DZero Run IIb Rev Nov 05 ‘03 1 Kotcher Agenda (from Rebaselining Review)  Introduction (Kotcher – 10’)  Trigger & DAQ/Online (Wood – 30’) u AFE II/TriP.

Slides:



Advertisements
Similar presentations
US CMS DOE/NSF Review: May 8-10, US CMS Cost & Schedule Mark Reichanadter US CMS Project Engineer DOE/NSF Review 8 May 2001.
Advertisements

MICE Collaboration MTG IIT – Feb 2002 The Fiber Tracker Option for MICE Spectrometers The D0 Central Fiber Tracker – Experience and Implications for MICE.
DZero RunIIb Director’s Review February 3, Run IIb Project Status Vivian O’Dell.
September 16, 2002 ID Groups Physics Coordinator B. Klima Software and Computing A. Boehnlein, J. Qian Physics Groups Spokesmen G. Blazey J. Womersley.
The Belle SVD Trigger  Tom Ziegler  Vertex 2002  Kailua-Kona, Hawaii, 4-8 th nov The Belle SVD Trigger Tom Ziegler on behalf of the Belle SVD.
Doug Michael Jan. 12, First goal is to be ready to select an optimal technology in ~one year. –Demonstrate that fundamental technologies are ready.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
WBS 1.7: AFE II Project Cost and Schedule Alan Bross DZero Run IIb AFE II Director’s Review April 13, 2005.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
March 20, 2001M. Garcia-Sciveres - US ATLAS DOE/NSF Review1 M. Garcia-Sciveres LBNL & Module Assembly & Module Assembly WBS Hybrids Hybrids WBS.
1 Framework Programme 7 Guide for Applicants
Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.
AGS RSVP Weekly Meeting P. Pile 27 Jan 2005 AGS RSVP Weekly Meeting 27 Jan 2005 Useful Links: RSVP Project : C-AD.
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
M. Gilchriese ATLAS Upgrade Introduction January 2008.
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
Aug 2005 Working Groups Physics J. Hobbs V.Buescher (deputy) Physics Groups Spokespersons G. Blazey T. Wyatt Trigger Silicon Layer O Online L3/DAQ Trigger.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
John Peoples for the DES Collaboration BIRP Review August 12, 2004 Tucson1 DES Management  Survey Organization  Survey Deliverables  Proposed funding.
Silicon RunIIb Workshop, Dec , A. Bean, M. Demarteau Slide 1 Workshop  Workshop is to “Move beyond the Technical Design Proposal”  Many.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
Muon trigger upgrades, missing since not aimed towards DOE funding PHENIX upgrades: view presented to DOE R&D $3.5M Construction $16.6M Au-Au p-p 200 Si-Si.
September 19,2006 TeV Working Groups Physics J. Hobbs R. Van Kooten Physics Groups Spokespersons T. Wyatt D. Denisov Trigger Silicon Layer O Online L3/DAQ.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
DZero RunIIb PMG June 7, Run IIb Project Status Vivian O’Dell.
DZero Run IIb PMG February 25, Run IIb DZero PMG  Status overview, issues (Kotcher)  Schedule, project status (Freeman)  AOB Jon Kotcher Fermilab.
October 3, 2008 John Haggerty 1 PHENIX Plan for Run 9 John Haggerty Brookhaven National Laboratory.
DZero Run IIb PMG January 28, Agenda Run IIb D-Zero PMG January 28, 2003  Overview, issues (Kotcher)  Project status (O’Dell)  Trigger technical.
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
Tevatron II: the world’s highest energy collider What’s new?  Data will be collected from 5 to 15 fb -1 at  s=1.96 TeV  Instantaneous luminosity will.
D0 Status: 01/14-01/28 u Integrated luminosity s delivered luminosity –week of 01/ pb-1 –week of 01/ pb-1 –luminosity to tape: 40% s major.
UCSC August 12, 2008 U.S. Upgrade R&D Meeting: Strip Detector  Seiden.
Rev of Run IIb, Nov 4-8, 2002, A. Bean 1 Silicon Management  Organization and Management  Schedule  Resources  Conclusions Alice Bean Univ. of Kansas.
All Experimenters MeetingDmitri Denisov Week of July 7 to July 15 Summary  Delivered luminosity and operating efficiency u Delivered: 1.4pb -1 u Recorded:
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
FNAL PMG Feb 5, DØ RunIIb Trigger Upgrade WBS 1.2 Paul Padley, Rice University for the DØ Trigger Upgrade Group.
D0 Status: 04/01-04/08 u Week integrated luminosity –1.7pb -1 delivered –1.5pb -1 utilized (88%) –1.1pb -1 global runs u Data collection s global data.
Aug 2003 Craig Ogilvie 1 Landscape/Goals for R&D  Goal: Barrel+structure ready Summer/Fall 06 (run07)  Goal: Endcaps ready Summer/Fall 07 (run08)  RIKEN.
V. O’Dell, D0 RunIIb PMG 4-Feb Dzero Run IIb PMG  Agenda u Overview & Management News: V. O’Dell u Trigger Upgrade Status:P. Padley u Silicon closeout.
DoE Review June 6, 2000 Cost Estimate  New Cost Estimate u Manpower Costs (Op. SWF) u Equipment Costs (Eq. M&S) u Contingency  Conclusions Mike Tuts.
1 EIR Nov 4-8, 2002 DAQ and Online WBS 1.3 S. Fuess, Fermilab P. Slattery, U. of Rochester.
Welcome and Presentation of Charge Steve Holmes Accelerator Advisory Committee ( May 10-12, 2005.
Tevatron BPM Upgrade Stephen Wolbers CD Accelerator Coordination Meeting September 21, 2004.
Brenna Flaugher Sept. 24 th Lehman Review1 Run IIB Silicon Upgrade: Cost and Schedule Lehman Review Sept. 24, 2002 Brenna Flaugher Run IIB Silicon Project.
WBS 1.2.8: AFE II Status and Plans Alan Bross for the DZero Central Fiber Tracker Group DZero Run IIb Detector Upgrade Director’s Review July 15, 2004.
March 15,2005 Working Groups Physics J. Hobbs V.Buescher (deputy) Physics Groups Spokespersons T. Wyatt D.Denisov Trigger Silicon Layer O Online L3/DAQ.
Plan to go forward Peter Wilson SBN Program Coordinator 27 September 2014.
February 3, 2005DZero Run IIb Director's Review1 Standing Committee on Upgrade Installation to Physics Commissioning  Charge: u Convened by spokespersons.
H. MatisSTAR Inner Silicon Tracking Detector Review – July 8, SSD software and hardware maintainability Howard Matis.
PHENIX Vertex Detector with Conventional Strip Sensors Abhay Deshpande Stony Brook University.
D0 PMG February 15, 2001 PMG Agenda February 15, 2001  Overview (Weerts) u Detector status u Reportable milestones u Summary  Operations Organization.
DZero Run IIb PMG December 10, Agenda Run IIb D-Zero PMG December 10, 2002  ESAAB news (Lab, Project, DOE)  Project status, overview (Kotcher)
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
V. O’Dell, L0 Workshop 25-Sep Run 2b Layer 0 Workshop u Layer 0 proposal from project Management perspective s History/News s Schedule.
Director’s Review July 15, Installation and Technical Commissioning of D0 RunIIb L0 Silicon and Trigger Upgrades Schedule & Costs R.P. Smith for.
All Experimenters MeetingDmitri Denisov Week of July 22 to July 29 D0 Summary  Delivered luminosity and operating efficiency u Delivered: 3.1pb -1 u Live:
F Fermilab Vertex Effort From a Fermilab Detector R&D Perspective Marcel Demarteau For the Fermilab ILC Detector & Physics R&D Group ALCPG Vertex Detector.
A New Inner-Layer Silicon Micro- Strip Detector for D0 Alice Bean for the D0 Collaboration University of Kansas CIPANP Puerto Rico.
Organization, Proposal and Funding We hope to finish the revised proposal this week Need some cleanup I added a section on simulation needs – should be.
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
Upgrade Intro 10 Jan 2010 Norman Gee. N. Gee – Upgrade Introduction 2 LHC Peak Luminosity Lumi curve from F.Zimmermann : Nov Upgrade Week ? ?
Jim Fast Pacific Northwest National Laboratory
U.S. CMS HL-LHC Project Report
NMMU Upgrade Integrator 3 Integrator UG 2014 Greg Saunders
Francesco Forti University and INFN, Pisa
Toward the final design of a TPC for the ILD detector
Preparations for a Lehman Review
Stan Whitcomb LSC meeting Livingston 21 March 2005
Preliminary Project Execution Plan
Presentation transcript:

DZero Run IIb Rev Nov 05 ‘03 1 Kotcher Agenda (from Rebaselining Review)  Introduction (Kotcher – 10’)  Trigger & DAQ/Online (Wood – 30’) u AFE II/TriP (Bross – 15’)  BREAK  Silicon Layer 0 (Lipton – 30’)  Baseline Change Proposal, Rebaseline Summary (Kotcher – 30’) Rebaselining Review of the Run IIb DZero Detector Project November 5, 2003 Fermilab Most everything you will see today is in draft form

DZero Run IIb Rev Nov 05 ‘03 2 Kotcher AFE II/TriP Upgrade WBS  We are proposing an upgrade to the Central Fiber Tracker (CFT) readout & triggering system u Maintain tracking capability in light of cancellation of silicon upgrade, particularly at increased luminosity s considerably improved noise performance – lower thresholds, enhance triggering, efficiency s z-information from timing u New Analog Front-End Boards (AFE II) and trigger (TriP) chip s First version TriP chip submitted with SVX4 s Designed, tested by Fermilab (PPD, Yarema) s Was major success out of the box s First full AFE II prototype being laid out now, expect back by end CY03 s System represents major simplification, performance upgrade u Exploiting considerable in-house experience – personnel, depth of technical knowledge  TPC = $2.2M (includes 50% total contingency) u M&S cost estimate based on detailed past experience u see talk by Bross

DZero Run IIb Rev Nov 05 ‘03 3 Kotcher Run IIb Project Organization Nov ‘03 D0 Run IIb Project J. Kotcher, Project Manager V. O’Dell, Deputy (Trigger/DAQ); R. Lipton, Deputy (Silicon Layer 0) W. Freeman, Associate; M. Johnson, Technical Coordinator D. Knapp, Budget Officer; T. Erickson, Administration WBS 1.2 Trigger P. Padley D. Wood L1 Track Trigger M. Narain L1 Cal Upgrade M. Abolins, H. Evans L2  Upgrade R. Hirosky Silicon Track Trigger U. Heintz WBS 1.3 DAQ/Online S. Fuess P. Slattery L1 Cal/Track Match K. Johns Simulation E. Barberis, M. Hildreth WBS 1.5 Installation R. Smith Silicon Installation Mechanical: (W. Cooper) Electronics: (L. Bagby) Trigger Installation D. Edmunds WBS 1.4 Project Administration Administration (D. Wood) Control Systems F. Bartlett, G. Savage, V. Sirotenko Level 3 Systems D. Chapin, G. Watts DAQ/Online Management (P. Slattery) Network & Host Systems J. Fitzmaurice, S. Krzywdzinski Installation an integrated part of project plan, but removed from formal Run IIb baselining AFE II/TriP A. Bross, TBD WBS 1.6 Silicon Layer 0 A. Bean (R. Lipton) Sensors M. Demarteau, R. McCarthy Readout Elec A. Nomerotski, R. Sidwell Mech Des & Fabrication W. Cooper 1.6.4, Detector Modules & Integ J. Fast, L. Bagby Administration (A. Bean) Full Run IIb silicon replacement, now cancelled, was WBS 1.1 For initial prototyping phase

DZero Run IIb Rev Nov 05 ‘03 4 Kotcher AFE II/TriP Decision Process  Project funding request ($2.2M) includes both salaries and M&S for production only; does not contain either salaries or M&S for R&D u Has been coming from operating funds (e.g., TriP work & testing) u Agreement with Laboratory that this will continue  Before fully supporting the pursuit of this sub- project, we first must convince ourselves that it will provide the experiment with sufficient gains to justify the considerable effort & potential interruptions to data-taking, and that the scheme will work as advertised  Given the time scales (summer ’05 completion), answering these questions must be given sufficient priority during the next few months…and without allowing operations to falter

DZero Run IIb Rev Nov 05 ‘03 5 Kotcher AFE II/TriP Decision Process  The following must be completed before production funds will be released: u Continuation/completion of simulations u TriP resubmission s Abder is starting u AFE II prototype layout, fabrication & testing s Arrangements to free John A. up to pursue this for next few months being finalized now s Operations will be covered s Fabrication and testing must immediately follow u DZero Internal Review, followed by a u Laboratory Review, if warranted

DZero Run IIb Rev Nov 05 ‘03 6 Kotcher AFE II/TriP Decision Process  The DZero Review will be a critical one  Among the things they will be asked to look over: u Technical gains & feasibility u Physics benefits u Realism of schedule u Long-term commitment of personnel u Credibility of installation and commissioning plan, and its impact on acquisition of physics quality data s A major consideration u Will be asked to provide an overall recommendation, submitted to Spokes, PM  If justification is there, and the DZero Internal Review Committee recommends moving forward, would like to hold the Laboratory Review no later than April ’04  Targeting summer ’05 completion (installation during summer shutdown), which is still tight