SYSTEM ® Value&Innovation I LEAN PROJECT MANAGEMENT FORUM ‘10 Aurora-CCPM Critical Chain Project Management with Intelligent Scheduling.

Slides:



Advertisements
Similar presentations
Simulating Ground Support Capability for NASAs Reusable Launch Vehicle Program Kathryn E. Caggiano Peter L. Jackson John A. Muckstadt Cornell University.
Advertisements

Work Breakdown Structures
Roadmap Agenda  iET Process Analyzer 3.0  iET CMDB Intelligence & Discovery 2.1  iET Enterprise 12  iET ITSM 6  iET Mobile ITSM for.
MIS 2000 Class 20 System Development Process Updated 2014.
Objectives Explain the purpose and various phases of the traditional systems development life cycle (SDLC) Explain when to use an adaptive approach to.
Enhancing Resource-Leveling via Intelligent Scheduling: Turnaround & Aerospace Applications Demonstrating 25%+ Flow-Time Reductions Rob Richards, Ph.D.
Chapter 1 Assuming the Role of the Systems Analyst
T-FLEX DOCs PLM, Document and Workflow Management.
Building Enterprise Applications Using Visual Studio ®.NET Enterprise Architect.
DECISION-MAKING SYSTEMS Decision Support Software.
1 Chapter 12: Decision-Support Systems for Supply Chain Management CASE: Supply Chain Management Smooths Production Flow Prepared by Hoon Lee Date on 14.
Chapter 7 Enterprise-Wide Information Systems
TechMIS LLC Proprietary Tracking Requirements And Compliance Engineering (TRACE ) Steve Collier/B. Squires/TechMIS LLC An affordable and user friendly.
CS Techniques Supporting Project Management (Part 4) Bilgisayar Mühendisliği Bölümü – Bilkent Üniversitesi – Fall 2009 Dr.Çağatay ÜNDEĞER Instructor.
Marakas: Decision Support Systems, 2nd Edition © 2003, Prentice-Hall Chapter Chapter 1: Introduction to Decision Support Systems Decision Support.
Review 4 Chapters 8, 9, 10.
Mgt 20600: IT Management & Applications Decision Support Systems Tuesday April 18, 2006.
Project Management and Scheduling
Professional Informatics & Quality Assurance Software Lifecycle Manager „Tools that are more a help than a hindrance”
National Finance Center’s 2008 Customer Forum EmpowHR 9.0 Billy Dantagnan Teracore.
What is Business Intelligence Business Intelligence (BI) encompasses the processes, tools, and technologies required to transform enterprise data into.
TIBCO Designer TIBCO BusinessWorks is a scalable, extensible, and easy to use integration platform that allows you to develop, deploy, and run integration.
ArcGIS Workflow Manager An Introduction
Lesson №2. is the unique activity that has a beginning and an end time, aimed at achieving a predetermined result/goal, the creation of a specific, unique.
Katanosh Morovat.   This concept is a formal approach for identifying the rules that encapsulate the structure, constraint, and control of the operation.
Primavera Highlights During COLLABORATE  Primavera Key Note: Making the Most of Your Oracle Primavera Investment Dick Faris, Primavera Co-Founder & Oracle.
9/10/20151 Hyperion Enterprise 6.5 New Features & Functionality Robert Cybulski, CPA Finit Solutions.
These materials are prepared only for the students enrolled in the course Distributed Software Development (DSD) at the Department of Computer.
© Electronic Data Processing PLC myViewpoint Business & Sales Intelligence for the MultiValue Manager.
By: Amber Shepard   Microsoft Outlook is an client and personal information manager (PIM) that's available as part of Microsoft's Office suite.
Name Class.  Review of Implementation Process  Identify Critical Success Factors  Define Change Management (big picture)  Define Role of Corporate.
1 ISA&D7‏/8‏/ ISA&D7‏/8‏/2013 Systems Development Life Cycle Phases and Activities in the SDLC Variations of the SDLC models.
Intelligent Planning & Scheduling Platform for Lean Manufacturing and Optimization of Changeovers Rob Richards, Ph.D. Stottler Henke Associates, Inc. IFPAC.
At A Glance VOLT is a freeware, platform independent tool set that coordinates cross-mission observation planning and scheduling among one or more space.
Homework 3 – Sample Solution Targeted Application –Electronic medical records (EMR) system in the “Designing Human-Centered Distributed Information Systems”
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
Ad Hoc Graphical Reports Ad Hoc Graphical Reports Copyright © Team #4 CSCI 6838 Spring CSCI Research Project and Seminar Team# 4 (
Systems Analysis and Design in a Changing World, Fourth Edition
Search Engine Optimization © HiTech Institute. All rights reserved. Slide 1 What is Solution Assessment & Validation?
GRID Overview Internet2 Member Meeting Spring 2003 Sandra Redman Information Technology and Systems Center and Information Technology Research Center National.
March 2004 At A Glance autoProducts is an automated flight dynamics product generation system. It provides a mission flight operations team with the capability.
Understanding StarTeam Enterprise Advantage Course #4124.
Modeling & Simulation Experience & Applications Overview for the Aerospace Education Program “It's about routine, affordable, and safe access to and from.
Workforce Scheduling Release 5.0 for Windows Implementation Overview OWS Development Team.
August 2003 At A Glance The IRC is a platform independent, extensible, and adaptive framework that provides robust, interactive, and distributed control.
RIA to visualize the health of a project Team #4 Midterm presentation February 28,2008.
Windows SharePoint Services. Overview Windows SharePoint Services (WSS) Information Worker Infrastructure component delivered in Windows Server 2003 Enables.
ITEC 1010 Information and Organizations Chapter V Expert Systems.
Software Requirements for the Testing of Prototype Correlator Sonja Vrcic Socorro, December 11, 2007.
Master Correlator Control Computer (MCCC) Requirements & Status Sonja Vrcic Socorro, December 12, 2007.
Week 1 Reference (chapter 1 in text book (1)) Dr. Fadi Fayez Jaber Updated By: Ola A.Younis Decision Support System.
Active-HDL Server Farm Course 11. All materials updated on: September 30, 2004 Outline 1.Introduction 2.Advantages 3.Requirements 4.Installation 5.Architecture.
M. Caprini IFIN-HH Bucharest DAQ Control and Monitoring - A Software Component Model.
VIEWS b.ppt-1 Managing Intelligent Decision Support Networks in Biosurveillance PHIN 2008, Session G1, August 27, 2008 Mohammad Hashemian, MS, Zaruhi.
Final Review Systems Analysis and Design in a Changing World, 4th Edition 1 Final Review u Chapters 1-6, 8-10, 13, 14, 15 u Multiple choice, short answer,
IS&T Project Reviews September 9, Project Review Overview Facilitative approach that actively engages a number of key project staff and senior IS&T.
A Schedule Optimization Tool for Destructive and Non-Destructive Vehicle Tests Jeremy Ludwig, Annaka Kalton, and Robert Richards Stottler Henke Associates,
Building Enterprise Applications Using Visual Studio®
Key Features Advantages over PDF sharing Use Cases Clients
Fundamentals of Information Systems, Sixth Edition
Performance Management Microsoft Office PerformancePoint Server 2007
INTELLIGENT SCHEDULING BENEFITS
Course: Module: Lesson # & Name Instructional Material 1 of 32 Lesson Delivery Mode: Lesson Duration: Document Name: 1. Professional Diploma in ERP Systems.
Microsoft Project Past, Present and Future
King Saud University College of Engineering IE – 462: “Industrial Information Systems” Fall – 2018 (1st Sem H) Introduction (Chapter 1) part.
CAD DESK PRIMAVERA PRESENTATION.
IEEE Aerospace Conference 2019 Rob Richards, Ph.D.
Pacific International Maritime Conference 2019
Presentation transcript:

SYSTEM ® Value&Innovation I LEAN PROJECT MANAGEMENT FORUM ‘10 Aurora-CCPM Critical Chain Project Management with Intelligent Scheduling

I LEAN PROJECT MANAGEMENT FORUM 2 About Stottler Henke Applies artificial intelligence and other advanced software technologies to solve problems that defy solution using traditional approaches. Planning & Scheduling, e.g., Aurora-CCPM Education & Training Decision Support Knowledge Management & Discovery Founded in

I LEAN PROJECT MANAGEMENT FORUM 3 Aurora-CCPM History st Intelligent Scheduling Project – NASA’s Kennedy Space Center (KSC) 1990’s Several IS projects independent of each other (most at NASA) 1999 Aurora conceived to subsume all 2000 Aurora designed and prototyped 2001 – 2003 Main Aurora implementation st Aurora application delivered 2005 Critical Chain enhancement: Boeing & others Driven by need for Critical Chain capabilities that no one else had

I LEAN PROJECT MANAGEMENT FORUM Aurora-CCPM Critical Chain Summary Enterprise Level Critical Chain Project Management Software Multi Project Completely stand-alone Does NOT depend on any other product However, designed to interface with other project management software and exchange information with databases 4

I LEAN PROJECT MANAGEMENT FORUM 5 Aurora Unique Capabilities Enterprise level Critical Chain Multiple-pass intelligent resource-constrained scheduling Mixed-mode scheduling providing both forward and backward scheduling, available on a task-by-task basis. Schedule Rationale – Aurora includes the rationale for each task on why it was schedule where it was schedule. Designed to interface with other tools

I LEAN PROJECT MANAGEMENT FORUM Flexible Deployment Completely stand-alone application on Windows, Linux & Mac Standalone Aurora with Database access Aurora Server version with Web access Flexible deployments –Windows XP to Windows Server –Linux –Mac –32 or 64-bit 6

I LEAN PROJECT MANAGEMENT FORUM Potential Workflow w/ Current Project Mgmt. Software: E.g., Primavera P6 7 Build in Primavera P6 PMs use updated Primavera P6 model for execution Schedule in Aurora Enter status updates into Primavera P6 Transfer to Aurora Transfer results to Primavera P6 Transfer status information back to Aurora

I LEAN PROJECT MANAGEMENT FORUM 8 Aurora 3 rd Party Interface For example: Primavera P6 & DB / SAP Primavera P6Aurora Primavera P6Aurora DB / SAP AuroraPrimavera P6DB / SAP XML

I LEAN PROJECT MANAGEMENT FORUM 9 Aurora-CCPM Screenshots: Overview

I LEAN PROJECT MANAGEMENT FORUM 10 A Small Critical Chain Project (Critical Chain in Yellow w/ Bold Outline)

11 Fever Chart

12 Task Priority Report

I LEAN PROJECT MANAGEMENT FORUM 13 Aurora / Aurora-CCPM Applications Boeing 787 Aircraft Assembly (replaced 20 year, in- house Timepiece product) Space Shuttle Processing Space Station Processing Facility (SSPF) floor space and resources Navy Ship System Upgrades Crew Exploration Vehicle (CEV) In-space crew/resource Ballistic missile intercepts Electronic Intelligence (ELINT) aircraft/sensors In every domain attempted, Aurora has surpassed all existing scheduling systems

I LEAN PROJECT MANAGEMENT FORUM Boeing Airplane Assembly Scheduling Very large, complex models Large numbers of resource contentions, constraints Widely distributed users working on different projects Part of integrated management system Accepts inputs from corporate modeling system, sends outputs to shop floor management system

I LEAN PROJECT MANAGEMENT FORUM Learjet Multi-Phase Assembly Scheduling Many small, inter-related models Each model must be managed separately, but may impact other models Significant resource contention, moderate additional constraints In long term, models to be used both for long-term projections and short-term recovery management

I LEAN PROJECT MANAGEMENT FORUM Medical Resident Scheduling Involves allocating residents for hospital staffing and educational purposes 150+ residents must be scheduled for a full year Extensive rules provide flexible constraints for an acceptable schedule

I LEAN PROJECT MANAGEMENT FORUM At NASA’s Kennedy Space Center, Aurora schedules the use of floor space and other resources at the Space Station Processing Facility, the world’s largest low-particle clean room where International Space Station components are prepared for flight. 17

I LEAN PROJECT MANAGEMENT FORUM 18 “Aurora is used daily to support major processing and space shuttle launch decisions; to coordinate our launches with those of Russia, Japan, and the European Space Agency; and to determine NASA's launch requirements and flight rates," says NASA Shuttle Processing Manager Tom Overton. "It enables us to generate complex schedules in a few hours, compared to days or weeks required by our previous scheduling systems."

I LEAN PROJECT MANAGEMENT FORUM Acquisition Decision Expert Planning Tool (ADEPT) Aurora is included in ADEPT, an intelligent acquisition and planning tool for upgrading U.S. Navy systems.

I LEAN PROJECT MANAGEMENT FORUM Temporis Aurora is included in Temporis, a scheduling system by the United Space Alliance, to be used by NASA crew members on-board next generation of space vehicles, and is currently being tested on the International Space Station (ISS)

I LEAN PROJECT MANAGEMENT FORUM Phased Array Smart Allocation and Planning (PASAP) Solution to optimize beam allocation and path planning solutions for satellite communication events with Geodesic Dome Phased Array Antennae (GDPAA)

I LEAN PROJECT MANAGEMENT FORUM Aurora-CCPM Screenshots & Videos

I LEAN PROJECT MANAGEMENT FORUM 23 Aurora: Main Project View

24 Resource Sets

25 Tabular Editor

Tabular Editor: Configuration 26

27

28

I LEAN PROJECT MANAGEMENT FORUM Video: Aurora-CCPM Project Overview & Constraints 29

I LEAN PROJECT MANAGEMENT FORUM Resource Contention: Task 6 30 Single Element Display Overall schedule flow Gantt Chart View The Single Element Display in Aurora helps the user visualize the relationships between tasks: Blue-grey lines denote a resource-constrained work flow Red lines denote temporally-constrained work flow Referring to the three diagrams to the right: Task 6 can start any time after Task 2 is completed (red line in Single Element Display), but must wait for Task 5 to release resources (blue-grey line). Tasks 3 and 8 must wait for 6 to release resources before they can start, as shown in the Gantt Chart View Task 7 starts after Task 6 completes (red line in Single Element Display)

I LEAN PROJECT MANAGEMENT FORUM Resource Contention: Visual Viewing resource contentions in Aurora 31 In this sample schedule, each task has a resource requirement attached as follows Resource-constrained relationship Note that there is a total amount of only 5 resources. Tasks 2, 4, and 5 are started at the same time (5 resources used). Task 2 completes, but there are not enough resources left to start Task 6, so Task 6 must wait until Task 5 is complete. Task #Resources Needed Aurora shows you this resource- constrained relationship with a blue-grey line between the two Tasks.

32 Calendars

33 Histogram

34

35

36 Spatial Plot

37 Personnel View Activities delayed by resource contention in blue

I LEAN PROJECT MANAGEMENT FORUM 38 Schedule Rationale Aurora includes the rationale for each task on why it was scheduled where it was scheduled, so it is easy to determine what changes could be made for a task to occur earlier.

39 Edit Tab: Schedule Results

40

I LEAN PROJECT MANAGEMENT FORUM Video Spatial Plot, Single Element Display & Explanation Facility 41

I LEAN PROJECT MANAGEMENT FORUM Gantt Chart in Execution 42

43 Gantt Chart with right-click menu

I LEAN PROJECT MANAGEMENT FORUM Video Execution Mode Fever Chart Task Priority List 44

45 Gantt Chart: Multiple Projects Activities delayed by resource contention in blue

46

GRACIAS POR SU ATENCIÓN Rob Richards, Ph.D. Project Manager Stottler Henke Associates, Inc. SYSTEM ® Value&Innovation