1 Collaboration Meeting 33 - Glasgow 26 th June 2012 Design Layout Andrew Moss for Alan Grant, STFC.

Slides:



Advertisements
Similar presentations
Andrew Moss ASTeC MICE RF workshop 16t h February 2012 Daresbury Laboratory Response to RF review for the MICE RF system.
Advertisements

RF Specification discussion MICE RF workshop 16 th April 2012.
1 RF Workshop 16 th & 17 th April 2012 Design Layout Alan Grant, STFC.
19th – 20th of September 2007Cryogenic Expert Meeting at GSI, Jan Patrick Meier1/11 Cryogenic Experts Meeting at GSI, 2007 The SIS 100 Cryogenic Jumper.
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Andrew Moss ASTeC MICE Project Board 28 th June 2011 MICE RF System.
MICE- AFC Unit Mechanical Design of the Cold Mass Support System Oxford University Rohan Senanayake.
Components for the low- maintenance switch Components for the low maintenance track Schwihag RBH system.
Collaboration meeting, RAL, 4 th – 7th November 2009 Andrew Moss ASTeC Collaboration meeting, RAL, 10 th – 13 th november 2009 MICE RF Amplifier Status.
Andrew Moss Daresbury Laboratory Collaboration Meeting th 19 th October 2012 RAL MICE RF System review.
RF Layout 3pi/2 for Discussion. 2 RF Design mtg 14/1/15 Output line from amplifier is lower than the PRY, needs to go high to clear PRY to couple to South.
MICE Hall – South Mezzanine Jason Tarrant - STFC l Contents »Device checks with current South Mezzanine »South Mezzanine change summary »Conclusion.
Magnet quench during a training run Magnet electrical circuit schematic PROGRESS ON THE MODELING AND MODIFICATION OF THE MICE SUPERCONDUCTING SPECTROMETER.
LCLS Undulators October 14, 2004 Heinz-Dieter Nuhn, SLAC / SSRL MMF Review Introduction to the LCLS Undulators Heinz-Dieter Nuhn,
1 RAL Integration Issues MICE Collaboration Meeting, Osaka, August 1-3, 2004 Elwyn Baynham, Paul Drumm, Yury Ivanyushenkov, Tony Jones RAL.
1 Status of infrastructure MICE Video Conference, August 17, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department.
DESIGN OF A HIGH POWER TEST STAND FOR ESS SPOKE CAVITIES
Assembly, Installation and Interfaces Steve Virostek Lawrence Berkeley National Lab RFCC Module Design Review October 21, 2008.
Andrew Moss ASTeC 7 th December 2011 MICE RF System.
Andrew Moss Daresbury Laboratory Collaboration Meeting th -16 th February 2013 Coseners House MICE RF HP System rprogress.
Collaboration meeting, DL, 19 h – 23 h October 2008 Andrew Moss ASTeC Collaboration meeting, DL, 19 th – 23 th October 2008 MICE RF distribution system.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
K. Alam, CLIC workshop, October 16-18, CLIC workshop, October 2007 Working group “ Two beam hardware and integration” Test module in the two.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
1 MICE RF Daresbury Laboratory Support Joe Orrett - ASTeC.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
IP-BSM Improvement Work N. Terunuma 2012/6/26 ATF2 Project Meeting.
Magnetic Shielding Issues Roy Preece STFC - RAL. Overview Issues Items in harms way – Step IV Step IV mitigation plan –Racks –Compressors Current / Future.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
Andrew Moss ASTeC Collaboration meeting CM29 15 th - 18 th February 2011 MICE RF System.
Magnetic Shielding Roy Preece. Issues Cooling channel initially designed without return yolks. Current North and South shielding walls designed to encapsulate.
MICE Integration Engineering Jason Tarrant - STFC l Contents »Device Interfaces – General »AFC »Spectrometer Solenoids »RFCC »EMR / KL »South Mezzanine.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 June 2006 No 1 /17 LARP Phase II Secondary Collimator RC1 Collimator Test Program Plan Forward Revised.
1 Layout and Installation MICE Collaboration Meeting, RAL, October 27-29, 2004 Elwyn Baynham, Tom Bradshaw, Paul Drumm, Matthew Hills, Yury Ivanyushenkov,
Andrew Moss ASTeC CM32 9t h February 2012 RAL MICE RF System.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l History l Requirements l Environment l Design l Structural Integrity l Preparation l.
1 SPL Collaboration Meeting dec 08 - WG1 Introduction First SPL Collaboration Meeting Working Group 1 High Power RF Distribution System Introduction.
Step IV Construction North Side Walls and End Walls May 2015 Stephen Plate, Brookhaven National Laboratory.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
QBPM System Installation Systems –Rack mount chassis –LO and CAL RF cable plant ( need 714Mhz from eels bedroom) –Down mix boxes –DC power cable plant.
Progress on the MICE RF High Power Drive Systems K Ronald, University of Strathclyde For the MICE RF team 1MICE CM38 RF Parallel Session.
1Matthias LiepeAugust 2, 2007 Future Options Matthias Liepe.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
Andrew Moss ASTeC TIARA Mid term meeting 12 th 14 th June 2012 CIEMAT ICTF Progress on the MICE RF System.
MICE RF System Overview Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory Andrew Moss STFC Daresbury Laboratory MICE UK.
Contents Jason Tarrant STFC Aim of Presentation to show: l Problem of compressors located at south shield wall l Description of compressor layout and services.
1 Status of infrastructure MICE Collaboration Meeting, Frascati, June 26-29, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
1 First wall mods status NCSX SIT Meeting July 1, 2002 Points at 0, 30, 60 degrees from Art Points x in cross sections RF launchers bigger issue.
1 First wall mods status NCSX SIT Meeting Aug 12, 2002 Points at 0, 30, 60 degrees from Art Points x and 1.00 in cross sections First try at vessel.
MICE Construction Project Update: SSs, PRY, Cavities, Tracker… 1MAP Friday Meeting – January 30, 2015 Alan Bross.
MICE RF – Installation at RAL Tim Stanley RAL 7 November 2013.
This material is based upon work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC Michigan State.
1 Implementation at RAL Iouri Ivaniouchenkov on behalf of Elwyn Baynham, Tom Bradshaw, Tony Jones, Jim Rochford Engineering Department, RAL MICE Collaboration.
RF Module Integration Colin Whyte University of Strathclyde on behalf of the MICE collaboration 1RF Review 9th & 10th Sept '15 Abingdon.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 MICE CM29 Engineering Summary Cooling channel moving platforms – Norbert Floor Beams and plates – Andy L Magnetic modelling – Mike RF Engineering – Andy.
Radiation Shutter Re-Purposing Roy Preece STFC RAL 18 th December 2014.
Andrew Moss ASTeC, Daresbury Laboratory October 2010 MICE RF Amplifier Status.
DT-LHCb coordination meeting 18 April 2016
MICE CM28 Engineering Session Summary (On behalf of Wing)
RF Layout 3pi/2 for Discussion
Introduction Jason Tarrant – Integration Engineering Step IV Removal
CEPC RF Power Sources System
Progress activities in short bunch compressors
Cooler e-source Magnetized Beam LDRD Progress Report
Cooler e-source Magnetized Beam LDRD Progress Report
Presentation transcript:

1 Collaboration Meeting 33 - Glasgow 26 th June 2012 Design Layout Andrew Moss for Alan Grant, STFC

Overview Review Panel Recommendations Coax Distribution Coax Installation Coax supports Magnetic Field – 4616 pre amp Next Steps Summary 2

Recommendation from Review Panel RF Distribution Coax high power phase shifters not warranted. Relocate Hybrid splitters from behind shield wall. Provides more space for access to amplifiers. Reduces the length and volume of 4” coax. Were possible reduce number of coaxial joints. Mechanical Installation & Maintenance Try and install all under floor coax distribution at stage V. Design improved mounting mechanism to minimise protrusions. Improve lateral movement capability for any miss-alignment of coax distribution during installation. 3

RF Layout – view from cooling channel side 4 high power phase shifters removed. no 4 inch coax over wall. hybrid splitters moved - more accessible manually adjustable line trimmers to take up errors in coax length easier to assemble – introduced flexible coax.

RF Layout – view behind shield wall 5 hybrid splitters moved – space freed up behind wall. no coax distribution going under the wall. 6 off 6 inch coax over the top of wall. Coax length matching now takes place other side of wall – space less of a constraint. improved access for installing amplifiers.

RF Layout – view behind shield wall 6

Fixed Phase Operation Schematic Mechanical Line Trimmers for assembly uncertainties. 7 Mechanical Line Trimmers Installed in 3 of the lines to each cavity pair. Primarily to take up the assembly uncertainty. 82mm of travel, implies +/- 10 degs of trimming might be available.

Line Trimmer Arrangement to South Side RF Couplers 8 Beam Direction Mechanical Line Trimmers 82mm travel = 20deg Direction Coupler - 1 to each Coupler 4” Flexible coax for any mis-alignment

Line Trimmer Arrangement to North Side RF Couplers 9 Beam Direction Mechanical Line Trimmers 82mm travel = 20deg 4” Flexible coax for any mis-alignment Direction Coupler - 1 to each Coupler

Clear Access for removal of AFC 10 AFC’s can be removed without having to dismantle any of the RF coax system

Coax Sections – Installation/Removal Concerns 11 ~55mm required to clear mating flangeFlexible coax system in each line. Have adjustment in clamp system. Phase shifters to be installed last in assembly sequence

Coax Supports 12 Rotation Vertical Longitudinal Horizontal CLAMP TEE SLOT RAILS

Pre Amp Tube Position Behind Shield Wall Pre amp tube below level of shield wall ~ 0.16m and spaced ~ 0.53m back. Initial magnet field analysis predict approx 8-10 gauss. Wall Tube 4616 Pre Amp

Next Steps – Design for Fixed Phase Angle of 124 degrees 14

RF Procurement Don Summers has been supplied with RF component procurement list which he is working on. These include:- Line trimmers (mechanical adjustment) Dummy Loads Hybrid Splitters Reducers Directional Couplers Circulators Elbows 15

Summary Addressed all of the issues raised by the review panel. Changed the design as per their recommendations. There are no clashes with the steel work on both the cooling channel false floor and the parked position false floor – lighting trunking clash on South mezzanine floor which is being resolved. Some concrete on south side needs to be removed. Installation made simpler with introduction of flexible coax and relocation of hybrid splitters. No clash issues with moving AFC’s to parked position on false floor. Magnetic field calcs indicate no issues for 4616 pre amp. Fire officer has been consulted and agreed that what is proposed causes no access problems or issues. 16