Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 MQXFA Functional Requirements Ruben Carcagno October 30, 2015 1.

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Advertisements

Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
23 October 2005MICE Meeting at RAL1 MICE Tracker Magnets, 4 K Coolers, and Magnet Coupling during a Quench Michael A. Green Lawrence Berkeley Laboratory.
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Progress Report V. Kashikhin for Superconducting Magnet Team.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
LARP review, Fermilab, 6/10/2013Magnet Project Overview – G. Sabbi 1 HL-LHC IR Quadrupole Magnet Project Overview GianLuca Sabbi Internal Review of proposed.
CRYOGENICS AND POWERING
E. Todesco PROPOSAL OF APERTURE FOR THE INNER TRIPLET E. Todesco CERN, Geneva Switzerland With relevant inputs from colleagues F. Cerutti, S. Fartoukh,
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
DOE Review of LARP – February 17-18, 2014 Helene Felice P. Ferracin, M. Juchno, D. Cheng, M. Anerella, R. Hafalia, Thomas Sahner, Bruno Favrat 02/17/2014.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
LQS01 Test Preparation and Test Plan LARP Collaboration Meeting 12 LBNL - April 8-10, 2009.
HL-LHC/LARP, QXF Test Facility Workshop– R. Carcagno QXF Test Requirements Ruben Carcagno BNL Workshop December 17, 2013.
11 T Nb3Sn Demonstrator Dipole R&D Strategy and Status
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
Title – xxxx 1 LARP & US-HiLumi Contribution to the Inner Triplet Quadrupoles G. Ambrosio Cost and Schedule Review CERN, March 9 th -11 th 2015.
February 13, 2012 Mu2e Production Solenoid Design V.V. Kashikhin Workshop on Radiation Effects in Superconducting Magnet Materials (RESMM'12)
Lab Coordination Meeting 3/21/13LHC IR Quadrupole Plan – G. Sabbi 1 LARP Magnet Systems Plan GianLuca Sabbi Lab Coordination Meeting March 21, 2013.
Joint HiLumi LHC-LARP Meeting – May 11-13, 2015 MQXFA Functional Requirements Ruben Carcagno May 13,
Review of Quench Limits FermilabAccelerator Physics Center Nikolai Mokhov Fermilab 1 st HiLumi LHC / LARP Collaboration Meeting CERN November 16-18, 2011.
General Considerations for the Upgrade of the LHC Insertion Magnets
CLIC Workshop th -17 th October 2008 Thomas Zickler AT/MCS/MNC 1 CLIC Main Linac Quadrupoles Preliminary design of a quadrupole for the stabilization.
F. Savary Question 1 A. Magnet design criteria for the prototype and production magnet to be tested before the installation into the tunnel.
5 th Joint Hi-Lumi LHC-LARP Annual Meeting 2015 SC Link Protection A.Ballarino 28/10/2015.
Cold powering test results of MBHSP102 Gerard Willering, TE-MSC-TF With thanks to Jerome and Vincent and all others from TF for their contribution.
Heat loads and cryogenics L.Tavian, D. Delikaris CERN, Cryogenics Group, Technology Department Accelerators & Technology Sector Friday, October 15, 20101HE-LHC'10.
Q4 MAGNETS FOR HL-LHC J.M. Rifflet, M. Segreti, E. Todesco WP3 - Q4 magnets for HL-LHC 5th Joint HiLumi LHC-LARP Annual meeting Research supported.
MQXF Workshop on Structure, Alignment, and Electrical QA – Feb 2-4, 2016 Requirements and feedback form LARP structure review Ruben Carcagno February 2,
HiLumi-LARP Annual Meeting November 2014 MQXF pre-series and series magnets fabrication plans Ruben Carcagno November 19,
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
LARP review, Fermilab, 6/10/2013Magnet Project Overview – G. Sabbi 1 HL-LHC IR Quadrupole Magnet Project Overview GianLuca Sabbi Internal Review of proposed.
Super Fragment Separator (Super-FRS) Machine and Magnets H. Leibrock, GSI Darmstadt Review on Cryogenics, February 27th, 2012, GSI Darmstadt.
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
MQXFS01 instrumentation, Projecting towards MQXFA D. Cheng, S. Myers, H. Pan, X. Wang 10/14/20151.
HL-LHC Meeting, November 2013D2 Status and Plans – G. Sabbi 1 D2 Conceptual Design Status and Next Steps G. Sabbi, X. Wang High Luminosity LHC Annual Meeting.
DOE Review of LARP – February 17-18, 2014 Helene Felice P. Ferracin, M. Juchno, D. Cheng, M. Anerella, R. Hafalia, Thomas Sahner, Bruno Favrat 02/17/2014.
First Q4 cold mass engineering follow up meeting 16/03/2016 Q4 Status update H. Felice, M. Segreti, D. Simon and JM. Rifflet.
MQXFS1 Test Results G. Chlachidze, J. DiMarco, S. Izquierdo-Bermudez, E. Ravaioli, S. Stoynev, T. Strauss et al. Joint LARP CM26/Hi-Lumi Meeting SLAC May.
LQS01a Test Results LARP Collaboration Meeting 14 Fermilab - April 26-28, 2010 Guram Chlachidze.
Workshop on Appraisal of Disassembled Magnets: Lessons learned March 17 th, 2005 Boundary Conditions-Technical Specification Jos Vlogaert.
Superconducting Cryogen Free Splittable Quadrupole for Linear Accelerators Progress Report V. Kashikhin for the FNAL Superconducting Magnet Team (presented.
DOE Review, 6/2/2011Answers to Committee Questions – Magnet Systems Answers to committee questions - magnets.
Jim Kerby Fermilab With many thanks to Vladimir Kashikhin, the FNAL, KEK, and Toshiba teams. SCRF BTR Split Quadrupole ILC ML & SCRF Baseline Technical.
Status of the PANDA Solenoid Magnet Production in BINP
CBM magnet overview of the BINP work
MQXC Nb-Ti 120mm 120T/m 2m models
Hervé Allain, R. van Weelderen (CERN)
Hervé Allain, R. van Weelderen (CERN)
SLHC –PP WP6 LHC IR Upgrade - Phase I.
11T Magnet Test Plan Guram Chlachidze
Model magnet test results at FNAL
The HL-LHC Circuits: Global View and Open Questions
MQXF Goals & Plans G. Ambrosio MQXF Conductor Review
Hervé Allain, R. van Weelderen (CERN)
Circuits description and requirements - Closed Session-
Introduction to the technical content The Q4 magnet (MQYY) for HL-LHC
Cooling aspects for Nb3Sn Inner Triplet quadrupoles and D1
MQYY: superconducting Quadrupole magnet for Hl-lhc
Cooling aspects for Nb3Sn Inner Triplet quadrupoles and D1
PROPOSAL OF APERTURE FOR THE INNER TRIPLET
Design of Nb3Sn IR quadrupoles with apertures larger than 120 mm
Updated concept of the CBM dipole magnet
Design of Nb3Sn IR quadrupoles with apertures larger than 120 mm
as a prototype for Super c-tau factory
MQXFS1e – PH-to-Coil hipot tests
Review of Quench Limits
Hi-pot results summary
Electrical integrity of magnets and coils
J. Fleiter, S. C. Hopkins, A. Ballarino
Presentation transcript:

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 MQXFA Functional Requirements Ruben Carcagno October 30,

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 Functional Requirements A clear specification of functional requirements for U.S. deliverables is needed to support the DOE Order 413.3B project management process for the US-HiLumi project These requirements should not be embedded in other documents (e.g., design reports) or mixed with requirements for other systems – Functional requirements for the U.S. project deliverables should be documented in a stand-alone document – These requirements should be such that their verification means that the project deliverable(s) are fit for the intended use They do not include design parameters, only the functions that the deliverable must satisfy – Functional Requirements must be reviewed and approved by the end user (CERN), well in advance of the project baseline establishment for the CD-2 DOE review A signed document should be finalized in less than a year from now 2

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 Main Project Planning Documents 3 Project Execution Plan (PEP) Project Management Plan (PMP) Risk Management Plan (RMP) Quality Assurance Plan (QAP) Change Control Management Plan Procurement Management Plan Manufacturing: Manufacturing Plan (MP), Procedures, etc. Risk Registry (RR), Risk Analysis Performance Baseline (PB) Cost Baseline Scope Baseline Schedule Baseline Acquisition Strategy (AS) Mission Need Statement (MNS) Integrated Safety Management Plan KPPs, WBS, WBS Dictionary Key Assumptions, KPPs, Baseline, Funding Profile, PM Strategy BOEs, Time- Phased, Escalation, Contingency BOEs, RLS, Milestones, Constraints, Contingency Design: Reports (CDR, PDR, FDR) Drawings, Specifications, etc. Functional Requirements Specification (FRS) OBS, RAM, CAMs Alternatives and Risk Analysis Value Engineering Cost and Schedule Range, Key Milestones Procurement: Procurement Plan (PP), etc.

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 Scope This presentation is for the MQXFA functional requirements for Q1 and Q3 only: The MQXFA magnets for Q1 and Q3 are assumed to be identical A separate, similar functional requirements document is also available for the Q1, Q3 Cold Mass Assembly (LMQXFA/B) 4 SS vessel not part of MQXFA

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 Previous Example: MQXB FRS Example of a previous FRS for the present Inner Triple Quadrupole MQXB for Q2 Some parameters for MQXFA FRS were taken from the MQXB FRS, but they need to be confirmed by CERN 5

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 MQXFA FRS Draft prepared as a US- HiLumi project document to start discussions Attempts to collect all the functions that the MQXFA magnet must satisfy Several parameters need definition and confirmation by CERN 6

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 Functional Requirements Classified into two groups: – Threshold Requirements (T): project must meet Usually related to “nominal” parameters, but not always (e.g., we must train to ultimate current, which is 108% of nominal current) – Objective Requirements (O): project should meet and will strive to achieve Usually related to “target” or “ultimate” parameters, but not always (e.g., reliability requirements that are hard or too costly to verify such as number of thermal cycles) Acceptance criteria and procedures will be defined in a separate document – At CERN’s discretion, deliverables that fall short of the threshold requirements may still be acceptable Example: a magnet deliverable trained to 107% of nominal current instead of 108% (the threshold requirement) The MQXFA draft was first presented during the Joint LHC-LARP meeting on May 2015 and already went through several iterations with CERN 7

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 MQXFA FRS Table 8 Parameters in black are more certain. Parameters in red less certain or still under discussion Threshold Requirements Objective Requirements

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 Next Slides Next slides will provide an overview of the draft MQXFA requirements – These requirements should be such that their verification means that the MQXFA magnet deliverables are “fit” (suitable) for the intended purpose, i.e., they will satisfy CERN’s needs for HL-LHC The purpose is to generate discussions and answer questions such as: – Are there still any missing or improperly stated requirements? – Can we start converging on agreement for parameters in red? 9

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 MQXFA Physical Requirements T: 150 mm aperture, ≤ 614 mm outer diameter O: ≤ 1 mrad/5m twist, ≤ 100 um/5m straightness 10

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 Magnetic Field Requirements T: nominal gradient T/m, ultimate gradient 143 T/m (8 % above nominal) in superfluid helium at 1.9K and for a magnetic length of 4.2 m O: Fringe field target at TBD distance from the magnetic axis < 50 mT 11

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 Magnetic Field Requirements O: Field harmonics optimized at high field with the following targets: 12

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 Cryogenic Requirements T: Operate at superfluid helium bath at 1.3 bar and 1.9K T: Minimum cooling channel diameter is 77mm to accommodate two 74mm O.D. copper heat exchanger tubes T: 40% inner coil surface free of polyamide T: provisions for cooling passages are 8mm pole holes every 50 mm and free helium paths interconnecting the yoke cooling channel holes T: 20 bar peak pressure T: Maximum temperature gradient of TBD K during testing 13

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 Electrical Requirements T: ramp rate of 14 A/s T: maximum operating voltage of 800 V to ground during quench T: Nb-Ti leads for connection to the bus, stabilized and rated for 18 kA T: Splices to be soldered with CERN approved materials O: Splice resistance target is less than 2 nΩ at 1.9K O: Provisions for routing LMQXFA/B superconducting busses T: 3 quench detection voltage taps, 2 voltage taps for each quench strip heater, 2 voltage taps for internal splice T: hi-pot test in liquid helium at 1 atm pressure with following limits: 14 Circuit ElementVmaxV hi-potI hi-pot Quench Protection Heaters - Coil500 VTBD< TBD µA Magnet Coil - Ground1,000 VTBD (2,500 V?)< TBD µA

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 Quench Requirements T: trained to a current of 108% (17.8 kA) of the nominal operating current O: reach nominal operating current with a target of no more than 1 quench after a room temperature thermal cycle T: must not quench while ramping down at 300 A/s from nominal current T: quench protection components compatible with CERN-supplied quench protection system 15

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 Radiation Hardness Requirements O: can withstand a maximum radiation dose of 30 MGy – Assumes beam screen with tungsten absorber (provided by CERN): 16

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 Reliability Requirements O: can survive 25 thermal cycles, 3,000 powering cycles, and 50 quenches 17

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 Interface Requirements T: Comply with Interface Specifications for: – Other LMQXFA(B) cold mass components – CERN Cryogenic System – CERN Power System – CERN Quench Protection System – CERN Instrumentation System 18 All these interface specifications To Be Defined

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 Safety Requirements T: comply with the corresponding CERN Work Package Launch Safety Agreement (LSA) specification (TBD) – Meeting scheduled for October 29 19

Joint HiLumi LHC-LARP Meeting – October 26-30, 2015 Path Forward The MQXFA draft was first presented during the Joint LHC- LARP meeting on May 2015 and already went through several iterations with CERN – Are there still any missing or improperly stated requirements? – Can we start converging on agreement for parameters in red? US-HiLumi Project Office is working with HL-LHC WP3 Manager (Ezio Todesco) to address these points – Process for final CERN approval? US-HiLumi is going to need a final, approved MQXFA requirements document in less than a year from now – Needed to support U.S. project baseline freezing prior to CD-2 20