Brenna Flaugher Sept. 24 th Lehman Review1 Run IIB Silicon Upgrade: Cost and Schedule Lehman Review Sept. 24, 2002 Brenna Flaugher Run IIB Silicon Project.

Slides:



Advertisements
Similar presentations
US CMS DOE/NSF Review: May 8-10, US CMS Cost & Schedule Mark Reichanadter US CMS Project Engineer DOE/NSF Review 8 May 2001.
Advertisements

L. Greiner 1HFT PXL LBNL F2F – March 14, 2012 STAR HFT The STAR-PXL sensor and electronics Progress report for F2F.
3 Oct Cost and Schedule Update Craig Ogilvie, Iowa State University Analysis of system risks Update schedule  Critical path.
Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 1 DOE/NSF Review of the Dark Energy Survey (DES) Project SC 6/7 Cost, Schedule.
US CMS Silicon Tracker – PAC Meeting – FNAL - Nov 3, Incandela 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Joe Incandela Fermilab Level.
1 SOFTWARE PRODUCTION. 2 DEVELOPMENT Product Creation Means: Methods & Heuristics Measure of Success: Quality f(Fitness of Use) MANAGEMENT Efficient &
Brenna Flaugher Oct. 31 th CDF Meeting1 RunIIb Silicon Project Successful Lehman Review Sept Workshop at LBL 10/23-10/25: Wednesday-Thursday  hybrids.
LSU 10/09/2007Project Schedule1 The Project Schedule Project Management Unit #4.
RF Cavity / Coupling Coil Module
W. Freeman, D0 PMG 25-Feb-03 1 Run IIb Schedule Status u Schedule Status u Update on near-term equipment expenditures u Budgeting Update u Summary.
March 20, 2001M. Garcia-Sciveres - US ATLAS DOE/NSF Review1 M. Garcia-Sciveres LBNL & Module Assembly & Module Assembly WBS Hybrids Hybrids WBS.
Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.
Linac Marx Modulator Update Trevor Butler 10/29/2014.
Common PDR Problems ACES Presentation T. Gregory Guzik March 6, 2003.
NEDM Construction Project Cost & Schedule Philosophy Vince Cianciolo, ORNL Physics Division Internal Cost & Schedule Review 02/11/2005.
Project Tracking. Questions... Why should we track a project that is underway? What aspects of a project need tracking?
Soft Tech Development Inc. 1 Software Project Tracking A CMM Level 2 Key Process Area Soft Tech Development Inc.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Martin Fallier Director, Conventional Facilities Conventional Facilities Value and Risk Management May 8, 2008.
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
Project management Lecture 10. Topics covered Management activities Project planning Project scheduling Risk management.
DOE/NSF Review of the U.S. ATLAS Construction Project June 3-4, 2002 WBS 1.1 Silicon Subsystem Abe Seiden UC Santa Cruz.
Slide 1 6-Nov-98PHOBOS Review: Cost & Schedule Cost & Schedule S. Steadman, MIT PHOBOS Cost & Schedule Review Technical Advisory Committee BNL November.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Silicon RunIIb Workshop, Dec , A. Bean, M. Demarteau Slide 1 Workshop  Workshop is to “Move beyond the Technical Design Proposal”  Many.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
TOF Project Construction Project Plan
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
Muon trigger upgrades, missing since not aimed towards DOE funding PHENIX upgrades: view presented to DOE R&D $3.5M Construction $16.6M Au-Au p-p 200 Si-Si.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
DOE Rev of Run IIb Sep 24-26, Detector Production WBS James Fast Fermilab.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
1 W-band Module Production and Other Fermilab Contributions Proposed Significant Partnership in QUIET-II to the Fermilab PAC in November 2009 Modest Fermilab.
ATLAS PIXEL SYSTEM OVERVIEW M. Gilchriese Lawrence Berkeley National Laboratory March 11, 1999.
David Lee, FVTX Review Nov Cost and Schedule WBS 1.0 David M. Lee Los Alamos National Lab Deputy Project Leader.
Director’s Review 5/5/03 Spalding DRAFT RLS 1 Project Planning  Documentation to DOE June 1  DOE Review ~July 22 Documents Summary Project Overview,
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
Tevatron II: the world’s highest energy collider What’s new?  Data will be collected from 5 to 15 fb -1 at  s=1.96 TeV  Instantaneous luminosity will.
UCSC August 12, 2008 U.S. Upgrade R&D Meeting: Strip Detector  Seiden.
CDF Japan Meeting, Dec 13-14, Run2b Silicon Detector - Overview K. Hara U of Tsukuba Project Status Sensor Prototype: Delivery Testing at U Tsukuba.
Rev of Run IIb, Nov 4-8, 2002, A. Bean 1 Silicon Management  Organization and Management  Schedule  Resources  Conclusions Alice Bean Univ. of Kansas.
DoE Review June 6, 2000 Cost Estimate  New Cost Estimate u Manpower Costs (Op. SWF) u Equipment Costs (Eq. M&S) u Contingency  Conclusions Mike Tuts.
Proton Driver Resources & Schedule (R&D Plan) Rich Stanek May 10, 2005.
PHENIX Vertex Detector with Conventional Strip Sensors Abhay Deshpande Stony Brook University.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
Tom Egebo PPPL Review of the NSTX TF Coil Repair Effort September 3 - 4, 2003 Cost & Schedule to Completion Supported by Columbia U Comp-X General Atomics.
DZero Run IIb PMG December 10, Agenda Run IIb D-Zero PMG December 10, 2002  ESAAB news (Lab, Project, DOE)  Project status, overview (Kotcher)
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
Run2b Silicon Detector Design goals of Run2b Si system Stave design Silicon sensors Schedule K. Hara (U. Tsukuba)
Brenna Flaugher, PMG, April 6, 2007 DECam Funding Need Profile (Dec 06) (then yr $, Overhead included) This gave a technically driven schedule resulting.
Strykowsky 1Office of Science Review August 15, 2007 Office of Science Project Review NCSX August 15-17, 2007 Cost and Schedule Ron Strykowsky.
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
Proton Plan PMG 7/27/06 J. Sims 1 Proton Plan Cost and Schedule Report Jeff Sims.
1 FVTX Quarterly/Monthly Report July 2008 Melynda Brooks, Dave Lee.
VELO Replacement Girish Patel University of Liverpool.
MUSE NSF Review March 24, MUSE Project Management Ronald Ransome Rutgers The State University of New Jersey For the MUSE Collaboration.
Lukens - 1 Contingency Reduction Review – 27 May 2005 The Run IIb CDF Detector Project Contingency Reduction Discussion Patrick T. Lukens Fermilab 27 May.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
Head, Office of Project Management Oversight (OPMO)
Final CALICE OsC meeting: Status and summary of project
External Independent Review (EIR)
SVT – SuperB Workshop – Frascati Sept. 2010
Presentation transcript:

Brenna Flaugher Sept. 24 th Lehman Review1 Run IIB Silicon Upgrade: Cost and Schedule Lehman Review Sept. 24, 2002 Brenna Flaugher Run IIB Silicon Project Co-leader Fermilab

Brenna Flaugher Sept. 24 th Lehman Review2 Outline  Project Organization  Cost  Schedule  Labor  Equipment Resources  Risk Analysis  Conclusions

Brenna Flaugher Sept. 24 th Lehman Review3 Silicon project organization Silicon project divides into 4 main Level 3 tasks  Level 3 managers are in place  Come from Universities and Fermilab  Includes physicists and engineering leadership  All have significant experience from Run IIa construction Run IIb Silicon Project N. Bacchetta B. Flaugher K. Hara (Assoc.) DAQ (1.1.2) P. Merkel S. Zimmermann Sensors (1.1.3) K. Hara Cooling (1.1.4) Support (1.1.6) K. Tollefson, S. Moccia Modules and Staves (1.1.5) G. Derylo

Brenna Flaugher Sept. 24 th Lehman Review4 Cost Basis of Estimate Costs (M&S and Labor) were derived in consultation with Run IIa project mechanical and electrical engineers BOE notebooks contain: quotations and drawings which were used to estimate the costs. Contingency is assigned at the task level  Most tasks assigned 50% on M&S and Labor Specific exceptions:  Cost based on quotations: 30% contingency –sensors –power supplies  A few high uncertainty items: 100% contingency –SVX4 chip layout cost estimates –L0 analogue cable production Contingency on Silicon Total Cost (M&S, Labor, G&A) is 50% Contingency money is treated as a global pool by Run IIb project manager and is not included in the plots in this talk.

Brenna Flaugher Sept. 24 th Lehman Review5 Silicon Project Costs Costs are in AY$ and include overhead. Contingency is not shown Total (M$) Grand Total

Brenna Flaugher Sept. 24 th Lehman Review6 Silicon M&S Cost breakdown Costs are in AY$ Overhead not included. Contingency not included Total M&S (M$): Total

Brenna Flaugher Sept. 24 th Lehman Review7 Silicon Labor Cost Breakdown Costs are in AY$ Overhead not included Contingency not included Total Labor (M$): Total

Brenna Flaugher Sept. 24 th Lehman Review8 Schedule and Milestones The Base Schedule – No Contingency  The schedule is constructed based on how long we think it will take to perform the tasks.  has ~100 low level milestones scattered over the project  End date is 5/20/05  used to aggressively manage the project. Level 2 Milestones (includes 30 wks total contingency)  Subset of low level milestones but dates include contingency  17 Level 2 milestones, ~1/quarter  Reported to Directorate and DOE project manager  End date with contingency is 12/23/05  Use of the contingency will be managed within the project, Fermilab and DOE project manager via change orders (similar to money contingency) Level 1 Milestones (additional 47 weeks contingency)

Brenna Flaugher Sept. 24 th Lehman Review9 Contingency and Milestones

Brenna Flaugher Sept. 24 th Lehman Review10 Schedule: Critical Path Critical Path Level 3 Milestones (*Level 3 = Level 2 without the contingency) Schedule is driven by production and testing of outer layer stave components: Hybrids, Bus Cable, Mini-Portcard

Brenna Flaugher Sept. 24 th Lehman Review11 Status of tasks in progress We have prototype parts and are just building and testing prototype modules - On track for 1 st prototype stave milestone 10/15/02 MPC fabrication is delayed, but we developed a workaround

Brenna Flaugher Sept. 24 th Lehman Review12 Critical Path Summary Schedule Each Round has all stave components: hybrids, bus cables, MPC Before each Round is complete we will hold a workshop/signoff meeting to formally review all aspects of stave functionality. Efficient procurement is essential – dedicated person for tracking procurement Will run a report each month listing procurements in next 3 months Get paperwork started through system early

Brenna Flaugher Sept. 24 th Lehman Review13 Labor Schedule based on what can be done in a realistic days work To convert to FTE we apply an efficiency factor of 0.85 (vac.,sick)  221 productive days work per person per year (442 hrs/qtr) Run IIb Labor total: 197 K hours Technical personnel: 89 K hours Physicists: 108 K hours Note contingency Labor is not inc. Run IIa Techs (no eng.) used: 98 K hrs for L00, SVXII and ISL Run IIb Tech. (no eng.) 63 Khrs for L00, SVXII replacement Note ISL is not being rebuilt

Brenna Flaugher Sept. 24 th Lehman Review14 Reported Effort on CDF Run IIb Project Cobra will be used to track effort on project in future. Now it is tracked “by hand” Reported Effort is growing as expected and is in good agreement with scheduled effort FY02 Reported Effort

Brenna Flaugher Sept. 24 th Lehman Review15 Engineering and associated support #1#2Prepro Production Final A. Labor Cont. not included Total hours: ElecTech: 11.5k ElecEng: 7.4k Designer: 11.7k MechEng: 18.5k

Brenna Flaugher Sept. 24 th Lehman Review16 SiDet Technical Staff #1 #2 Prepro Production Final A. Cont. not included Total Hours: Cmm prog.: 4.5k Wirebonder: 4.5k ElecTechSF: 1.5k MechTech : 29k

Brenna Flaugher Sept. 24 th Lehman Review17 Resources: Large Equipment Module Production – 8 modules/day  2 G&L CMMs (Lab D): 4 Modules/day/CMM  Wirebonding – use 1.3 machines (have one 8090 and one 1478) –automatic 8090 bonder for data lines (Si-Si, Si-Pa, Pa-Hybrid) 100% –semiauto 1478 bonder for bonding hybrid to test card Stave Production – 1.3 staves/day  2 G&L CMMs (Lab D, Lab C): capacity for 2 staves/day  Wirebonding – use 0.5 of the 1478 –for hybrid-bus cable, MiniPC to bus cable Barrel Production  2 B&S 3m CMMs in Lab C Layer 0 – 1.5m B&S in Lab C These CMMs and Wirebonders already exist at SiDet and are dedicated to CDF for Run IIb production

Brenna Flaugher Sept. 24 th Lehman Review18 Risk Assessment Risk analysis performed by Project manager for CDF Run IIa Silicon project (Jeff Spalding)  ~ independent review of cost and schedule risk Risk assessment document lists risks associated with Level 4 summary tasks, more detailed analysis for critical tasks Conclusion: Risk covered by Mitigation already in schedule  Cost risk mitigated by attaching contingency to each task –Total cost contingency ~50% (M&S + Labor)  Schedule risk mitigated by including contingency lag time on major milestones. This contingency time will be managed with change orders similar to cost contingency. –Total Schedule contingency = 30 weeks at Level 2  Technical Risk mitigated by: –extensive testing time –2 prototype rounds + preproduction before production of all stave components

Brenna Flaugher Sept. 24 th Lehman Review19 Conclusions Run IIb silicon project is based on experience with Run IIa, Run Ia and Ib silicon detectors at CDF. Critical path is dominated by production and testing of outer layer staves Risk Assessment analysis found the Silicon project risks are adequately mitigated by cost and schedule contingency (30 weeks at Level weeks at Level 1). Total Silicon Project Costs Costs are in AY$ Overhead is explicitly included Contingency is not included. Contingency = 7.2 M$ Grand Total = 21.6 M$

Brenna Flaugher Sept. 24 th Lehman Review20 Costs: AY$ and 2002 $ Total Project costs in 2002 $ without SWF escalation Total project costs in AY$ with SWF escalation Contingency = 6.6 M$ Grand Total = 20.2 M$ Contingency = 7.2 M$ Grand Total = 21.6 M$

Brenna Flaugher Sept. 24 th Lehman Review21 Costs: AY$ and 2002 $ M&S costs in 2002 $ M&S costs in AY$

Brenna Flaugher Sept. 24 th Lehman Review22 Costs: AY$ and 2002 $ Labor costs in 2002 $ without SWF escalation Labor costs in AY$ with SWF escalation