LS1 planning meeting 26.4.2013. 25/4/13 ALICE TBStatus of LS1 activities - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare.

Slides:



Advertisements
Similar presentations
TC meeting /11/14TC meeting2 ALICE LS1 plan from now till MarchWeeks Install TRD infrastructure46 TRD4&5 (and counterweights removal)47.
Advertisements

1 Installation of Delphi Frame  ITS Installation.
LS1 planning meeting Activities weeks 13, 14 & 15 22/3/13LS1 planning meeting - A.Tauro2.
08/24/07Shutdown’07 Week 3 F.G. Garcia1 MTA beam line installation Weekly Report August 24, 2007 Period covered: August 17 th to August 24 th (Week 3)
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
ALICE planning meeting /12/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
ALICE planning meeting /1/11 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
TC meeting P2 planning wks 7&8 A.Tauro
Notes After TIG 17/7/08 HF+ Move out of garage: Aug 15* Platform+table+collars+racks+BP support (jack up for platform) = 3 days Controls for motors = 1.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
DCS - general Unscheduled power cut Wed. morning ( , human error) –DCS (and HLT) off, due to UPS on bypass –In the middle of DB migration, had.
winter shutdown preparatory meeting A.Tauro /1/12ALICE winter shutdown schedule - A.Tauro 1.
winter shutdown planning A.Tauro
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
LS1 reference slides LS1 plans Detector’s plans Services and central systems availability 8/2/13LS1 planning meeting - A.Tauro1.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
LS1 planning meeting Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore.
LHC Insertions Upgrade Working Group (LIUWG) Space available in tunnel Y. Muttoni.
ALICE Collaboration Meeting Heidelberg Services Update  Progress on services Detector cabling Gas systems Cooling systems  Rack footprint  Primary electrical.
SU ACTIVITIES PENDANT LS1 CMS ALICE. Antje Behrens | SU pendant LS1 day| | EDMS | page 2 CMS Quoi (quelles activités prévues pendant.
P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.
TS4 preparatory meeting TS4 – weeks Underground access possible in week 51 – as from Monday morning 9:30 –Ulli and Philippe will start.
winter shutdown preparatory meeting A.Tauro /12/11ALICE winter shutdown schedule - A.Tauro 1.
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
1st LTEX 22 June 2009D.LACARRERE1 Protection of UX85 EDMS No IP8 Current Status & Plans  UX85 Expt Area  RB84 (8-7 sector)  RB86 (8-1 sector)
ALICE 5 o’clock meeting Wk 51. INDICO You’ll find this meeting here: – The full shutdown planning.
Claudio Bortolin. Drilling: – tungsten carbide tip welded on twisted ss cable – drill to operate the rotation – counter-flow at 200 mbar w/manometer to.
ALICE TC meeting – Plans for the next technical stop A. Tauro.
TS planning meeting 7 to 11 Nov Technical stop Wk 45: Monday 7 th to Friday 11 th November Ramp down magnets (SL): Mon 8:00 – 8:30 (latest) RP search.
winter shutdown planning A.Tauro
winter shutdown planning A.Tauro
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
TS May 9-12 – Schedule SL instructions: Both magnets ramped down Monday May 9 th 7:00 latest Thursday: check with CCC before restarting magnets: – TE-EPC.
ALICE planning meeting /2/11 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
TC meeting P2 planning wks 9&10 A.Tauro
ALICE Arturo Tauro Werner Riegler.
TC meeting LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS extraction, remove RB24 beampipe and PMD10 Remove.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
André Augustinus Infrastructure  Turbines  Radmon  Thermocouple readout  Netgear redundancy  Other cavern items  Cooling CRs  Other CR and surface.
TPC Collaboration Meeting Peter Glassel 1 Reminder on Installation Schedule (ALICE Forum June 2002)  Install Muon magnet directly into experimental.
ALICE 5 o’clock meeting Wk 49. INDICO You’ll find this meeting here: – The full shutdown planning.
winter shutdown planning A.Tauro /1/12ALICE winter shutdown schedule - A.Tauro 1.
TC meeting P2 planning wks 5&6 A.Tauro
TS2 preparatory meeting A.Tauro. General information LHC- TS2: from Monday 31st 6am, to Friday 4th 5pm LHC beam stops on Monday morning.
LS1 planning meeting /7/13LS1 planning meeting - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS.
1 Planning DCS WS L.Jirdén. 2 TPC HMPID ACORDE FE PC Console DSS Disk SRV DB-SRV App GW sensors actuators DSS sensors actuators PC room SXL2.
1 Update on Power Supplies TB L.Jirden u LV u Concerns u Orders & deliveries u Maintenance u HV u Overview u purchasing.
TS3 preparatory meeting 14/9/2012 TS3: 17-21/
ALICE 5 o’clock meeting Wk INDICO You’ll find this meeting here: – The full shutdown planning.
TS3 preparatory meeting A.Tauro. General information LHC-TS3: from Mon 9 6am, to Fri 13 5pm LHC beam stops on Mon morning at 6:00.
TC meeting P2 planning wks 3&4 A.Tauro
ALICE planning meeting /11/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
DCal-ALICE integration and installation plan and status A. Tauro.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
ALICE Installation: Planning Meeting Agenda: 1- ALICE shutdown schedule 2- Miniframe removal sequence.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
EYETS planning A.Tauro.
ALICE 5 o’clock meeting Wk 51.
TS2 preparatory meeting
LS1 planning meeting - A.Tauro
LS1 planning meeting
ALICE 5 o’clock meeting Wk
TS1 preparatory meeting
Shutdown conclusion, LS1 and LS2 planning - A.Tauro
ALICE 5 o’clock meeting Wk
MON TUE WED THU
Sun Mon Tue Wed Thu Fri Sat
Sun Mon Tue Wed Thu Fri Sat
2016 | 10 OCT SUN MON TUE WED THU FRI SAT
Sun Mon Tue Wed Thu Fri Sat
Presentation transcript:

LS1 planning meeting

25/4/13 ALICE TBStatus of LS1 activities - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS extraction, remove RB24 beampipe and PMD10 Remove PHOS cradle and modules, transfer TOF crates on SF11-13 Modify L3 services and install YP for TRD1714 Modify L3 services, remove TRD17 and rework LV distr. TRD , DCal tests in SXL Modify L3 services, open low-beta and swap Q5L8 magnet, DCal tests in SXL Swap PHOS beams with DCal beams25-28 (tbc) DCal and PHOS services (1/2)31-33 Contingency34-35 (August) Install DCal Cradle36-38 DCal and PHOS services (2/2)39-40 Open Days – / Install 2 1/3 DCal modules41 Install 3 DCal modules (C-side)42-43 Rework LV distr. TRD Two weeks between 44 and 51 Xmas pause52-1 Done Ongoing

25/4/13 ALICE TBStatus of LS1 activities - A.Tauro3 LS1 plan 2013 – detailed plan weeks 18-30Weeks Modify L3 services18 Modify L3 services, TRD1019 Preparation for low-beta opening, DCal tests in SXL2 (?), drill holes L3 (C-side)20 Open low-beta start Swap Q5L8 magnet /5, Install UPSes22 Close low-beta23 24 Swap PHOS beams with DCal beams, TRD and TPC tanks (1w)25 Swap PHOS beams with DCal beams, CR1 racks (2d)26 Swap PHOS beams with DCal beams 27 Swap PHOS beams with DCal beams

25/4/13 ALICE TBStatus of LS1 activities - A.Tauro4 LS1 plan 2014Weeks Install 4 PHOS modules (incl.pre-commiss.)2-5 Install 3 DCAL modules (A-side)6-7 Install top/bottom counterweights8 Remove comp. magnet and Suspend Miniframe9-11 Install TRD with yellow platform (bottom)12-14 ‘Un-suspend’ Miniframe15-16 Reinstall TRD1717 Concrete walls & TRD installation frame18-19 Install TRD4-5 (top) & counterweights20-21 Remove TRD infrastructure22 Reinstall PMD, ZEM and comp. magnet23 Reinstall and bakeout RB24 beampipe Close plug, mobile shielding26-29

Activities weeks 18, 19 & 20 26/4/13LS1 planning meeting - A.Tauro5

Access situation No access restrictions foreseen 26/4/13LS1 planning meeting - A.Tauro6

Week 15 (8-14/4) UX25: TRD + P2tech: take out TRD17 (Mon) – L3 access from O-side only P2tech + ALTEAD: move L3 staircase from O-side to I-side (Tue) P2tech ALTEAD: install blocks + rails yellow platform on O-side (Tue) P2tech + ALTEAD: install yellow platform on O-side (Tue) TRD + ALTEAD: take out TRD7 (Wed) TRD: modify TRD7 in Low-Beta (Thu) TRD + ALTEAD: reinstall TRD7 (Fri) TRD + ALTEAD + P2tech: remove TRD8 (Sat) TRD: modify TRD8 in Low-Beta (Sun) Muon TRK: work on CH6L and CH5R (whole week) BE-ABP-SU: survey babyframe, TRD feet and A-side beampipe flange after each TRD removal (whole week) L3: TOF + PH-DT (gas): check C2H2F4 tightness (Mon) P2tech: L3 services modifications (whole week) TPC work on A-side (Tue ?) Surface: P2tech: load test DCal extension ribs (Mon) TRD + ALTEAD: move TRD17 to blue frame (Mon-Tue) P2tech + ALTEAD + Nantes: DCal insertion test in SXL2 (60 and 40deg ?) (Tue-Fri) Removal barracks 6120 (HLT), 6121 (MTR) and 6122 (MTG) (Mon-Tue) 26/4/13LS1 planning meeting - A.Tauro7

Week 16 (15-21/4) UX25: TRD + P2tech: reinstall TRD8 (Mon) P2tech + ALTEAD: remove blocks and install rails yellow platform on O-side (Mon) TRD + ALTEAD: take out TRD10 (Tue) TRD: modify TRD10 in Low-Beta (Wed) TRD + ALTEAD: reinstall TRD10 (Thu) Muon TRK: work on CH6L and CH5 R (whole week) FMD + P2tech: modify 2 FMD1 cooling pipes (miniframe) P2tech: install survey plate RB26 side P2tech + ALTEAD: remove ADC + BCM C-side Fire brigade test: ‘pompe relevage’ (Wed) L3: P2tech: L3 services modifications (whole week) –cut and remove 20 inox pipes along the PHOS (I-side) beam Surface: ALTEAD + P2tech: modify DCal infrastructure SXL2 (whole week) P2tech: install ZDC fences in SXL2 (provided by ALTEAD) SDD: swap SuperCarlosRX boards in CR4 (whole week) 26/4/13LS1 planning meeting - A.Tauro8

Week 17 (22-28/4) UX25: P2tech: move baby-frame (Wed) ALTEAD + P2tech: modify TRD infrastructure (Wed-Thu) TRD + P2tech: TRD10 extraction (Thu) Muon TRK: work on CH6L and CH5 R (whole week) DGS-RP: RAMSES maintenance BE-ABP-SU: survey UX25 RB26 (Tue-Thu) L3: P2tech + SPD: drill filter SR3 P2tech: L3 services modifications (whole week): –Remove 4 PHOS cooling pipes –Remove false floor (O-side) and modify the supports for the cooling pipes (interference with the new beams) –Install new cable tray for the cables which were lifted Surface: P2tech + ALTEAD + Nantes: DCal and PHOS insertion test in SXL2 (0deg) (Tue-Fri) LHC tunnel: ZDC: remove both detectors (Mon-Tue) 26/4/13LS1 planning meeting - A.Tauro9

Week 18 (29/4-5/5) UX25: TRD: modify TRD10 in Low-Beta (Fri-Sun) Muon TRK: work on ST4 (whole week) BE-ABP-SU: survey UX25 RB24 (Mon-Tue) P2tech: remove/reinstall steel plates RB24 to allow for survey measurement (Mon-Tue) P2tech: help for extraction and reinstallation of TRD11 (Thu-Fri) ACO: exchange old PMTs and check the functionality (mechanics, alignment, optical coupling) of the complete 60 ACO module system (start on Wed – several weeks) P2tech: remove CO2 bottles from UX25 (C-side, level 0) L3: P2tech: install new L3 ladders (top part, access from scaffolding) Surface: ALTEAD: move ALICE stuff from SX2-SA2 to b.185 (tbc) 26/4/13LS1 planning meeting - A.Tauro10

Week 19 (6-12/5) UX25: TRD + P2tech: reinstall TRD10 (Mon) ALTEAD + P2tech: removal of all equipment from cavern: rotator + control rack + tookboxes, YP, test equipment (1 rack, 1 box) (Tue-Wed) P2tech: reinstall L3 staircase (O-side) (Wed) Muon TRK: work on ST4 (whole week) L3: P2tech: install new gangway (I-side) P2tech + SPD: drill SPD filter (tbc) 26/4/13LS1 planning meeting - A.Tauro11

Week 20 (13-19/5) UX25: ALTEAD: open low-beta and swap Q5L8 magnet Muon TRK: work on ST4 (whole week) L3: P2tech: P test TRD pipes P2tech: start LV consolidation (TRD-TPC-TOF) O-side (whole week) Ouvaroff: remove scaffolding inside L3 (Fri) Surface: DCal + ALTEAD + P2tech: test in SXL2 26/4/13LS1 planning meeting - A.Tauro12

Visits in the coming weeks 26/4/13LS1 planning meeting - A.Tauro13

AOB /4/13LS1 planning meeting - A.Tauro14