CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1.

Slides:



Advertisements
Similar presentations
ATLAS SCT Endcap Detector Modules Lutz Feld University of Freiburg for the ATLAS SCT Collaboration Vertex m.
Advertisements

ATLAS LHCC 28/11/00 A. Henriques/CERN 1 H8 : Pixel, SCT, TRT, Tiles, LAr em barrel, Muons SPS H6: EMEC, HEC, FCAL, Background studies GIF: Muons (MDT,
The First-Level Trigger of ATLAS Johannes Haller (CERN) on behalf of the ATLAS First-Level Trigger Groups International Europhysics Conference on High.
18th March Richard Hawkings Humidity control in the ATLAS ID Richard Hawkings (CERN) JCOV meeting 18/3/04  Overview of humidity and associated gas.
June 2-4, 2004 DOE HEP Program Review 1 M. Sullivan for the PEP-II Team DOE High Energy Physics Program Review June 2-4, 2004 PEP-II Status and Plans.
Atlas SemiConductor Tracker Andrée Robichaud-Véronneau.
19 March 2012Muon Week - Operations1 Muon Week Muon Operations Session Introduction Status and LHC Schedule Detector Readiness + Preparation for Physics.
ATLAS detector upgrades ATLAS off to a good start – the detector is performing very well. This talk is about the changes needed in ATLAS during the next.
WP2: Detector development Summary G. Pugliese INFN - Politecnico of Bari.
M. Battistin – 1 st September 2009 EN/CV/DC 1 M. Battistin (EN/CV/DC) 1 st October 2009 ATLAS cooling Group - Thermosiphon solution for ATLAS ID cooling.
Experimental Area Meeting V. Bobillier1 Good connection to earth (in many points) of every metallic parts to be installed in the cavern is very.
H. MatisTracking Upgrade Review – Dec. 7, SSD Update Howard Matis.
T. Kawamoto1 Small Wheel upgrade project Muon week, upgrade meeting T. Kawamoto.
M. Gilchriese ATLAS Upgrade Introduction January 2008.
IBL MoU G. Darbo – INFN / Genova 24 April 2010 o IBL MoU ATLAS Upgrade Week DESY, April 24 th 2010 M. Nordberg, M. Nessi, C. Gößling, H. Pernegger Presented.
Status of the NO ν A Near Detector Prototype Timothy Kutnink Iowa State University For the NOvA Collaboration.
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
IBL MoU G. Darbo – INFN / Genova 17 April 2010 o IBL MoU Contribution prepared for Marzio’s talk at April RRB G. Darbo - INFN / Genova.
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
CERN, Main challenges for the ATLAS upgrade project in the coming year.
Concept idea for the modular 2PACL system for the Atlas ITK 3 June 2015 Bart Verlaat 1.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
1 H. Pernegger/CERNIBL cooling review 15/5/2012 IBL Cooling Requirements H. Pernegger.
ATLAS SCT End-Cap C Integration 1.Introduction: to the SCT within ATLAS 2.End-Cap C Reception at CERN 3.Final Assembly 4.Integration with the TRT 5.Combined.
M&O status and program for ATLAS LAr calorimeter R Stroynowski (on vacations)
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
G. Carboni – Muon Meeting – April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
ATLAS TRT CO 2 cooling system project status Beaufort 12: “Hurricane” (>119 km/h) Saffir-Simpson 5: “catastrophic damage” (>250 km/h) (CO 2 distribution.
Main priorities for the next years. Where do we stand Muon system in good shape (in my opinion) – Sub-systems hardware quite robust (see later for main.
The Status of the ATLAS Experiment Dr Alan Watson University of Birmingham on behalf of the ATLAS Collaboration.
T. Kawamoto1 ATLAS muon small wheels for ATLAS phase-1 upgrade LHCC T. Kawamoto (New) small wheels ? Why new small wheels for high.
IDE DCS development overview Ewa Stanecka, ID Week, CERN
Tevatron II: the world’s highest energy collider What’s new?  Data will be collected from 5 to 15 fb -1 at  s=1.96 TeV  Instantaneous luminosity will.
Luca Spogli Università Roma Tre & INFN Roma Tre
D0 Status: 01/14-01/28 u Integrated luminosity s delivered luminosity –week of 01/ pb-1 –week of 01/ pb-1 –luminosity to tape: 40% s major.
All Experimenters MeetingDmitri Denisov Week of July 7 to July 15 Summary  Delivered luminosity and operating efficiency u Delivered: 1.4pb -1 u Recorded:
D0 Status: 04/01-04/08 u Week integrated luminosity –1.7pb -1 delivered –1.5pb -1 utilized (88%) –1.1pb -1 global runs u Data collection s global data.
Peter Sharp CERN CMS Tracker Summary of the Tracking Trigger Working Group Peter Sharp 21 November 2008.
R. Boyd 1 February  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.
Pixel power R&D in Spain F. Arteche Phase II days Phase 2 pixel electronics meeting CERN - May 2015.
Atlas Muon Spectrometer: installation and commissioning L. Pontecorvo INFN Roma.
TC Straw man for ATLAS ID for SLHC This layout is a result of the discussions in the GENOA ID upgrade workshop. Aim is to evolve this to include list of.
Tracking in a TPC D. Karlen / U. Victoria & TRIUMF for the LCTPC collaboration.
Status of ATLAS Resources Presentation to RRB Markus Nordberg ATLAS Resources Coordination CERN-RRB
General Muon Meeting, 03-March-2014 Jay Hauser “Update on Phase 2 muon Technical Proposal”  Recent developments:  ME0 inserted into HGCAL as for other.
The Detector Performance Study for the Barrel Section of the ATLAS Semiconductor Tracker (SCT) with Cosmic Rays Yoshikazu Nagai (Univ. of Tsukuba) For.
RRB scrutiny Report: Muons. Internal scrutiny group for RRB report Internal scrutiny group composition – J. Shank, G. Mikenberg, F. Taylor, H. Kroha,
Status of the ATLAS ID Evaporative cooling system JCOV 25 Nov P. Bonneau TS/CV/Detector Cooling CONTENTS Overall statusOverall status Cooling plant.
T2K Status Report. The Accelerator Complex a Beamline Performance 3 First T2K run completed January to June x protons accumulated.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
TOF status and LS1 plansTOF status and LS1 plans 27/06/2012.
Eric Vigeolas, July the 3 rd Status The IBL detector construction already started and the components assembly (flex, modules, stave loagin) will.
August 24, 2011IDAP Kick-off meeting - TileCal ATLAS TileCal Upgrade LHC and ATLAS current status LHC designed for cm -2 s 7+7 TeV Limited to.
Atlas status report. LHC Cooldown Status LHC is proceeding with the cooldown and the hardware commissioning L.Evans is asking the experiments to close.
110 th November 2010EN/CV/DC Detector Cooling Project - advancement status of Work Package N3 Thermosiphon project Michele Battistin 18 May 2011.
1 Projectile Spectator Detector: Status and Plans A.Ivashkin (INR, Moscow) PSD performance in Be run. Problems and drawbacks. Future steps.
1/20 LHCb upgrade, Jeroen van Tilburg Nikhef Jamboree, 14 Dec 2015 Preparing for the LHCb upgrade.
`` ATLAS inner detector JV Els KoffemanAtlas - Inner Detector1 Tracking in solenoid 2 Tesla field – 3 pixel layers with 50 um x 400 um cells – 4.
TDAQ and L1Calo and Chamonix (Personal Impressions) 3 Mar2010 Norman Gee.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
14 Aug. 08DOE Review John Huth Future Harvard ATLAS Plans John Huth.
EPS HEP 2007 Manchester -- Thilo Pauly July The ATLAS Level-1 Trigger Overview and Status Report including Cosmic-Ray Commissioning Thilo.
Upgrade plans for ATLAS. Nigel Hessey (Nikhef) is overall ATLAS upgrade coordinator.
Technical Design for the Mu3e Detector
P. Morettini Towards Pixel TDR PM - ITk Italia - Introduction 8/2/2017.
IBL Overview Darren Leung ~ 8/15/2013 ~ UW B305.
Bringing the ATLAS Muon Spectrometer to Life with Cosmic Rays
Update on ATLAS insertable B-layer
Presentation transcript:

CERN-RRB Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

…. since last RRB (12 th October) From 10 th November 2009 to 16 th December the detector has been taking physics data at 450 GeV and 1.18 GeV per beam (single beams and collisions) From 17 th December 2009 to early February 2010 we have been in shutdown mode, but with no internal detector opening. Just access to the external services and to the muon spectrometer From 28 th February 2010 (first 2010 beams injections) we went back to data taking mode with up to now ~400  b -1 =~ 22M collisions events registered at 3.5 TeV per beam with the entire detector active 2

Data taking efficiency 3 Stable beam flag Data taking efficiency In the last few weeks our data taking efficiency has been in average around 94%, some time is still lost in turning on the inner detectors once the stable beam flag is set by LHC

Operation resources 4 After the initial learning period we will now operate ATLAS with 55 shifts/day (including Tier0 and distributed computing) at P1 … on top of this, we need ~ 140 x 8 hours-equivalent shifts for experts on call, satellite rooms shifts or remote shifts outside CERN, …… = ~ 150 people involved/day to keep the entire machinery running !

Operation Tasks (OT) sharing 5 ATLAS operation (detector, data quality and calibration, software, world-wide computing, including all kinds of shifts …) requires ~ 800 FTE (physics is not an OT) OT are distributed in a fair way across Institutions: proportional to the number of authors - students get favorable treatment as they are weighted new Institutions contribute more the first two years (weight factors 1.5, 1.25) 200 FTE (out of 800 total) are for shifts: ~ shifts in 2010 (~20 per author) - 70% CERN-based (Control Room or on-call); 30% remote shifts - we have recently reduced the number of Control Room shifts by 15% - as we gain experience  less shifts in general, in particular less CERN-based shifts Funding Agency Covered-expected expected Distribution per FA in 2009 (CERN-based shifts not included) Zero means ok, negative is bad FTE requirements and FA contributions reviewed and updated yearly

Shutdown activities 6 Most of the active detectors components have been switched off for the Xmas break. This has been the occasion for fixing some known problems or upgrade some components in view of the long run in front of us

Shutdown activities 7 All magnets were left floating in temperature to save operation resources and allow some interventions to fix problem (Shield Refrigerator cryo-filter clogging and Current Lead thermal repair) Phase separator temperature Toroid inlet temperatur e At 4K, start of Helium pumps Ramp to 20.4kA Cool down of Toroids and Solenoid 28 Jan-11 Feb, 13 days from start at 126K to Cryo_ready flag Since then we have established all records on magnets stable operation !

Shutdown activities Fixed a water leak in the caver floor Consolidated the access structure to the inside of the detector Continued the installation of the staged EE chambers (barrel forward) Fixed problems of LV and HV in the muon spectr., fixed elect. problems Replaced gas filters (MDT), solved gas leaks problems RPC brought trigger coverage to practically 100% Got CSC readout chain operational inside the overall TDAQ system Added redundancy to several infrastructure key elements (electrical and UPS distribution, magnet safety, ventilation, …. ) Anticipated yearly maintenance on various safety systems Consolidated gas and detector cooling systems Installed the first ALFA detector station (1/8), testing methods and time ……

Detectors status 9

Pixel tracker 10 p K d Pixel operation Recovered few modules Non operational 45 modules (2.5 %) Improved timing, soon ready for high number of bunches Pixel hits ad vertices in all ATLAS analysis dE/dx demonstrates how well the pixel-by-pixel calibration works and it has been widely used for all “re- discoveries” The resolution on the primary vertex in the beam direction would be much worse (40% effect) without for example the b-layer.

Pixel tracker 11 p K d Pixel operation Recovered few modules Non operational 45 modules (2.5 %) Improved timing, soon ready for high number of bunches Pixel hits ad vertices in all ATLAS analysis dE/dx demonstrates how well the pixel-by-pixel calibration works and it has been widely used for all “re- discoveries” The resolution on the primary vertex in the beam direction would be much worse (40% effect) without for example the b-layer.

SCT Tracker 12 Modules Excluded BarrelEnd-Cap- C End-Cap- A Total Cooling Loop -13- LV Problems 5(4)1(1)06(5) HV Problems 1(1) 4(0)6(2) RO Problems 2013 Other 1--1 Number of Modules Total Modules Excluded As a %

TRT (Transition Radiation Tracker) 13 Barrel End- caps pions electron 92%

LAr Calorimeters (LVPS & OTx) 14 Today: 58/58 operational FE-LVPS 5 have lost the redundancy on one voltage line Backup in preparation 2 vendors prepared 2 prototypes each A Source Selection Committee selected the best one Production Readiness Review Then place the order Production should be completed by end of 2010 Setting-up a large test bench at CERN for 16 units Long term running Installation next time we open the detector

LAr Calorimeters (LVPS & OTx) 15 Optical Transmitters Status For 19 FEB-OTx: VCSEL died between May 2009 & April 2010 The width of the optical spectrum has been found as an indicator of the weakness After the measurement was performed ( ) all the OTx which died had a narrow OS There are ~50 remaining OTx with narrow spectrum on the detector Narrow OS OTx have been kept OFF until mid-March (start of LHC) OS spectra measured three times since July 2009: stable Failure rate ~ 3/month. None since 3 weeks! Future 2 backup solutions in preparation (choose before the summer) B1: Replacement by a single VCSEL from a different producer B2: Replacement by a double VCSEL + layout of double fibers

Tiles Calorimeter 16 Cosmics: Signal /Noise = % Tile cells powered ON 3.2% cells are masked/bad for physics: 0.5% noise or dig. corrupted data 2.7% OFF : - 5 (1.9%) LVPS - 2 (0.8%) S-drawers We have a solution to be implemented in the next shutdown (needs opening)

Muon spectrometer (CSC flagged as a problem last RRB) 17 CSC now routinely run in the combined partition Very stable CSC DAQ operation Current Read-out rate limit 43 KHz, new versions expected at 53 KHz CSC tracking commissioning on-going, Ex: good Residual Pool distribution

Muon Spectrometer Performance (precision chambers) 18 MDT detector coverage very good: 99.7% Small sectors Large sectors Stand alone momentum resolution measured with cosmics

TGC trigger timing and efficiency : first results TGC Trigger timing TGC Trigger efficiency vs P T

Today’s major worries Tiles Calorimeter LV power suppliers failure (5 out of 256 modules since ~8 months) LAr OTX : additional failure of the light emitting component (VCSEL) on optical transmitters (1 every 2-3 weeks) Keep the evaporative cooling plant operational (proximity compressor plant). Magnets shield refrigerator filter clogging (H 2 O contamination) Follow up evolution of power supplies failures in the muon spectrometer Follow up evolution of fragile gas inlets (RPCs) 20 Solutions are being worked out, but it requires a 11 weeks shutdown to make the interventions possible (next Xmas period ?)

Today’s major worries Tiles Calorimeter LV power suppliers failure (5 out of 256 modules since ~8 months) LAr OTX : additional failure of the light emitting component (VCSEL) on optical transmitters (1 every 2-3 weeks) Keep the evaporative cooling plant operational (proximity compressor plant). Magnets shield refrigerator filter clogging (H 2 O contamination) Follow up evolution of power supplies failures in the muon spectrometer Follow up evolution of fragile gas inlets (RPCs) 21 A new evaporative cooling plant is being evaluated and is under study A major upgrade of possible single point of failure is being pursued. It should be ready by 2012

ID evaporative cooling plant problems 22 Important traces of debris impacts have been found on the cylinder and piston head. The origin of the failure and the debris has been identified in the suction valve of the first stage of the compressors. A new problem was found in March on 2 out of the 7 compressors, which forced us to a major repair once more …. But we managed to keep the plant nevertheless operational (with 4 units) …. No impact on physics!

ID evaporative cooling plant : 2 solutions under evaluation 23 PR thermal screen others 4 liquid lines 4 gas lines condenser liquid tank pneumatic valve manual valve manual valve dummy load Heater BPR pixel 6 X SCT manual valve pneumatic valve Low temperature chiller (-70 C) UX15 USA15 Surface Full thermo-siphon solution which uses gravity to establish correct pressure conditions, no active mechanical components …. But it requires a large chiller plant on surface to condensate the liquid!

ID evaporative cooling plant : 2 solutions under evaluation 24 PR thermal screen others 4 liquid lines 4 gas lines condenser liquid tank pneumatic valve manual valve manual valve dummy load Heater BPR pixel 6 X SCT manual valve pneumatic valve Standard Chiller UX15 USA15 Surface Hybrid solution where condensation is helped by a new generation of compressors (vibrations and oil free, magnetic bearings) …. It requires a standard chiller plant on surface (-10C)! One of such compressors is now under test at CERN!

ID evaporative cooling plant : Thermo-siphon solution R&D 25 Tests of a mini thermo-siphon in bldg 191 successfully finished : o13 meters height, silent no mechanical stress oStable operation at -22 o C o-30 o C reached oStart up procedure and limitations well understood Next step : installation and test at Point1 oA full (geometrical) scale thermo-siphon circuit should allow us to study thermo-dynamics and time constants and to study blends C3F8-C2F6 oVertical piping installed from SH1 to USA15 level 3 Our goal : ready for 2012 shutdown

Magnet system consolidation work 26 Most shut-downs are related to cryogenics : 1) Today we have 1 main compressor in the Main Refrigerator, when it breaks we are down for 9-12 months. Cure: install redundant main compressor for the Main Refrigerator 2) We are experiencing several problems of filter clogging (water contamination). To solve the problem we have just identified an air dryer to install in the next few months 3) The main Helium pump represents another single point of failure, solutions are been worked out, this adds to other consolidation needs on vacuum, controls, ….. All must be ready for 2012

Today’s major worries Tiles Calorimeter LV power suppliers failure (5 out of 256 modules since ~8 months) LAr OTX : additional failure of the light emitting component (VCSEL) on optical transmitters (1 every 2-3 weeks) Keep the evaporative cooling plant operational (proximity compressor plant). Magnets shield refrigerator filter clogging (H 2 O contamination) Follow up evolution of power supplies failures in the muon spectrometer Follow up evolution of fragile gas inlets (RPCs) A new potential problem of hot cells in the LAr Had endcaps is being investigated 27

What is next on the detector side ? The detector is ready for a long run in 2010/2011. It is performing well We have solutions for the problems we are facing. To fix the Calorimeters % problems we will need access and therefore enough time to open and close the detector (~11 weeks) A consolidation of the cryogenics system and of the evaporative cooling plant is foreseen for the long shutdown in We are actively preparing it. We have learned enormously on the way to operate the detector. Now we can start to optimize the necessary resources, in particular the manpower needs for operation! 28

… and on the medium/long term ? (upgrade/consolidation) We are developing plans in 3 phases: Phase 0: when we will fix all problems we know (cryogenics, evaporative cooling plant, calorimeters LVPS, optical transmitters, various single points of failure,….). We will also substitute the Fe beam pipe with a lighter one (Al or Al/Be) in order to minimize radiation backgrounds  2012 LHC shutdown Phase 1: when we have collected enough statistics (at least 50 fb -1 ) and we will feel ready to make changes to the detector itself. We want the best possible detector for the bulk of the data we will take at LHC (~300fb -1 ). We need then a detector capable of ultimate Luminosity. We can improve on b- tagging and on the sharpness of the LVL1 trigger Phase 2: we will then prepare the detector for the sLHC challenge. We will need to construct and install a new ID (after fb -1 ) 29

30 Our strategy ! Phase -0 Phase -1 Phase -2 Int. Luminosity year Shutdown requirements : Phase-0 : months (defined by the LHC consolidation) Phase-1 : 8-9 months (time necessary to install at least the new pixel b-layer) Phase-2 : months to install and debug the new ID detector Consolidation + new beam pipe - Be ready for ultimate Luminosity - Insert new pixel b-layer - Upgrade various systems for a better and sharper LVL1 trigger Be ready for sLHC New ID + solve LAr end-caps problems We need to input our requirements in the overall LHC optimization plans

31 Our strategy for Phase-1 Phase -0 Phase -1 Phase -2 Int. Luminosity year We are preparing projects to be ready for phase-1 : - The first one is the insertable pixel b-layer (IBL). We will be ready at the end of 2014, in case the pixel detector will start showing problems. We will then install it as soon as a long shutdown can be scheduled. The construction is starting. We have drafts of a TDR and MOU - We are in the process of defining other projects, which can be organized in a way similar to the IBL. Most of these projects relate to an upgrade of the trigger system (more detector trigger granularity in the muon system, new generation of trigger hardware, a fast track processor, ….) - Be ready for ultimate Luminosity - Insert new pixel b-layer - Upgrade various systems for a better and sharper LVL1 trigger

The present 7m long section of the beam-pipe will be cut (flange too big to pass inside the existing pixel) and extracted in situ: The new beam-pipe with the IBL will be inserted at its place. IST IBL Support Tube Alignment wirers PP1 Collar IBL (insertable B layer) Detector IBL Staves Sealing service ring Existing B-layer IBL (Staves)

Technical Status of the IBL Project FE-I4 – New pixel front-end chip for IBL 20 x 19 mm 2 real-estate, more that 70 M-transistors, largest HEP chip ever. 2 year design work for a team of ~15 engineers + several physicists from 5 laboratories. Three design reviews: 17/3/2008, 3-4/11/2009, 16/4/ submission to IBM: 17/5/2010 Sensor prototypes for FE-I4 under processing – 3 technologies considered: Planar Sensors, 3D Sensors, Diamonds. Expected sensors bump-bonded to FE-I4 for next fall IBL Layout finalised – 14 staves with 32 FE-I4 chip modules at R=3.2 cm Stave baseline (following last December review’s recommendations) Low density carbon foam (ρ = 0.2 g/cm 3 ), thin wall titanium cooling pipe (d=2mm), CO 2 cooling. Fitting and permanent cooling joints under prototyping. FEA analysis on going, thermal figure of merit measurement on samples Mechanical design of the whole IBL detector 3D model and FEA for the whole detector on going. Installation mock-up under construction in bld.180 at CERN. Internal electrical services, flex hybrid in prototype phase. New ROD/BOC (off-detector readout). Modernized version of the Pixel VME ROD – more compact (x4 more channels/board) increased performance, large reduction of component count with state of the art FPGA technology.

Memorandum of Understanding IBL Memorandum of Understanding (MoU) Between The ATLAS COLLABORATION, and Funding Agency/Institution of the ATLAS Collaboration IBL MoU – Steps toward project shaping: “IBL Kick-off” meeting (8/7/2009) – Institutes express their interest in the IBL based on project WBS (Workpackage Breakdown Structure). Sharing of Resources (draft) discussed in the (interim) Institute Board (1/3/2010) – Contribution to the Cost presented to the National Contact Physicists in ATLAS (ATLAS NCP meeting – 25/2/2010). IBL interim MoU Ad Interim MoU until sensor technology is chosen (Planar Silicon / 3D Silicon / Diamond) - Decision on sensor technology (early 2011) – Sensor R&D and IBL communities work in tight collaboration to finalise a design matching IBL specification. Consolidate interest of Institutes and availability of funds

MOU Annex 4: Tentative Contribution to IBL Note: the numbers in the table "are not final, nor are the suggested financial contributions yet firm, but are meant for a common overall discussion.” Technology options refer to supplementary costs that are sensor technology specific and will be known before the definite MoU takes effect. So far, France, Italy and US have requested their shares to be moved from M&O B to Project part.

36 Phase-2 Upgrade (sLHC) We have centrally organized a vigorous R&D program for most of the technology we have to act on (more then 20 active R&D projects have been approved and are operational) The optimization of the layout of the new Inner Detector is at the moment the major concern. Most of the work is on simulation! The process is ongoing The first step of detailed engineering has started, we are now facing a new phase where we need to decide on the construction of large prototypes (staves, modules, services layout, support structures,….) to demonstrate feasibility. The time needed for mass production is probably around 7-8 years, once the project is fully defined

37