in S56 and S67; – 22:15: Starting injection; – 22:30: Injection kicker fault - sparking (called experts); spark occurred after clean injection; – 22:30: Beams dumped due to Cryo problem for right IR5 triplet (back by 01:00); ● Preparing second fill with 48 bunches: – 03:30: Injection finished  protons per beam in 48 bunches;  x1 = 2.6  m;  y1 = 2.6  m;  x2 = 2.8  m;  y2 = 3.2  m; – 03:40: Start ramp; losses in IR3 at beginning of ramp;  Beams dumped by SIS TCDQ_B2 interlock triggered by the TCS_BEAM_OFFSET_B2; – 04:50: Trip of RCBYVS4.L1B1 during the ramp down combo;  power module to be exchanged on RCBYVS4.L1B1, access needed in Pt 1; Saturday :30 meeting

● Morning: Access following perturbation of electrical network: – 06:50: PC permit sector 45 lost due to perturbation on electrical network; ALICE and LHCb dipoles also tripped; – RD1.LR5 also down (water cable fault); – QPS: RQS.A12B2 and RQTF.A81B1 we changed QPS board; – 09:00: Access finished and experiments back up running; ● Morning and afternoon: Trying to get machine ready for beam: – 09:00: Start pre-cycle (RQTL11.L5B2 needed change of board channel and several ciruits tripped); – RQ6.L1B1/B2 tripped several times due to a bad contact (caused too low threshold) that was probably generated during intervention in the morning.  need access again. Access finished by 12:15. – 13:50: Machine ready for injection; – Asking for mastership resulted in a PM - with no beam in the machine - first triggered inputs in PM seem to be BLMs in 6  search for BPM expert; interventions finished by 18:00. Sunday :30 meeting

● Morning and afternoon: Trying to get machine ready for beam: – 09:00: Start pre-cycle (RQTL11.L5B2 needed change of board channel and several ciruits tripped); – RQ6.L1B1/B2 tripped several times due to a bad contact (caused too low threshold) that was probably generated during intervention in the morning.  need access again. Access finished by 12:15. – 13:50: Machine ready for injection; – Asking for mastership resulted in a PM - with no beam in the machine - first triggered inputs in PM seem to be BLMs in 6  search for BPM expert; interventions finished by 18:00. – 18:00: Starting injection; – 19:00: Staring over injection with nominal bunches  Beam dumped by BPM interlock in point 6 (BPM L & R for Beam 1); – 19:30: Problems in IP6 (BPM error: CALIBRATION MODE); fixed by 21:15; Sunday :30 meeting

● Third fill with 48 bunches per beam: – 22:20: Injection finished  protons per beam in 48 bunches; Emittances between 2.5  m and 3.0  m (measured in the SPS); – 22:30: Start ramp; – 00:40: Start Squeeze Initial luminosity: L > cm -2 sec -1 ; – 00:50: Stable beams after optimization: L = cm -2 sec -1 ;  fitted average emittances for bunch current of N b = :  = 3.35  m; with  * = 3.6m (average of three 1/  * measurement in IR5)  integrated luminosity = 190 nb -1 after 7.5 hours; Sunday – Monday :30 meeting

● Initial luminosity above cm -2 sec -1 ! Sunday-Monday :30 meeting

● Plan for the week: – Continue physics fills with 48 bunches; – Continue preparatory studies for bunch train injection; – Loss maps and  * measurement via Q1 modulation; ● Coordinators for week 34: – Ralph Assmann & Roger Bailey Monday :30 meeting

● Open Issues for next Technical Stop: – CMS cooling for central tracker. – Ion pumps in dump line MKB (B2 only 4 out of 8 pumps working; few days intervention). – BLM racks (in buildings SR1 and SR5 and both at position BY02): would like to correct the way the power cable for the multi-plug arrives inside the rack. – QPS boards: several boards had to switch from channel A to B. – Access team to replace oxydized connectors for PAD-PX24 (3 hours). – CV needs to replace a motorization of the water valve of the sector 56 (3h). – RCBH18.R7B2 – Miguel Cerqueira Bastos. – RCSSX3.L1 super blocked for cryo. Week :30 meeting