ESS Programme Plan and Schedule Update C. Darve, Deputy WP05 and WP04 leader Acknowledgement: N. Elias, WP05 and WP04 P. Bosland, WP05 leader https://ess-ics.atlassian.net/wiki/display/CRYOM/Cryomodules+Collaboration+space.

Slides:



Advertisements
Similar presentations
1 Requirements Conformance for SRF cryomodules October 2014 Lund P. Bosland (on behalf of the CEA/Irfu and CNRS/IPNO teams) ESS elliptical cryomodules.
Advertisements

SLHC-PP – WP7 Critical Components for Injector Upgrade Plasma Generator – CERN, DESY, STFC-RAL Linac4 2MHz RF source Thermal Modeling Gas Measurement and.
SRF Cryomodules November 2013 Meeting
ESS cavities interfaces
Test Stands Roger Ruber Uppsala University ESS TAC4 16 Feb
Materials to support the discussion: - Recall of TAC11 (1-2 April 2015) recommendations -HOM and PED -Possible QA applicable to SRF collaboration projects.
The ESS Cryomodules 2012 December, 5th Christine Darve
In-Kind Contribution Management Update Allen Weeks March 20, Lund.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
ESS Spoke Cryomodules: QA / QC Plans Workshop on Requirements Conformance for SRF Cryomodules, 15 th -16 th October 2014 Denis Reynet, Veronique Poux Sebastien.
Test plan for SPL short cryomodule O. Brunner, W. Weingarten WW 1SPL cryo-module meeting 19 October 2010.
Accelerator/WP High Beta Structures Alan Wheelhouse HIGH-BETA CAVITY DELIVERY April 21, 2015.
Accelerator / Elliptical Cavities Cryomodules
Preliminary Functional Analysis of ESS Superconducting Radio-Frequency Linac C. Darve, N. Elias, J. Fydrych, D. Piso European Spallation Source ESS AB,
Spoke test in vertical cryostat IPNO-UU Meeting on spoke test program, 2 nd -3 st October 2013 IPNO Team.
1 P. Bosland - Audit WP5 10 th of December 2015 Lund Annual audit for WP5 Elliptical cryomodules Prototype cryomodule M-ECCTD Prototype cryomodule H-ECCTD.
Accelerator/ Medium Beta Cavities Paolo Michelato INFN Milano - LASA April 21, 2015.
Medium Beta Cavities Paolo Michelato, Paolo Pierini, and Carlo Pagani INFN Milano - LASA.
Medium beta cavities Paolo Michelato, Paolo Pierini, Carlo Pagani INFN Milano - LASA.
HL-LHC Crab Cavity Review Debriefing Comments from LARP June 30, 2014.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
Collaborating for Quality Quality Assurance (QA) & Quality Control (QC) in the Accelerator Project (ACCSYS) Matthew Conlon ACCSYS QA/QC
CDR for the ESS Linac Magnets for LWUs (pulsed quadrupoles and DC correctors) Closeout May 4, 2016 J.G. Weisend II, Chairman CDR.
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
H-ECCTD - KICK-OFF MEETING 16TH MARCH 2016 GENERAL INTRODUCTION Florence ARDELLIER.
Christine Darve ESS deputy WP leader Pierre BOSLAND, CEA Saclay External WP5 leader With special Acknowledgment to Nuno Elias (ESS) and Gilles Olivier.
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
Pierre Bosland 4 TH OF FEBRUARY 2016 COORDINATION COMMITTEE FR-SW AGREEMENT STATUS OF THE FRENCH ACTIVITIES UNDER THE RESPONSIBILITY OF CEA.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
THE ESS ELLIPTICAL CAVITIES CRYOMODULES STAT US ON THE CEA SACLAY ACTIVITIES P. BOSLAND & F. ARDELLIER TAC13 07 th APRIL 2016.
Accelerator/Technical Documentation and Breakdown Structure Dr. Felix Schlander Lead Engineer 20 April
O. Kester, NuSTAR annual meeting, 27/02/2013
Accelerator/Elliptical Cavities Cryomodules Pierre BOSLAND, CEA Saclay External WP5 leader Christine Darve, ESS deputy WP leader
Wish list from ESS Christine Darve H-ECCTD Kick-off meeting 16 March
Spoke section of the ESS linac: - the Spoke cryomodules - the cryogenic distribution system P. DUTHIL (CNRS-IN2P3 IPN Orsay / Division Accélérateurs) on.
11/12/2013P. Bosland - AD-retreat - Lund Designs of the Spoke and Elliptical Cavity Cryomodules P. Bosland CEA/Saclay IRFU On behalf of the cryomodule.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
H-ECCTD KICK-OFF DESCRIPTION AND CHALLENGES 16/03/2016 F. PEAUGER.
ESS SC cavities development G. Devanz TTC meeting, march 1st 2011, Milano.
H-ECCTD KICK-OFF DEVELOPMENT PLAN AND SCHEDULE 16/03/2016.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
Cavities, Cryomodules, and Cryogenics Working Group 2 Summary Report Mark Champion, Sang-ho Kim Project X Collaboration Meeting April 12-14, 2011.
P. Bosland CEA-Saclay Collaboration Board meeting Copenhagen 14/04/ Status of the French activities under the responsibility of CEA Philippe CHOMAZ.
Collaborating for Quality through the Project Quality Plan Matthew Conlon ESS ACCSYS QA/QC Quality Learning & Planning.
CONFIGURATION MANAGEMENT AND CONTROL PLAN ESS Quality Assurance and Control workshop (30June) V. HENNION.
ESS Program Plan and Schedule Update
WP High Beta Cavities Delivery
Crab Cavity Technical Coordination meeting:
Status of the M-ECCTD F. Peauger - P. Bosland
Medium Beta Elliptical Cryomodule CDR Closeout
Cryomodule test stand at ESS site
Preparation of functional/engineering specifications for HL-LHC
WP5 Elliptical cavities
at STFC Daresbury laboratory
Uppsala Commitment to ESS and FREIA Planning
TTC Topical Workshop - CW SRF, Cornell 12th – 14th June 2013
Test plan of ESS HB elliptical cavity
Spoke CDS PDR Closeout J. G. Weisend II June 10, 2016.
ESS RF Development at Uppsala University
SPOKE Cavities frequency preparation plan and RF control procedures
Daresbury ESS In-Kind Contributions
Cryomodule ESS FAT & SAT SRF meetinG on 07/11/2017
Licensing requirements for Cryomodules
PSS verification and validation
as a prototype for Super c-tau factory
How Do We Define Acceptance of a Cryomodule? - A Discussion
Critical design review #1 for medium beta cavity cryomodules 3-4 APRIL SAFETY AND RAMI INPUTS - Franck Peauger OLIVIER KUSTER (INSTALLATION AND.
CDS-EL IRR Closeout 28 March 2019 J.G. Weisend II, Chairman.
SNS-PPU upgrades the existing accelerator structure
Overview of the TARGET Monolith Rough Vacuum
Presentation transcript:

ESS Programme Plan and Schedule Update C. Darve, Deputy WP05 and WP04 leader Acknowledgement: N. Elias, WP05 and WP04 P. Bosland, WP05 leader

Headline ESS Programme Plan  Scope –Life-cycle flow for the cavities and cryomodules –Interface requirements between cavities and cryomodules  see afternoon Workshop –Acceptance criteria and NC  see afternoon Workshop –Use lessons-learned from ECCTD (and XFEL)  Schedule (time) ESS Technical Annex (“schedule”) –PDR –CDR –Data packages –Tracking progress Communication channels: –Follow-up –Collaboration Space web site –Video-conferences 2

Headline ESS Programme Plan  Scope –Life-cycle flow for the cavities and cryomodules –Interface requirements between cavities and cryomodules  see afternoon Workshop –Acceptance criteria and NC  see afternoon Workshop –Use lessons-learned from ECCTD (and XFEL)  Schedule (time) ESS Technical Annex (“schedule”) –PDR –CDR –Data packages –Tracking progress Communication channels: –Follow-up –Collaboration Space web site –Video-conferences 3

Scope: Cavities and Cryomodules life-cycle Cavity Cryomodule Technology Demonstrators: 1 x Medium-beta, M-ECCTD<= FR-SW agreement 1 x High-beta, H-ECCTD<= CEA/CNRS Early In-Kind Production of cavities of the series with RF tests: 36 x operating Medium-beta cavities<= LASA In-Kind 84 x operating High-beta cavities<= STFC In-Kind Production of all other cryomodule components (incl PC, CTS):<= CEA In-Kind Cryomodule assembling:<= CEA In-Kind Low-power tests of 3 first medium and high-beta cryomodules<= CEA FR In-Kind RF and cryogenics for low power testing Transport of cryomodules from assembly hall to ESS: 9 x Medium-beta cryomodules <= STFC In-Kind 21 x High-beta cryomodules <= STFC In-Kind 4

5 NameDescriptionClarification Plug- compatible cavity design The cavities installed in the MBL cryomodules shall be designed such that they are plug- compatible with the cryomodule designed for the MB-ECCTD "Plug compatible" means that no alterations to the design of the remainder of the cryomodule components are necessary, e.g. Anchoring system. Note that design alterations resulting from the results of the MB-ECCTD are not ruled out by this requirement. R/QThe R/Q of the cavities designed for the MBL cryomodules shall not differ from that of the ECCTD cavity by more than +/-3.5% R/Q should be calculated at a beam velocity of beta = Note that no alteration of the geometric beta of the cavity is suggested by the use of this value for beta. Epeak/EaccThe ratio of the peak surface electrical field (Epeak) to the accelerating gradient (Eacc) for the cavities installed in the MBL cryomodules shall not exceed that of the ECCTD cavities Eacc should be calculated for a beam velocity of beta = Note that no alteration of the geometric beta of the cavity is suggested by the use of this value for beta. Interface requirements between cavities and cryomodules Cavity design shall be compatible with : Cold tuning system Power coupler Cryomodules component, e.g. thermal and magnetic shield, tie-rod system Assembly procedures Tooling handeling Use the technologies demonstrated via the ECCTD Preliminary

Cryomodule & main components 6  Similar to CEBAF/SNS cryomodule concept with 4 cavities per cryomodule  Common cryomodule design for medium and high beta cavities  Similar to CEBAF/SNS cryomodule concept with 4 cavities per cryomodule  Common cryomodule design for medium and high beta cavities MediumHigh Geometrical beta Frequency (MHz) Maximum surface field in operation (MV/m)45 Nominal Accelerating gradient (MV/m) Nominal Accelerating Voltage (MV)14,318,2 Q 0 at nominal gradient> 5e9 Cavity dynamic heat load (W)4,96,5 Power Coupler (HIPPI type coupler) Diameter 100 mm 1.1 MW peak power Antenna & window water cooling Outer conductor cooled with SHe Doorknob transition equipped with a bias system Cold Tuning System (Saclay V5 type modified for ESS cavities) stepper motor + gear box at cold Max tuner stroke: ± 3 mm Max tuning range: ~ 600 kHz Tuning resolution: ~1 Hz 2 piezo staks Cavities without HOM coupler 5 cells high beta (0,86) cavity 6-cells medium beta (0,67) cavity

7 Cavity Production Transport to CEA Assembly in Cryomodule Acceptance Test in VC Acceptance CEA- in * Possible “partner’s transfer flagpoint” * Transport to ESS Acceptance CEA- out * Acceptance ESS-in High Power ESS Acceptance Test  Tunnel Ready For Installation In tunnel INFN/STFC ESS/STFC CEA Scope: Cavities and Cryomodules Life-cycle Ready For Assembly in CM

8 Cavity Production Transport to CEA Assembly in Cryomodule Acceptance Test NC Report NC Minor NC Minor NC Repairable at CEA NC Repairable at CEA NC Report NC Not Repairable at CEA NC Not Repairable at CEA Repair Out of Work Data management and dealing with non-conformance * “partner’s transfer flagpoint” * * NC Minor NC Minor NC Repairable at STFC/LASA NC Repairable at STFC/LASA NC Not Repairable at STFC/LASA NC Not Repairable at STFC/LASA

9 Data management Action items: -Define a general Data management system, based on a simplified version of the XFEL DB, to be implemented at the ESS. Study: system functionality and select data to store. -Define simplified Data management system at ESS, CEA, LASA, STFC, Desy, Zanon, RI, etc..

M&H Technology Demonstrators 10 Engineering studies completed Fabrication of the components in progress Assembly infrastructure and procedures Preparation of the test stands (coupler processing & cryomodule tests)

Technology Demonstrators: ECCTD The goals of the ECCTD are to verify/validate the design to initiate the series production. It shall verify (but not necessarily be limited to): Fabrication process and industrialization of ALL cryomodule components: e.g. Fabricate successfully the SRF 704 MHz cavities, chemical and heat treatments, power couplers, CTS, cryomodule equipment, assembly procedures, etc Validate RF design: e.g. performance of cavities in vertical cryostat and on the test stand; power coupler performance, test slow tuning system, fast tuning System, LLRF Validate thermal and vacuum cryomodule design: eg. cool-down rate, operating conditions; heat loads; cooling scheme efficiency, leak tightness; Validate the alignment techniques. Validate the toolings design: e.g. handling and transportation Validate the verification procedure and threshold: e.g. Acceptance criteria process, SAT, FAT Verify the non-conformity tracking process. Control command: e.g. Validate the PLC sequences and the fast acting system, verify the operating algorithms ES&H e.g. Complete risk analysis, Cavities and CM mechanical relief sizing. Training: e.g. fabrication follow-up, testing procedure, assembly, operation, 11

Ex: “HoA - ANNEX C: H-ECCTD Test Plan” Before installation: vacuum tightness checks alignment measurements After installation / RF power OFF: Cryogenics and vacuum connections leak checks Temperatures measurement during cool down Static losses measurement RF resonant frequencies measurement (fundamental and HOMs) Alignment measurement at room temperature and at cold temperature At cold temperature with RF power (limited to 3 months) Measurement of every cavity from 1 to 4 at low power: external coupling factors measurements: Q i, Q t Tuning operations study Test of every cavity from 1 to 4 at high power in pulsed mode Maximum accelerating gradient measurement Lorentz force detuning compensation study Dynamic losses at 2 K measurement Field emission thresholds and quench limits determination Cryogenic behaviors study Temperature measurements Couplers: variation of He mass flow and CM consumption as a function of RF power (to optimize coupler static losses) 12

1 st April 2015TAC1113 M-ECCTD CDR review decision H-ECCTD CDR review decision 2) Power couplers contract awarded RF power source ready for coupler processing Cryomodule components contract awarded Planning Ready For Installation OK with ESS schedule: 03/09/18 => 02/05/19 1CM/month Planning Ready For Installation OK with ESS schedule: Q1 + Q2 2021: installation of HBL n° 1 to 11 Q1 + Q2 2022: Installation of HBL n° 12 to 21 Overall WP5 planning 1) Mb cavities contract awarded 1) Hb cavities contract awarded Mb – CDR – 15/09/16 Hb – CDR – 15/09/17 CDR – 23/12/16 CDR – 13/10/17

Proposed Milestones for LASA IKC “Technical Annex” 14

Proposed Milestones for LASA IKC “Technical Annex” 15

Proposed Milestones for STFC IKC “Technical Annex” 16

Proposed Milestones for STFC IKC “Technical Annex” 17

Headline ESS Programme Plan  Scope –Life-cycle flow for the cavities and cryomodules –Interface requirements between cavities and cryomodules  see afternoon Workshop –Acceptance criteria and NC  see afternoon Workshop –Use lessons-learned from ECCTD (and XFEL)  Schedule (time) ESS Technical Annex (“schedule”) –PDR –CDR –Data packages –Tracking progress Communication channels: –Follow-up –Collaboration Space web site –Video-conferences 18

Technical Annex - TOC SCHEDULE AIK [ACCSYS WP NUMBER. ACCSYS IKC REGISTER NUMBER] TO THE IN-KIND CONTRIBUTION AGREEMENT SIGNED BETWEEN ESS and [name of partner] on DATE 1.Scope 2.Related documents 2.1Applicable Documents 2.2Reference documents 3.Terms and Definitions 4.Project definition 4.1Deliverable Item definition 4.2Project Stages Definition 4.2.1Stage 1: Design Stage 4.2.2Stage 2: Realization and Verification 4.2.3Stage 3: Installation, Commissioning and Initial Operations 19

PDR - Definition “Preliminary Design Review(s) reviews preliminary design, sometimes referred to as conceptual design. A PDR assesses preliminary design options and decisions in comparison with ESS input baseline reference design including requirements. A successful PDR demonstrates that design is sufficiently developed, clear and agreed between ESS and the Partner. Preliminary design updates the baseline reference design which was agreed at Kick-off, and a successful PDR establishes a new baseline, described in [CMP] The ‘Allocated Baseline’ from which the Partner may proceed to detailed design, including any agreed pre-series prototyping. For planning purposes, a PDR should be limited to no more than one working day.” 20

PDR - Deliverables The contents of the technical data package for PDR(s) shall include but not be limited to: Requirements, agreed or proposed updates to documents comprising the baseline reference design. Design Reports, including reports of prototyping and other preliminary design-related analyses, tests, simulations. Design Data, (preliminary design level of detail) including 3D CAD models and CAD drawings, general arrangement drawings, P&ID, FE models, etc., and interface descriptions including at least interface identification and any preliminary design definition. RAMI Report, an initial version of a report of the estimation of the probability and consequences of failures in equipment as well as main maintenance tasks and proposed spare parts. Safety Report, an initial version of the safety risk assessment report (including identifying hazards and evaluating likelihood of incidents occurring and severity of potential consequences, also list of existing control measures). [PQP], any outline draft for the Project Quality Plan including initial identification of Standards to be applied, initial planning for compliance testing and inspection, and initial planning for verification. 21

CDR - Definition “Critical Design Review(s) conclude Stage 1. The CDR assesses if the design meets all facility element requirements with acceptable risk and within the cost and schedule constraints. The CDR demonstrates that the maturity of the design is appropriate to support proceeding with full-scale fabrication, assembly, integration, test, and future operation and decommissioning. The CDR should also review initial planning for verification. Detailed design updates the baseline reference design which was agreed at Kick-off, and any ‘Allocated Baseline’ of preliminary design established by PDR. A successful CDR establishes a new baseline, described in [CMP] as the ‘Design Baseline’ from which the Partner may proceed to Stage 2 Realisation and Verification. “ 22

CDR “The contents of the technical data package for CDR(s) shall include but not be limited to: Requirements, agreed or proposed updates to documents comprising the baseline reference design. Design Reports, including reports of prototyping and other design-related analyses, tests, simulations. Design Data, (detailed design level) including 3D CAD models and CAD drawings, general arrangement drawings, P&ID, FE models, etc., and detailed interface descriptions including interface identification and definition for controlling interface design. RAMI Report, a report of the estimation of the probability and consequences of failures in equipment as well as main maintenance tasks and proposed spare parts. Safety Report, safety risk assessment report (including identifying hazards and evaluating likelihood of incidents occurring and severity of potential consequences, also list of existing control measures). Verification Plan, (including planned FAT and SAT activities) [PQP], a full draft for the Project Quality Plan including identification of Standards applied in design, procurement, manufacture and assembly, and planning for compliance testing and inspection.” 23

CDR “The CDR data package shall also contain documentation to initiate a competitive tender for the procurement of the facility element and to support the project activities. The CDR data package should additionally include but not necessarily be limited to: Procurement Package, a complete documentation package for the procurement of the facility element including as a minimum a statement of work, manufacturing follow-up description, applicable and reference documentation Project Plan, updated plan in Gant chart form, describing in detail remaining Stage 1 activities, describing in detail Stage 2 Realisation & Verification activities, and an outline of any Stage 3 Installation, Commissioning and Initial Operations activities for the Partner. Risks, Risk Register, showing identified project management risks and/or technical risks.” 24

Example of status/doc at CDR-phase To start stage 2 the necessary prerequisite are the following: The interface document of the cryomodules with the tests stations at CEA Saclay, with the transport to ESS-Lund, with the test stand at ESS-Lund and with the LINAC infrastructure is settled by the end of stage 1. The acceptance criteria for the cryomodule assembly are settled by the end of stage 1. The ESS acceptance management process is operational. The verification plan followed up all along the cryomodule assembly, at the test stand at Saclay until the shipment to ESS-Lund is settled by the end of stage 1. The configuration items for cryomodule is clearly defined. The cavity string configuration with individual cavity performance for each cryomodule is known 3 weeks before the assembly. The last version of all assembly drawings and P&ID is released at the end of stage 1. Each design change needs an acceptance from CEA and the assembly drawing has to be updated and released to CEA. The ESS change management process is operational. The ESS-“CHESS” interface is operational to upload the cryomodule assembly documentation. The ESS non-conformity management process is operational. Transport test is successfully performed. Could this sentence be more specific? Should we clearly refer to a “document management database”? 25

Headline ESS Programme Plan  Scope –Life-cycle flow for the cavities and cryomodules –Interface requirements between cavities and cryomodules  see afternoon Workshop –Acceptance criteria and NC  see afternoon Workshop –Use lessons-learned from ECCTD (and XFEL)  Schedule (time) ESS Technical Annex (“schedule”) –PDR –CDR –Data packages –Tracking progress Communication channels: –Follow-up –Collaboration Space web site –Video-conferences 26

Communication channels SRF collaboration Kick-off meeting at Saclay: 23 June 2015 SRF collaboration at STFC: 15 December 2015 Medium-beta cavity design: 2-3 November 2015 Weekly Vidyo meeting: Fridays mornings Monthly Project reports Collaborative Project Objectives: Freeze the cavities design List interfaces requirements CEA needs to analyse the impact on the cryomodule design and on the toolings before approval Track actions items Etc 27

Cryomodules Collaboration space Interface between Cryomodule and Cavities- Within EMR Interfaces LASA - Medium-beta cavity/cryomodules Interface STFC - Collaboration for SRF Elliptical Cavities Collaboration Interface with Radio-Frequences - RFS - WP08 Interface with RF sources Interface with RFS/LLRF Interface Meeting between EMR and LLRF - Meeting notes (LLRF Interface) Interface Meeting between EMR and RF systems - Meeting notes Interface with RFS/RFDS Interface with RFS/Interlocks Interface with Cryogenics (Cryoplant, Distribution System) - CRYO - WP : Interface Meeting - Cryogenic Instrumentation Minutes of meeting 16-Feb-2015 (Cryogenic Instrumentation) : PED Meetings - Pressure Equipment Directive : Interface Meeting - Cryomodule instrumentation Minutes of (Cryomodule instrumentation) : Interface Meeting - Pressure Configuration

Cryomodules Collaboration space Interface with Vacuum - VAC - WP : Interface Meeting - Cryomodules vacuum Interface meeting - Cryomodules Vacuum Beam Vacuum Interface Requirements Insulation Vacuum Interface Requirements Interface with Cabling and Conventional Power - CNPW - WP15 Interface with Cooling support - WTRC - WP16 Interface with Power Supplies, HV Power Converters - PWRC - WP17 Interface with Proton Beam Instrumentation - PBI - WP07 Interface with Test Stands - WP10 Interface with Control and Command - Integrated Control System (ICS) Interface with Survey and Alignment

Thanks for your attention 30

Compliance with European Pressure Equipment Directive (PED) 31 Volumes of the helium circuits and vessels < 48 l bara < Working pressure Ps = 1.04 barg TUV Nord analysis report: The elliptical and Spoke cryomodules are classified according to PED article 3.3 Cryo pipes designed to reduce the overpressure in case of beam vacuum failure continuous diphasic pipe Ø=100 with large curvatures 2 Ø=100 bursting disks at each extremity

 S. Bousson, Workshop on Requirements Conformance for SRF Cryomodules, Lund, 15 th Oct Spoke cryomodule overall life cycle Appro Niobium Fabrication Cavité Traitement surface Cavité Assemblage cavité Salle blanche Test en CV COMPONENT PHASE Export / delivery Test / validation Préparation/ assembly SUpply/ Production NiobiumCavitiesCouplers vessel Vacuum Cryomod. Full. compon.. Cryomod. string Cavity CTS… Transport -> site assemblage Transport -> Fabriquant cavités … … … … Fabrication Enceinte Cryomodule Transport -> site assemblage Appro Compos. cryomodule Transport -> site assemblage Assemblage train cavités Transport -> site assemblage Fabrication SAF Assemblage SAF Test à chaud SAF Transport -> site assemblage Assemblage cryomodule Test à chaud Transport -> Uppsala Fabrication Coupleur Préparation salle blanche coupleurs Conditionn- ement coupleurs Transport -> site assemblage

Charge to the Committee This review constitutes the principal technical and project review of the Work Package for this year. Additional specific design reviews may also be held. Keeping in mind the current status of the Accelerator Project, the committee is asked to review the information presented, answer to the extent possible the questions below and make specific recommendations to increase the likelihood of success of the Work Package. The result of the review will be a short report that includes recommendations. The committee serves in an advisory capacity to the Work Package Leader and the ACCSYS management team. Has the work package reached a level of technical maturity consistent with its current status on the schedule? Are there any technical concerns regarding the work package? Is any additional development or testing required for the work package to meet its goals? Are the requirements for the work package well understood and documented? Are all the interfaces between the work packages and other work packages and products properly defined, understood and agreed upon? Have all safety issues in the work package been properly identified and dealt with? Are there sufficient resources (funding, staff) assigned to the work package to allow the goals of the work package to be met? Are there decisions that need to be made in order to allow the work package to meet scope, cost and schedule? Are there any outstanding procurements or personnel actions that are limiting the progress on the Work Package? Is the Work Package on track to meeting its milestones? Are there any adjustments to the schedule and milestones that should be made? Are there any changes to the work package scope that should be made? Are additional reviews warranted before the next annual audit? 33

Technical Annex - TOC 4.3Project Schedule and Key Milestones 4.3.1Kick-off meeting 4.3.2Status meetings 4.3.3Design Review(s) in Stage Readiness / Acceptance Review(s) in Stage Review(s) in Stage 3 4.4Deliverables 4.4.1Status reports 4.4.2Technical Data Package(s) for Design Review(s), Stage Technical Data Package(s) for Review(s), Stage Final report 4.4.5Documentation package for supply 34

Technical Annex - TOC 5.Tasks applicable to all project stages 5.1Project management and control 5.1.1Use of a Planning Tool 5.1.2Delivery Milestones 5.1.3Milestone Definition List 5.1.4Interim Milestones 5.1.5EV – Weighted MS value 5.1.6Monthly Forecasting 5.2Risk Management 5.2.1ESS Risk Management Process 5.2.2ESS risk criteria 5.2.3Risk register 5.2.4Risk status report 35

Technical Annex - TOC 5.3Configuration management 5.4Organization 5.5Product & Quality assurance and safety 5.5.1Applicable law, legislation and standards 5.5.2Safety 5.5.3Quality 5.5.4Licensing 6.Documentation format 7.Transportation and DELIVERY 8.Warranty 9.Excluded Background 36