Freedom Park Schedule Design Start DateJune 8, 2005 Construction Start DateDecember 10, 2007 Substantial Construction CompletionJune 2009 Grand OpeningOctober 2009 Cost Land Acquisition$ 19.2 Million Design$ 1.3 Million Construction$ 10 Million $ 30.5 Million Funding Florida Communities Trust $ 6 Million (Construction) SFWMD$1.5 Million (Design & Construction) SFWMD/BCB$10 Million (Property Purchase) * Transportation Impact Fees$2.7 Million Ad Valorem Taxes$10.3 Million (Design, Purchase, Construction) * Part of $20 million for purchase of roadways in Southern Blocks for Everglades Restoration
Lake excavation for water treatment Cut & fill Removal of exotic plants Underground utilities Installation of storm water structures Work in Progress DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL UTILITIES & STORM STRUCTURES INSTALLATION OF IRRIGATION SYSTEMS LANDSCAPING & PLANTING BOARDWALK CONSTRUCTION SITE WORK FINAL COMPLETION EDUCATIONAL BLDG, RESTROOMS & MAINTENANCE BLDG PARKING, PAVING, SIDEWALKS Freedom Park
Building boardwalk in lake “D” Lime rock stone for bus loop Fill & compact site for educational building Planting of native plants in wetlands area Installation of irrigation systems Construction of boardwalk in wetlands Work in Progress DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL UTILITIES & STORM STRUCTURES INSTALLATION OF IRRIGATION SYSTEMS LANDSCAPING & PLANTING BOARDWALK CONSTRUCTION SITE WORK FINAL COMPLETION EDUCATIONAL BLDG, RESTROOMS & MAINTENANCE BLDG PARKING, PAVING, SIDEWALKS Freedom Park
Start foundation for educational building Planting native plants in wetlands area Landscaping & planting around lakes Work in Progress DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL UTILITIES & STORM STRUCTURES INSTALLATION OF IRRIGATION SYSTEMS LANDSCAPING & PLANTING BOARDWALK CONSTRUCTION SITE WORK FINAL COMPLETION EDUCATIONAL BLDG, RESTROOMS & MAINTENANCE BLDG PARKING, PAVING, SIDEWALKS Freedom Park
Observation Decks in lakes “B” & “C” Planting of large trees Planting of gopher tortoise preserve Work in Progress DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL UTILITIES & STORM STRUCTURES INSTALLATION OF IRRIGATION SYSTEMS LANDSCAPING & PLANTING BOARDWALK CONSTRUCTION SITE WORK FINAL COMPLETION EDUCATIONAL BLDG, RESTROOMS & MAINTENANCE BLDG PARKING, PAVING, SIDEWALKS Freedom Park
Completion of Decking on boardwalks through Wetland Limestone base for paths Planting of trees around lakes Work in Progress DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL UTILITIES & STORM STRUCTURES INSTALLATION OF IRRIGATION SYSTEMS LANDSCAPING & PLANTING BOARDWALK CONSTRUCTION FINAL COMPLETION SITE WORK EDUCATIONAL BLDG, RESTROOMS & MAINTENANCE BLDG PARKING, PAVING, SIDEWALKS Freedom Park
Completed in installation of the 20” Pipe from the river to lake “D” Planting of Littorals in lakes Installation of roofs on the NW buildings and pavilions Work in Progress DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL UTILITIES & STORM STRUCTURES INSTALLATION OF IRRIGATION SYSTEMS LANDSCAPING & PLANTING BOARDWALK CONSTRUCTION FINAL COMPLETION SITE WORK EDUCATIONAL BLDG, RESTROOMS & MAINTENANCE BLDG PARKING, PAVING, SIDEWALKS Freedom Park
Completion At Educational Building: Roof Siding Decking All Rough MEP Windows Work in Progress Freedom Park DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL INSTALLATION OF IRRIGATION SYSTEMS LANDSCAPING & PLANTING BOARDWALK CONSTRUCTION FINAL COMPLETION Education Building PARKING, AREA Paver
View of the Oak Hammock from one of the paved paths
A completed pavilion along the boardwalk
Storm Structures from Goodlette Frank Rd
Overflow for the recharge well
A Finished Pavilion
Education Building
Freedom Memorial