ILC TRANSPORT AND INSTALLATION Questions from last CES: Beam height explanation, Transport implications of sloping access tunnels proposed for access to.

Slides:



Advertisements
Similar presentations
SiD Surface assembly Marco Oriunno (SLAC) MDI-CFS Meeting Sep. 4-6, 2014, Ichinoseki (Japan)
Advertisements

SPL Intercavity support Conceptual design review 04/11/ A. Vande Craen TE/MSC-CMI.
MODULE TRANSPORT CLIC Module Working Group 27 September 2010 Keith Kershaw CERN EN-HE.
Plasma Wakefield (AWAKE) Project Meeting 18 October 2012 Civil Engineering Feasibility Issues for the West Area EDMS : John Osborne GS-SE.
Pipe Supports and Restraints
Collimation Remote Handling Highlights from work for collimation remote handling and remote survey. Plans Keith Kershaw EN-HE 14 June 2011.
Remote Handling design progress for the Collimation Upgrade project Keith Kershaw EN-HE 6 June 2011.
Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.
Global Design Effort - CFS for Asian Single Tunnel Configuration Design Progress Masanobu Miyahara KEK.
Update on alignment kit and stave 250 frame M.Gibson (RAL) 1.
Global Design Effort - CFS ILC CFS and Global Systems Meeting 1 ILC CFS AND GLOBAL SYSTEMS MEETING CONVENTIONAL FACILITIES AND SITING GROUP GENERAL.
CES Status J.Osborne 6 November 2009 Status Report from Civil Engineering and Services Working Group J.Osborne GS/SEM for CES Working Group.
Lecture 23 Site Selection. Layout and Design of Grain Storage Systems  Two general (guiding) principles:  closed loop - deliver or receive grain from.
Conceptual Design Study - Cryogenic Requirements How to decide the layout of ILC cryogenic system Conceptual design of cryogenic system Layout of cryogenic.
Cryogenic Experts Meeting (19 ~ ) Cooling scheme discussion for 300 Tm High Energy Beam Transfer line (HEBT) with large inclination MT/FAIR –
EHN1 Extension overhead crane coverage Keith Kershaw CERN EN-HE.
Transport and handling at CERN for FAIR
ILC experimental area - How to ‘develop’ CFS details for TDP (cavern size, number of shafts, HVAC, EL spec etc) ? - KEK site specific issues CFS V.Kuchler.
Global Design Effort - CFS TILC09 and GDE AAP Review Meeting - Tsukuba, Japan 1 GDE ACCELERATOR ADVISORY PANEL REVIEW CONVENTIONAL FACILITIES.
1 CLIC / ILC Collaboration for CES issues JOHN OSBORNE – CES 8 April 2009.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
6th ST workshop, Thoiry, 1-3 April ST-HM Design Section Strategy and working methods 3rd April 2003 C. Bertone ST-HM.
1 Global Design Effort TILC08 - WG1 Summary WG-1: Cost Reduction Studies J. Carwardine, T. Shidara, N. Walker (For WG-1 participants)
LHC Insertions Upgrade Working Group (LIUWG) Space available in tunnel Y. Muttoni.
Agenda : CLIC Civil Engineering and Services (CES) WG.
Andrew Moss ASTeC CM32 9t h February 2012 RAL MICE RF System.
Cryomodule Development at Fermilab Don Mitchell Representing the SRF engineering community at Fermilab April 20, 2009 Tsukuba, Japan TILC09.
Global Design Effort - CFS ILC Accelerator Design and Integration Meeting 1 ILC AD&I MEETING CONVENTIONAL FACILITIES AND SITING GROUP UPDATE V.
10/2010 IWLC2010 Global Design Effort 1 Brief Overview of Interaction Region Conventional Facilities in RDR Times Presenter Tom Lackowski.
Civil Engineering and Services - drawings for CDR - CDR chapter J.Osborne and M.Gastal for CES WG 1.
Americas Region: T4CM Status and Plans H. Carter TD SRF Dev. Dept. July 14, 2006.
April 23rd-24th 2013Handling Engineering Group. Introduction to CERN April 23rd-24th 2013Handling Engineering Group2  CERN: European Organization for.
Transport of the CLIC Modules and Elements CLIC Workshop October 2007 Two Beam Hardware and Integration Working Group Keith Kershaw (CERN)
Transport and Handling (T&H) considerations for HL-LHC
John Osborne : GS-SEM Civil Engineering 18 May 2009 CES 9 June News from ILC Japan CFS review 1-3 June 2010 :
RICH1 Gas Enclosure Installation. Experimental Area Meeting at CERN on 21st June 2006 Bill Cameron (Imperial College London) on behalf of the RICH1 team.
Transport & Handling of Detectors TAN Workshop S. Prodon –
Transport need for SPS external dump to the new dump cavern area LIU-SPS external beam dump JL GRENARD EN-HE
Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.
LMQXFA Cold Mass Assembly Antonios Vouris Fermilab February 3, 2016.
Global Design Effort - CFS Oct IWLC ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto.
Europe / CERN studies for SB2009 ILC Re-Baseling J.Osborne CERN (CFS & CES) 2009 Linear Collider Workshop of the Americas 28 September - 4 October 2009.
March 22, –  Design Concept & Hall Layout  Access Tunnel  Top heading Tunnel  Displacement of detector hall by push-pull operation.
Cryostat & LHC Tunnel Slava Yakovlev on behalf of the FNAL team: Nikolay Solyak, Tom Peterson, Ivan Gonin, and Timergali Khabibouline The 6 th LHC-CC webex.
CLIC MODULE TRANSPORT AND INSTALLATION Keith Kershaw CES, 8 October 2008.
Long-Baseline Neutrino Facility LBNF Cryostats Systems Requirements on FSCF Marzio Nessi LBNF/DUNE DOE/SC CD-3a Director’s Review October 27-29, 2015.
Cryogenic Cooling Schemes for the SPL U. Wagner TE-CRG.
SPSU – May 19, 2009 – Resources needed for SPS coating project– J. Bauche 1 Coating of the SPS Main Dipoles Vacuum Chambers: Resources Needed for Project.
Experimental hall in Japanese mountain site 2011/11/30 Yasuhiro CFS Webex meeting 1.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
Design considerations for the FCC electrical network architecture FCC week 2016, Rome, April 2016 Davide Bozzini - CERN/EN/EL With the contribution.
Logo area Handling Engineering Requirements EN-HE Group Bruno Feral – EN/HE EDMS HL-LHC CE Consultant Kick-Off Meeting – 31/05/2016.
H. Hayano(KEK), B. Petersen(DESY), T. Peterson(FNAL),
SIS 100 Vacuum chamber Recooler String system Components
CBM magnet overview of the BINP work
CLIC Handling Engineering Update
CLIC Civil Engineering Update
SBN Far Detector Installation & Integration
CLIC Civil Engineering & Infrastructure Working Group Meeting
Yasuhiro Sugimoto 2012/2/1 ILD integration meeting
Marco Oriunno (SLAC), March 12, 2014 MDI WG
Experimental hall design in Japanese site
CLIC / ILC Collaboration for CFS works
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
Latest ILC tunnel cross section May 2017
Status of Cryogenics Facilities Design
Optimum cryomodule length at the ESS
RDR Baseline Layouts for Interaction Region
Overview of Day One – 29 Feb 2016
LIFT,ESCALATOR AND MOVING WALKS
Presentation transcript:

ILC TRANSPORT AND INSTALLATION Questions from last CES: Beam height explanation, Transport implications of sloping access tunnels proposed for access to underground areas of Asian site. Acknowledgements: Jerry Leibfritz, FNAL David Smekens, CERN Caterina Bertone, CERN Keith Kershaw, EN-HE CERN CES 11 March 20091

Reason for the (relatively high) height of the cryomodules above the floor (1) Response from Jerry Leibfritz, FNAL (1) This is what is used at DESY for FLASH and CMTS, and also at the Fermilab ILCTA. It is based on the large support girder that sits underneath the first and last cryomodules of a string to counteract the large vacuum load and prevent movement of the cryomodule. The support stand sits on top of this girder. Keith Kershaw, EN-HE CERN CES 11 March

Picture of the first cryomodule on its green support girders at Fermilab. ( cryogenic components not installed ) Keith Kershaw, EN-HE CERN CES 11 March 20093

Reason for the (relatively high) height of the cryomodules above the floor (2) Response from Jerry Leibfritz, FNAL (continued) The cryogenic feedbox and endcaps are designed for this elevation and it would have been too expensive for us at Fermilab to redesign this, so we used basically the same design as DESY. When we were initially laying out the ILC tunnel, we tried to maximize the use of space, so we set the elevation of the cryomodule to be in the widest part of the diameter of the tunnel, allowing us to move it as close to the wall as possible. For a machine as big as the ILC, these components could be redesigned, so the cryomodule sits lower, but it would require some engineering effort. Keith Kershaw, EN-HE CERN CES 11 March

SLOPES… Effect of slope on vehicle design: Need more traction force Cooling of motors (duty factor) Need more braking force Cooling of brakes Space Keith Kershaw, EN-HE CERN CES 11 March 20095

Asian site Keith Kershaw, EN-HE CERN CES 11 March 20096

CLIC longitudinal section Keith Kershaw, EN-HE CERN CES 11 March 20097

CLIC access ramp tunnel summary Figures based on CLIC Longitudinal section drawing data. Access Point Number1153 upper height (m) lower height (m) delta h (m) slope (%)878 length (m) Keith Kershaw, EN-HE CERN CES 11 March 20098

NOTES ON SLOPES Standard electric vehicles Typically 1.5-2% slope for continuous use at full rated load with increased slope the load capacity or the use factor reduces. (see performance chart) Encyclopedie de la Manutention “rampe ≥ 7% = problème délicate” (this is with unbraked trailers) Effect of 2% slope is to double traction force needed compared with horizontal surface. Keith Kershaw, EN-HE CERN CES 11 March 20099

10

Keith Kershaw, EN-HE CERN CES 11 March

Example on effect of slope In the example a tractor with a nominal towing capacity of 20 tonnes can be used on a 7% slope to tow a 6 tonne trailer a maximum of 3500m in one hour. Keith Kershaw, EN-HE CERN CES 11 March

Other slope experience at CERN Vehicles for LHC warm magnet installation: Specified max slope 12% for short distances. During testing on 7% slope (several passes) overheated after approx 1hour. Special purpose fork lift: customised for 14% slope (needed continuous forced ventilation for brakes and motors) Difficult to find supplier willing to do this. Keith Kershaw, EN-HE CERN CES 11 March

Slope conclusions General comments at this stage: % slope means can use standard vehicles (lowest cost most reliable solution) Up to 7 or 8% slope achievable by reducing capacity to approx one third of nominal (space issues?). Any steeper slopes will mean that it becomes more difficult to use standard equipment –this will have cost and reliability implications. What are slope options for Asian site? Keith Kershaw, EN-HE CERN CES 11 March