CSCM Project Status and Prospects Andrzej Siemko on behalf of the CSCM project core team: Mike Koratzinos, Jens Steckert, Hugues Thiessen and Arjan Verweij.

Slides:



Advertisements
Similar presentations
RRR Measurements in S23 during LS1 Emmanuele Ravaioli Daniel Rasmussen Scott Rowan Thanks to Z. Charifoulline, R. Denz, J. Steckert, H. Thiesen, A. Verweij.
Advertisements

February 2009 Summary of Chamonix 09 Steve Myers.
ELECTRO THERMAL SIMULATIONS OF THE SHUNTED 13KA LHC INTERCONNECTIONS Daniel Molnar, Arjan Verweij and Erwin Bielert.
REVIEW OF THE CRYOGENIC BY-PASS FOR THE LHC DS COLLIMATORS ELECTRICAL CIRCUIT MODIFICATION, INCLUDING OPERATIONAL CONSIDERATIONS PRESENTED BY A. SIEMKO.
CRYOGENICS AND POWERING
HQ02b : Test plan overview Test plan overview: Main elements and Open questions H. Bajas TE-MSC-TF H. BAJASUpdate meeting on HQ02b assembly and test plan02/05/2014.
The LHC energy: past and future XXIX Workshop on Recent Advances in Particle Physics and Cosmology, Saturday, 16 April 2011 Mike Koratzinos, CERN.
1 Copper Stabilizer Continuity Measurement Project CSCM Mini Review Powering Implementation H. Thiesen 30 November 2011.
Session th January 2010 R.Schmidt TE/MPE Hardware Commissioning 2010 and beyond R.Schmidt.
Overview of the recommendation on LHC Splices Consolidation Frederick Bordry, head of the CERN Technology Department, has called for a series of three.
LMC 30 LPC A. Verweij, TE-MPE. 30 Sept 2009, LMC meeting 1.9 K, 0 T, 7.5 kA run Heat pulse.
A. Verweij, TE-MPE. 3 Feb 2009, LHC Performance Workshop – Chamonix 2009 Arjan Verweij TE-MPE - joint stability - what was wrong with the ‘old’ bus-bar.
A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.
Chamonix Risks due to UPS malfunctioning Impact on the Superconducting Circuit Protection System Hugues Thiesen Acknowledgments:K. Dahlerup-Petersen,
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
CERN Rüdiger Schmidt FCC week 2015 Long Magnet Stringpage 1 Incident September 19 th Architecture of powering and protection systems for high field.
1 Copper Stabilizer Continuity Measurement Project Copper Stabilizer Continuity Measurement Status & Plans – May 2011 MPE-TM – 12 May 2011 M. Koratzinos,
LHC diodes: Status report (for information)
1 CSCM-7TeV Powering Implementation and ELQA Third LHC Splice Review November 2012 M. Bajko, M. Bernardini, B. Bordini, k. Brodzinski, J. Casas-Cubillos,
CSCM type test: Diode Leads and Diodes Gerard Willering & Vincent Roger TE-MSC With thanks to Bernhard Auchmann, Zinour Charifoulline, Scott Rowan, Arjan.
Training LHC Powering R. Denz Quench Protection System R. Denz AT-MEL.
LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, slides  Status of LHC: electrical connections  Description of shunt.
MP3 recommendations from June 2013-Feb 2014 Arjan Verweij on behalf of the MP A. Verweij, LSC meeting 7/2/2014 One of the tasks of the MP3 is.
L. Serio COPING WITH TRANSIENTS L. SERIO CERN, Geneva (Switzerland)
Measurement and data extraction. How to measure the splice and diode interconnections. Accuracy and issues of these measurements. Data extraction issues.
LHC Enhanced Quench Protection System Review 24 – 26 February 2009.
A PROPOSAL TO PULSE THE MAGNET BUSES TO VALIDATE SPLICE QUALITY H. Pfeffer 3/7/09 Version 4.
Power Converters and DC cablesSlide 1/.. LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005 Water cooled cables warm bus bars power converter.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
NQPS commissioning …a long way to go. Topics nQPS component overview Enhancements in Firmware Commissioning diagram Detailed task list Summary.
Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel.
Cold powering test results of MBHSP102 Gerard Willering, TE-MSC-TF With thanks to Jerome and Vincent and all others from TF for their contribution.
1 A. Verweij, TE-MPE. LHC Performance Workshop – Chamonix Feb 2010 Arjan Verweij TE-MPE - type of defects - FRESCA tests and validation of the code.
TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb R. Denz TE-MPE-CP on behalf of the QPS team QPS Upgrade and Re-commissioning.
1 LHC Status LHCC 23 rd September 2009 Steve Myers.
LHC Machine Status Report Mike Lamont for the LHC team Acknowledgements: Mirko Pojer, Matteo Solfaroli, Katy Foraz et al.
HWC with nQPS Splice Monitoring Zinur Charifoulline & Bob Flora Real Time (~10 sec) BUS Voltage Energy Extraction Trip 300 µV threshold on Un-bypassed.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
TE/MPE-MS MPE-TM meeting 14/06/2012, Richard Mompo Updated ELQA test procedure Co-authors: Nuria Catalan Lasheras Mateusz Bednarek Giorgio D’Angelo Richard.
Main dipole circuit simulations Behavior and performance analysis PSpice models Simulation results Comparison with QPS data Ongoing activities Emmanuele.
LHC circuit modeling Goal: Create a library of electrical models and results for each circuit Useful and usable for the next 20 years…… Web site cern.ch/LHC-CM.
MPE Workshop for LS1 Summary of Global Activities Thanks to Speakers Arjan Verweij Hugues Thiesen Zinur Charifoulline Kajetan Fuchsberger.
MPP Meeting 07/03/2007 MPP Main Ring Magnet Performance Panel Meeting Wednesday 7th March 2007 Agenda: 1)Matters arising 2)Recommendations for the case.
MPE Workshop 14/12/2010 Analysis of the RB and RQF/D splice data recorded with nQPS - status and plans towards full automation Analysis of the RB and RQF/D.
CSCM (Thermal Amplifier) Sequence and detailed planning 07/10/2011 M.Solfaroli Thanks to: K.Brodzinski, G.D’Angelo, M.Koratzinos, M.Pojer, R.Schmidt, J.Steckert,
MQXFS1 Test Results G. Chlachidze, J. DiMarco, S. Izquierdo-Bermudez, E. Ravaioli, S. Stoynev, T. Strauss et al. Joint LARP CM26/Hi-Lumi Meeting SLAC May.
The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar ( )
Machine Protection Review, Markus Zerlauth, 12 th April Magnet powering system and beam dump requests Markus Zerlauth, AB-CO-IN.
Quench behavior of the main dipole magnets in the LHC By Gerard Willering, TE-MSC On behalf of the MP3-CCC team Acknowledgements TE-MSC, MP3, BE-OP, TE-MPE,
CSCM Test description and Risk assessment  Goal  The typical and ultimate current cycle  Test sequence for type test and regular test  Risk assessment.
Introduction, Andrzej Siemko
HL-LHC IT STRING and Series test of SC link
11T Magnet Test Plan Guram Chlachidze
Minimum Hardware Commissioning – Disclaimer
Giorgio on behalf of ELQA team
12 October 2009 RRB Plenary R.-D. Heuer
Powering the LHC Magnets
Dipole diode lead resistance measurement
Dipole circuit & diode functioning
Powering from short circuit tests up to nominal
Circuits description and requirements - Closed Session-
Detailed global view on protection and detection of the circuits
3 issues identified in review
Do the splices limit us to 5TeV – plans for the 2010 run
Andrzej Siemko (CERN) and Marco Zanetti (MIT)
Other arguments to train two sectors to 7 TeV
Electrical measurements and diagnostics
Presentation transcript:

CSCM Project Status and Prospects Andrzej Siemko on behalf of the CSCM project core team: Mike Koratzinos, Jens Steckert, Hugues Thiessen and Arjan Verweij

Introduction The major factor for limiting the LHC energy at 3.5TeV is the continuity of the copper stabilizer close to a (non-perfect) superconducting joint. This continuity has been measured in The measurements are partial and have large errors. The measurements are also indirect, so we need to rely on simulation, which, to compensate for the lack of knowledge of the joint condition, has deliberately been made rather conservative. Even if the 2009 measurements were accurate, there is no guarantee that a joint cannot deteriorate with time

A reminder of recommendations and proposals regarding the CSCM: Recommendation: (R9) Launch the Copper Stabilizer Continuity Measurements Project aimed at the measurement of all the copper stabilizer joints in all the LHC sectors during the technical stop at the end of On the basis of these measurements the safe 2012 operation beam energy can then be determined. Conclusions of Steve Myers from Chamonix 2011: Recommendations of the 3 rd MAC meeting:

The CSCM Project The CSCM (Copper Stabilizer Continuity Measurement) is a qualification tool that can determine the maximum safe energy per sector by testing the main circuits, RB and RQ. It measures the very process we are trying to avoid during operation, the thermal runaway of a joint. It manages to do this by using similar conditions to those during a quench, but has no energy stored in the magnets so that the thermal runaway can safely be stopped by an interlock process. This is achieved by doing the test at a temperature of about 20K, so that the magnets are no longer superconducting and the current passes through the bypass diode connected to all main magnets.

Reminder of simulation of safe energy – what are we aiming for? New simulation using the latest, best known values for RRR, lengths, etc. M. Koratzinos EnergyR_defect_max 3.5TeV- 4TeV66uOhms 4.5TeV54uOhms 5TeV45uOhms 5.5TeV39uOhms For Magnet quenches (propagation through the bus bar) and EE time constant of 68sec This is for magnet ‘busbar propagation’ quenches. Semi-prompt quenches very similar.

The principle of the method M. Koratzinos Tunnel measurement There is a relatively simple correlation between the time before the thermal runaway and the highest safe energy of a sector. This is derived from simulation but a lot of uncertainties cancel out (RRR of the bus, RRR of the cable, if it is a single or double-sided defect, if the defect is concentrated in one or two splices, etc.) simulation Current 6000A Busbar segment voltage

t plateau dI/dt I plateau I t FPA if V>V thr dV/dt to open the diodes Fast ramp down if V>V thr t1t2 T=20 K (  T to be defined) 500 A 4-6 kA 60 s PC in voltage modePC in current mode Trip by mQPS th 500 A/s CSCM typical current cycle H. Thiesen – 16 August 2011 – TE-TM To qualify for 5TeV operation, interlock should come >~20 seconds into the 6kA cycle

What will the CSCM measure? All main circuits (RB, RQD, RQF) All interconnection splices All current lead-busbar connections at the DFB All bypass diode paths (see A. Verweij talk) H. Thiesen – 16 August 2011 – TE-TM

Major engineering challenges Need to develop a new interlock system Need a special power converter configuration Needs non-standard cryo conditions (20K) But also Rigorous testing programme (SM18 tests) Complete analysis and simulation package

Circuit protection The circuit is protected by redundant hardware interlock electronics New QPS card developed Circuit also protected by the QPS Qsym cards Current leads are protected by standard QPS Qsym CL_QPS

The new QPS card Based on an existing nQPS design Four prototype boards ready and tested in the tunnel Components for 1000 boards ordered (good for 3 sectors) Last delivery date (ADuC834): end of August Limited tender is started Delivery expected in November 2011 Card tester needs to be developed (adapted from an existing tester) Noise well within expectations (well below 0.1mVolt – between 100 and 1000 times smaller than the detection voltage)

the standard RB power converter is rated at 13kA/190V – not sufficient for the CSCM, as all diodes need to be opened Modification needed: To reach the requested output voltage, the 2 SCR bridges have to be connected in series This modified converter will be used for both the RB and for the (RQD and RQF combined) circuits 12 Normal configurationCSCM configuration - Put in series the 2 bridges - Modify the output voltage sensor (divide by 2 the gain) - Modify the power converter voltage loop (F filter /2) 30 Hz L L Power converter issues H. Thiesen – 16 August 2011 – TE-TM 15 Hz L L

Tests of the new configuration of the RB power converter 13 V1V1 V2V2 i 4 Ohm or 4 mH – 4 mOhm V 1 + V 2 Test at nominal voltage 400 V and 100 A 100 mV/u200 mV/u 1 V/u 2 V/u H. Thiesen – 16 August 2011 – TE-TM Test at nominal current 6.5 kA and 20 V Configuration tested successfully in P-hall

Cryogenics issues Cryo will have to be regulated as per the RRR measurements during the last Xmas technical stop (20K) This was performed in all 8 sectors very efficiently. Additional requirement is that the DFBs will be maintained at 20K and Current Leads at nominal condition. An initial test has demonstrated that this is possible, but it will represent a new challenge for the Cryo team. The proper test lasts less than 60 seconds, estimated recovery time around 6 hours One day 20K Example of Cryo regulation in one sector during the RRR measurements last year

SM-18 validation tests: Validate the interpolation between CSCM tests at 20K and real splice quench at 1.9K Validate the interlocking electronics 10 m of MQ busbar (SC + copper) with a 30 mm defect are being prepared Perform several CSCM current cycles at different temperatures (20 to 40 K) and different current levels (1 to 6.5 kA) At 1.9 K (or 4.5 K), quench the splice at different current levels Tests planned to start mid September SM-18 auxiliary validation tests H. Thiesen – 16 August 2011 – TE-TM mBS board

Envisaged RB circuit test sequence Plateau current (A) Plateau time (s) Warm-up bus after t plateau (K) Stored energy in the sector (kJ) Dissipated energy in the sector (kJ) V 0 at t=t1 and t=t2 (mV) V thr for 30m segments (mV) to to to to Test at 1000 A: general check of all signals. Define V 0 and RRR of all the bus segments. After this test the thresholds can be defined. Test at 4500 A: find the very large defects (  ) without the risk of a very fast thermal runaway. If no defect found at 4500 A then: Test at 6000 A: find defects of the order of . 2 nd test at 4500 A/6000 A: ensure that the thermal runaway did not deteriorate the defect Assuming bus of 30 m, RRR=200, neglecting ramp up and ramp down. L RB =4 mH Parameters like plateau current and time might be reviewed after SM18 validation tests H. Thiesen – 16 August 2011 – TE-TM

CSCM type test planning H. Thiesen – 16 August 2011 – TE-TM 17 To get some experience before the full campaign a type test is required in one sector First results can be ready for Chamonix 2012

Success-driven staged approach M. Koratzinos10/08/2011CSCM Measure sector Good for 5TeV? 3.5TeV Estimated delay = D weeks (test + HWC) 3.5TeV Estimated delay = D weeks (test + HWC) Measure 2 more sectors Good for 5TeV? Measure 2 more sectors Good for 5 TeV? Measure last 2 sectors Good for 5TeV? NO (D = 2) NO (D = 6) NO (D = 8) YES 5 TeV Estimated delay = 11 weeks (test + HWC + BC) 5 TeV Estimated delay = 11 weeks (test + HWC + BC) NO(D = 4) Increasing probability of success All delays very approximate – for illustration purposes

Summary of progress since the 3 rd CERN MAC Project defined, core team working efficiently Interlock issues addressed successfully: a new QPS card has been developed, tested and 1000 cards have been ordered (sufficient for 3 sectors in parallel) Power converter issues addressed successfully: by converting the 13kA/200V main RB power converter to a 6.5kA/400V one. New configuration tested successfully Cryo issues addressed successfully: initial test demonstrated that it is possible to maintain arc circuits at 20K and current leads at nominal conditions Testing programme in test facilities under way: 10m long busbar segment with a realistic interconnect and defect will be tested in SM18 in mid September Has anything been forgotten? We would like to have an international review committee to look at the project (October). No show-stopper identified. The project is on target to perform the first test in the tunnel during the coming Christmas shutdown

Concerns CSCM tests present some important risks – Burning of a splice or a CL can not be excluded CSCM tests require to modify several critical protection systems as QPS, 13kA-EE, PIC and PC – Thorough re-commissioning is mandatory (time, resources) 5 TeV is not guaranteed a priori (if limiting splices found) CSCM tests will strongly interfere with other Xmas stop activities The full CSCM campaign cannot be performed during the present duration of the 2011/2012 Xmas stop – Significant “beam physics” time needs to be (re)allocated

Conclusions The CSCM is a qualification tool that can provide measurements for a deterministic decision on the maximum safe energy of the LHC and can increase significantly our knowledge about splices and diodes. Engineering challenges are being met and a test and simulation programme is under way. No show-stoppers found so far. The project will benefit from an international and external reviews A success-driven staged approach will ensure maximum time available for physics in Irrespective of the LHC maximum energy issues for 2012, the CSCM will most probably need to be performed in all sectors before LS1 to measure all diode contact resistances (A. Verweij talk) and after LS1 to validate the quality of splice repairs.

EXTRA SLIDES

SectorMeasured at 1A at: Largest R_excess measured (uOhm at warm) 5 magnet quenches per year, 1 incident in 1000 years Approximate Emax (5 magnet quenches) R excess for 0.08 bad joints (uΩ) 12At warm39±9554.5TeV 23At cold80± At warm36±8504.8TeV 45At warm53± TeV 56At warm20±7355.8TeV 67At warm31±9494.8TeV 78At cold90± At cold120± Out of the 8 sectors: 1 sector can go to 5TeV 3 sectors can go to 4.5TeV 1 sector can go to 3.5TeV 3 sectors not measured Current knowledge of 13 kA circuits RB circuits measured using hand-held voltmeters (Biddle) Assumptions: 1 incident in 1000 years 5 magnet quenches next year H. Thiesen – 16 August 2011 – TE-TM (RQ circuit knowledge much worse) Problems: RQ not measured 3 sectors not measured Possible deterioration over time Possible deterioration with current Problems: RQ not measured 3 sectors not measured Possible deterioration over time Possible deterioration with current