WP 11.5.3: HIGH-BETA CAVITY DELIVERY A Wheelhouse ASTeC, STFC Daresbury Laboratory ESS SRF Elliptical Cavities Kick-Off Meeting CEA Saclay 15 th December.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Coupling Coil Test Facility Update Ruben Carcagno Fermilab September 20, 2012.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
Hydrogen Delivery System – R&D Activities T W Bradshaw M Courthold M Hills J Rochford Daresbury Controls Group etc…
MICE Collaboration Meeting Harbin, China 13 – 17 January 2009 Integration Issues By Wing Lau, Oxford University.
LINACs Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
RF Cavity / Coupling Coil Module
An SRF Single Cavity Horizontal Test Facility Tom Peterson, Fermilab May 10, 2005.
Naomi Wyles ASTeC STFC Daresbury Laboratory
From Research Prototype to Production
ESS cavities interfaces
Test Stands Roger Ruber Uppsala University ESS TAC4 16 Feb
IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
MICE Collaboration meeting (CM20) At RAL 10 – 13 Feb 2008 AFC Magnet – Status and Progress W. Lau, Oxford University.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62)
Americas Region: T4CM Status and Plans H. Carter TD SRF Dev. Dept. July 14, 2006.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
Harry Carter – LCFOA Meeting 5/1/06 1 LCFOA Technical Briefings: Cryomodules H. Carter Fermilab Technical Division.
Accelerator/WP High Beta Structures Alan Wheelhouse HIGH-BETA CAVITY DELIVERY April 21, 2015.
1Matthias LiepeAugust 2, 2007 Future Options Matthias Liepe.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
ESS WP 12 Project Management & Capabilities Overview Neil Bliss Projects & Mechanical Engineering Group Leader ESS PDR, Lund, 10 th November 2015.
HIGH-BETA CAVITY DELIVERY P McIntosh ASTeC, STFC Daresbury Laboratory ESS Technical Advisory Committee Lund 1 – 2 April 2015.
Accelerator/ Medium Beta Cavities Paolo Michelato INFN Milano - LASA April 21, 2015.
Shrikant_Pattalwar TTC 2015 Dec 1, 2015 SLAC 1 Horizontal Tests in a Vertical Cryostat Shrikant Pattalwar STFC Daresbury Laboratory UK.
Medium Beta Cavities Paolo Michelato, Paolo Pierini, and Carlo Pagani INFN Milano - LASA.
Medium beta cavities Paolo Michelato, Paolo Pierini, Carlo Pagani INFN Milano - LASA.
Industrial Participation & SRF Infrastructure at Fermilab Phil Pfund with input from Harry Carter, Rich Stanek, Mike Foley, Dan Olis, and others.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62) Manager.
HL-LHC Crab Cavity Review Debriefing Comments from LARP June 30, 2014.
Spreaders & Recombiners Beam Transport Michael Bevins May 30, GeV Upgrade - Beam Transport Spreader/Recombiner Dipoles and Layout, & Installation.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
SM18 cryogenics infrastructure upgrade L. Serio TE-CRG.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Accelerator/WP High-Beta Structures Alan Wheelhouse HIGH-BETA CAVITY DELIVERY April, 2016.
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
1 BNL LHC Hi-Lumi QXF Vertical Test Facility Status Update M. Anerella, H. Hocker, P. Joshi, P. Kovach, A. Marone March 28, 2016.
CMTF Cryogenics (status and plans) SRF program and AD/Cryogenics work presented by Arkadiy Klebaner May 21, 2013.
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
Shrikant_Pattalwar ICEC 26, March 7-11, 2016, Delhi 1 Horizontal Tests in a Vertical Cryostat Shrikant Pattalwar STFC Daresbury Laboratory UK.
Status of Vertical Test Stand at RRCAT P Shrivastava, P Mohania,D.Baxy, Vikas Rajput S C Joshi, S Raghavendra,S K Suhane RRCAT, Indore November 26, 2012.
WP : HIGH-BETA CAVITY DELIVERY A Wheelhouse ASTeC, STFC Daresbury Laboratory ESS SRF Elliptical Cavities Kick-Off Meeting CEA Saclay 23 rd June 2015.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Developing the Collaboration P McIntosh STFC Daresbury Laboratory.
WP : High-Beta Cavity Delivery
Extra / Discussion Slides. 2 1.Helium Top Fill Port Add extra CF/ISO flange as collar so that the weld-region is not disturbed 2.Helium bottom FillCF.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
Collaborating for Quality through the Project Quality Plan Matthew Conlon ESS ACCSYS QA/QC Quality Learning & Planning.
WP High Beta Cavities Delivery
Cryomodule test stand at ESS site
High-Beta cavity STATUS at DAREsbury laboratory
FRIB Cryogenic Support
at STFC Daresbury laboratory
WP-46 XFEL 3rd harmonic system XFEL Project Progress Report (1-2010)
Uppsala Commitment to ESS and FREIA Planning
Progress and Issues with VTS Upgrade
Evolving an ILC focused SCRF Facility from the XFEL Infrastructure
MICE CM31 Schedule summary
ESS RF Development at Uppsala University
UK RFD Pre-Series cryomodule
Horizontal Tests in a Vertical Cryostat
IHEP Cryomodule Status
Electron Beam Systems ETC and Methodology
Daresbury ESS In-Kind Contributions
ESS High Beta Cavities Quality Assurance and Control - Learning and Planning Workshops, CEA Saclay, 30 June - 1 July 2016 Mark Pendleton STFC, Daresbury.
CDS-EL IRR Closeout 28 March 2019 J.G. Weisend II, Chairman.
SuRf Lab: (STFC) VTF Infrastructure and Process
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Presentation transcript:

WP : HIGH-BETA CAVITY DELIVERY A Wheelhouse ASTeC, STFC Daresbury Laboratory ESS SRF Elliptical Cavities Kick-Off Meeting CEA Saclay 15 th December 2015

Outline Delivery Schedule –Project plan –Risk Register –Progress Infrastructure –Cleanroom –Shielding –Cryogenic Plant –Cryogenic System –RF System Quality Assurance Summary

Outline Delivery Schedule –Project plan –Risk Register –Progress Infrastructure –Cleanroom –Shielding –Cryogenic Plant –Cryogenic System –RF System Quality Assurance Summary

Original Project Delivery

Revised Project Delivery

MilestoneDescriptionDate 1Infrastructure preparation start4/5/15 2Infrastructure preparation finish13/3/17 3Niobium procurement start29/8/16 4Niobium procurement finish16/7/18 5Cavity testing procedure training start4/1/16 6Cavity testing procedure training finish26/2/18 7Cavity procurement start18/8/17* 8Cavity procurement finish6/3/20 9Cavity testing start3/8/18 10Cavity testing finish25/11/20 11Cavity shipment start3/10/18 12Cavity shipment finish4/12/20 HBCM Assembly at CEA start5/4/19 HBCM Assembly at CEA finish11/11/21 Provisional Milestones

* Driven by H-ECCTD qualification at CEA MilestoneDescriptionDate 1Infrastructure preparation start3/8/15 2Infrastructure preparation finish18/8/17 3Niobium procurement start20/6/16 4Niobium procurement finish16/7/18 5Cavity testing procedure training start4/1/16 6Cavity testing procedure training finish26/2/18 7Cavity procurement start18/8/17* 8Cavity procurement finish6/3/20 9Cavity testing start3/8/18 10Cavity testing finish25/11/20 11Cavity shipment start3/10/18 12Cavity shipment finish4/12/20 HBCM Assembly at CEA start5/4/19 HBCM Assembly at CEA finish11/11/21

Risk Register RiskCurrent ControlsAdditional Controls Required HOM managementFull understanding of requirements to be gained from CEA Saclay Lessons to be learnt from testing of medium-β cavity by INFN Cavity fabrication process to be defined and specified Vendor qualification to be performed Procurement timescalesDedicated resource supplied by SBS Tight controlled management of suppliers −Monthly reports Assess the need to bring forward the procurement of the Nb and cavities Conflict of resources with other ASTeC and TD projects Dedicated team for the production and qualification of cavities Personnel to be prioritised for the project Regular monitoring and reporting of project progress to ensure any required remedial action with regards to resource can be actioned by ASTeC and TD management. Interviews to be held as early as possible Project funding timescales – Major procurements on hold until commitment provided by BIS Interim funding to be provided by STFC Procurement to be commenced as early as possible

Progress STFC ESS Project Board approval granted for the programme – July 2015 Programme of work formally started 3 rd August 2015 Confirmation from BIS that George Osborne has signed off the ESS business case (2 nd December 2015) –Release of the funds now needs BIS to write a letter to STFC  Authority to proceed with major procurements has been agreed by STFC ESS Project Office Infrastructure designs and procurement being progressed Recruitment of ESS project staff progressing –Cryogenic engineer appointed – Starts 1 st Feb 2016 –Interviews held for other positions – Offers are being made Technical annex has been written and reviewed by ESS –New revision to be progressed –Able to sign TA from a technical point –To be signed by the STFC ESS project office once the IKC has been agreed

Outline Delivery Schedule –Project plan –Risk Register –Progress Infrastructure –Cleanroom –Shielding –Cryogenic Plant –Cryogenic System –RF System Quality Assurance Summary

SRF Hall Thin Film Lab Crab Lab Offices upstairs Cavity Goods-In & Out downstairs He Compressor House Cleanroom VTF Cryo-plant Full crane coverage 20m 55m

SRF Hall – Cleanroom Layout Thin Film Lab Crab Lab Offices upstairs Cavity Goods-In & Out downstairs He Compressor House Cleanroom VTF Cryo-plant BCP not included in ESS scope

Shielding Outlined radiation assessment has been performed More detailed assessment is to be undertaken To date the concrete thickness is defined – 1.8 m Shielding design is still being finalised Procurement through central services

Shielding Outlined radiation assessment has been performed More detailed assessment is to be undertaken To date the concrete thickness is defined – 1.8 m Shielding design is still being finalised Procurement through central services

Cryogenic Plant Cryogenics plant will consist of: –He Liquefier (100 l/h) –5000 l LHe Dewar –Helium Recovery System (10g/s) –Gas Storage Tender for Cryogenics Plant now live. 3 Companies expected to tender and have had pre tender visits. –Linde Kryotechnik –Air Liquide Advance Technologies –Vorbuchner Cryogenics & Applications Linde Kryotechnik Air Liquide Advance Technologies

Cryostat options have been assessed A horizontal test design is being progressed Cryostat is sufficiently large to accommodate the cavities horizontally or vertically Aim to test 3 cavities in the cryostat Plan to use the cavities own helium vessel to cool it: Sufficient condition to enable the cavity to be cooled to 2K Easily achieved by filling LHe in its own vessel (with a volume of ~ only 50 l) Horizontal Tests in a Cryostat Cryostat Proposed Design

Cryogenic Requirements: LHe requirement of ~1500 l Gas handling capacity < 2 g/S Ancillaries (2K Hex, 2K pump, distribution pipes, valves, safety devices, etc.) −Significantly simplified −Lower cost Design reviewed at TTC meeting −Feedback provided Procurement of components has commenced Horizontal Tests in a Cryostat Cryostat Proposed Design

Horizontal tests  Performance is near final configuration  Automatic leak checks on He vessel  Higher confidence in performance  Reduced test duration (quick cool- down/warm up)  Lower operational hazards (due to lower gas flow/less quantity of LHe)  75% saving on LHe and gas storage Risks/Issues Additional assembly steps Additional leak checks during assembly  Need to understand the cryo load during F/E or multipactor  Need careful QA steps Horizontal Tests in a Cryostat Cryostat Proposed Design

19 1.Helium Top Fill Port Add extra CF/ISO flange as collar so that the weld-region is not disturbed 2.Helium bottom FillCF to Flexible pipe 3.Beam Pipe VacuumCoupler Port(ISO flange via all metal angle valve) 4.RF input couplerBeam pipe side flange-2 5.RF pick upBeam pipe side flange-2 5a (OR) Pick up point 5b 6.Mounts for T-sensors? Cu mounts to bolt 4 Cernox on each cavity 7.Film Heater50 W Items 3,4 and 5 factory mounted on the cavity Cavity transported in Vacuum or in N2 at what pressure? a 5b Modification 6 7 Cavity Interfaces For discussion after lunch:-

RF System Existing VTF test facility is installed in the Electron Hall (old SRS Outer Hall) Capable of performing high gradient validation tests on 1.3 GHz Tesla cavities  Needs to be upgraded to enable testing at 704 MHz System has been defined −Robust and versatile system −Low risk as it is an already operational system Procurement of components being progressed RF amplifier is being sourced −Need to understand the RF power requirements for F/E or m/p conditions  250W or 500W? Courtesy of Tom Powers (Jlab) Low level block diagram

Outline Delivery Schedule –Project plan –Risk Register Infrastructure –Cleanroom –Shielding –Cryogenic Plant –Cryogenic System –RF System Quality Assurance Summary

Quality Assurance Industrial: Nb material Company – Provision documentation STFC – Monitoring of documentation - Approval, Inspection Industrial: Cavity fabrication Company – Provision documentation STFC – Monitoring of documentation (with factory visits) - Approval, Inspection STFC: Cavity Testing STFC − Provision of cavity documentation and test data ESS − Monitoring of documentation (with factory visits) - Approval, Inspection, Inspection CEA Saclay − Monitoring of documentation (with factory visits) - Approval, Inspection, Inspection

Quality Assurance Data management (For discussions after lunch) –Need a better understanding of what parameters need to be recorded  What data has been collected so far on the prototype cavities tested to date? –Need to understand / agree on how the data is to be presented  Need to define the architecture

Outline Delivery Schedule –Project plan –Risk Register Infrastructure –Cleanroom –Shielding –Cryogenic Plant –Cryogenic System –RF System Quality Assurance Summary

Next Steps Finalise all the designs for the infrastructure and complete all the procurements Continue on-going discussions with potential suppliers –Defining requirements – on-going Commence the tender process for the Nb material –The final material requirements and specification will need to be understood Finalise Technical Annex –Technical sign off –STFC ESS Project Office sign off

Summary Programme of work has commenced Infrastructure requirements are being defined and agreed Infrastructure procurement is being progressed Recruitment of ESS production team progressing well UK funding agreed - awaiting final BIS sign off Technical Annex progressing