Greg Hainsworth, P.E. M&R Workshop February 2014
Route 13 Puncheon Run South State Street
Bay Road Puncheon Run
Original plan of execution ◦ Maintain through traffic ◦ Replace one lane at a time ◦ 2 to 3 week duration Contractor Proposal ◦ Complete shut down of all N/B traffic ◦ Replace both lanes simultaneously ◦ 72 hour duration – supported by hourly schedule ◦ Contingency resources on standby
Atlantic Concrete ◦ Air Temp – 70F / Mix Temp – 77F ◦ Type 1S cement ◦ Class A mix with 7.5 sacks per CY ◦ Air content 3.8% ◦ Slump 7-inches ◦ Non Chloride Accelerator ◦ Super Plasticizer ◦ Water reducer
12 hour sure cure break – 2040 psi.
Contractor Innovation ◦ Equipment ◦ Manpower Producer Mix Design Smoothness ◦ Roller screeds / Bull Floats – Surface Chatter Temporary Traffic Control plans
American Infrastructure JJID Atlantic Concrete Dave Angstadt, South 1 Construction Gerry Nagyiski, Traffic David Dodd & M&R Concrete Staff