1 Allocating Resources to the Project Expediting a Project Fast-Tracking a Project Resource Loading Allocating Scare Resources.

Slides:



Advertisements
Similar presentations
6-1 Goldratt’s Critical Chain  In 1997, Goldratt introduced the Critical Chain Project Management (CCPM) methodology to apply the theory of constraints.
Advertisements

MGMT 483 – Week 11.  The issues involved in developing a project plan and schedule in the face of constrained resources (people or facilities)  Critical.
Defining activities – Activity list containing activity name, identifier, attributes, and brief description Sequencing activities – determining the dependencies.
Critical Path and Gantt
Critical Chain Project Management
Chapter 6 Allocating Resources to the Project
Critical Chain Project Scheduling. Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall11-2 Theory of Constraints (ToC) A constraint limits.
Critical Chain Project Scheduling
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Day 21.
1 Operations Management Lesson 5 Project Management.
Copyright © 2014 McGraw-Hill Higher Education. All rights reserved. CHAPTER 15 Supplement Advanced Methods for Project Scheduling McGraw-Hill/Irwin.
Project Management Workshop By Jonathan W. Powell, CGFM, PMP.
Projmgmt-1/18 DePaul University Evaluating Schedule In MicroSoft Project Instructor: David A. Lash.
9-1 Resource Allocation Some definitions Resource allocation, loading, leveling Expediting and crashing projects Goldratt’s “Critical Chain”
Reducing Project Duration: Project Crashing
Importance of Project Schedules
Project Management Lecture Resource Analysis. Introduction Project planning Gantt chart and WBS Project planning Network analysis I Project planning Network.
Project Management: A Managerial Approach
Applied Software Project Management Andrew Stellman & Jennifer Greene Applied Software Project Management Applied Software.
Class 28: Chapter 16: Project Management Class 28 Agenda –Collect Player Diary 2 and Conduct Player Audit No ed diaries – 5 PM Deadline –Discuss Grade.
OPERATIONS MANAGEMENT for MBAs Second Edition
Project Management in Practice Fourth Edition
Allocating Resources to the Project
Copyright 2009 John Wiley & Sons, Inc. Chapter 9 Resource Allocation.
Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation.
MANAGING PROJECT RESOURCES
Allocating Resources to the Project
Methods and Tools of Success Driven Project Management
© 2006 John Wiley and Sons, Inc. Project Management: A Managerial Approach Chapter 9 – Resource Allocation.
Real-World Project Management Chapter 13. Characteristics of Project Management Unique one-time focus –Difficulties arise from originality Subject to.
Appendix A Project Management: Process, Techniques, and Tools.
Introduction to the Theory of Constraints (TOC) & Critical Chain Project Management (CCPM) Major Mark McNabb.
Midterm Review SE503 Advanced Project Management.
When Things Go Right Cornell’s PeopleSoft 8.9 Upgrade Lisa Stensland Manager, CIT Project Management Office May 15, 2008.
Critical Chain From “Theory of Constraints” Developed by Elihu Goldratt in 1984 Goldratt – Many of his key ideas were first explained via “business novels”
Quick Recap.
Time-Cost Tradeoffs Time-Cost Tradeoff Example Time-Cost Tradeoff Example (cont’d) Project Duration (weeks)Critical Path(s)Task(s) Reduced Total Direct.
File:CCPGS05 CC present Page: 1 ETXPGS
IS 556 Enterprise Project Management 1IS 556 -Spring 2008 Lecture 2 Apr 7, 2008 //48.
Network Planning Techniques Program Evaluation & Review Technique (PERT): Developed to manage the Polaris missile project Many tasks pushed the boundaries.
MBP1123 | Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar L8 – Project Time Management - IV
VMcG 2/11/02 Critical Chain as an Extension to CPM Vincent McGevna, PMP February 11, 2002
Chapter 6: Project Time Management Information Technology Project Management, Fourth Edition Using Critical Chain Scheduling, PERT, and MS Project 2003.
Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 2nd Edition © Wiley 2005 PowerPoint Presentation by R.B. Clough.
Introducing Project Management Update December 2011.
MEM 612 Project Management Chapter 6 Allocating Resources to the Project.
Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Patterson University Copyright 2007 John Wiley & Sons, Inc.5-1.
Project Time Management
Critical Chain Method These sides and note were prepared using 1. The book Streamlined: Building Lean Supply Chain Using the Theory of Constraints. Srinivasan.
Critical Chain A Novel by Eliyahu Goldratt Copyright 1997.
McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects.
Chapter 9 Resource Allocation © 2012 John Wiley & Sons Inc.
SE503 Advanced Project Management Dr. Ahmed Sameh, Ph.D. Professor, CS & IS Critical Chain Project Management.
1 Critical Chain Project Management  A modern approach to dealing with uncertainty in project management (an alternative to PERT)  Developed by Goldratt.
Orlando Critical Chain as an Extension to C P M Orlando A. Moreno, PMP February,
Project Planning & Scheduling What is a “project”? Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time Networks.
Supply chain Dynamics in Indian Apparel Export Manufacturing Submitted by: Shikha Aggarwal Vikas Punia.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
Chapter 16 – Project Management
Introduction to the Theory of Constraints (TOC) & Critical Chain Project Management (CCPM) Major Mark McNabb.
The Project Schedule and Budget
Class 27: Project Management Part II
Project Planning & Scheduling
Information Technology Project Management – Fifth Edition
assemble-to-order (ATO) A system that produces standard modules to be
ENGINEERING MANAGEMENT (GE 404)
Chapter 9 Resource Allocation © 2012 John Wiley & Sons Inc.
Reducing Project Duration
Presentation transcript:

1 Allocating Resources to the Project Expediting a Project Fast-Tracking a Project Resource Loading Allocating Scare Resources

2 Introduction Projects Compete With One Another for Resources –resources that are not consumed –resources that are consumed Goal of Resource Allocation is to Optimise Use of Limited Supply Requires making trade-offs –time constrained –resource constrained

3 EXPEDITING A PROJECT The Critical Path Method Probabilistic Activity Durations Fast-Tracking a Project

4 The Critical Path Method Normal Duration Estimates Normal Costs Crash Duration Estimates Crash Costs Crash Cost Per Day

5 Probabilistic Activity Durations Three time estimates made for both normal resource loading and crash resource loading Variance of normal activity may be different than variance of crash time

6 Fast-Tracking a Project Used Primarily in Construction Industry Building phase started before design and planning phases completed (Scottish Parliament) Particularly appropriate when large proportion of work is routine

7 Resource Loading Amount of specific resources that are scheduled for use on specific activities or projects at specific times. Usually a list or table.

8 Use of Software Begin with Pert/CPM Schedule Activities examined period by period and resource by resource In cases where demand for resource exceeds supply, tasks considered one by one and resources assigned to these tasks based on priority rules

9 Some Priority Rules As soon as possible As late as possible Shortest task duration first Minimum slack first Most critical followers Most successor Most resources first

10 Resource Loading/Leveling and Uncertainty What about –Workers getting sick? –Task not ready when worker is ready? –Change orders?

11 Pseudo activities Used to link several project together Have duration but do not require any resources This approach allows a set of projects to be dealt with as though it were a single project –use of MSP’s resource loading and leveling charts and tables

12 Bottle Necks Identify the constraint Exploit the constraint Subordinate everything else Elevate the constraint Go back to step 1

13 Goldratt’s Critical Chain What is it? Tackles the inherent uncertainty in managing projects Systems approach

14 Goldratt’s Critical Chain Similar issues that trouble people about working on projects regardless of type of project –unrealistic due dates –too many changes –resources and data not available –unrealistic budget These issues/problems related to need to make trade-offs To what extent are these problems caused by human decisions and practices?

15 Observations Average Completion Times Implications of Assuming Known Activity Times Worker Time Estimates Impact of Inflated Time Estimates Student Syndrome

16 Common Chain of Events Underestimate time needed to complete project Project team members inflate time estimates Work fills available time Safety time misused Misused safety time results in missed deadlines

17 Common Chain of Events concluded Poor multitasking increases task durations Uneven demand on resources also results due to poor multitasking More projects undertaken to ensure all resources fully utilized More projects further increases poor multi tasking

18 Reversing the Cycle Reduce number of projects assigned to each individual Schedule start of new projects based on availability of bottleneck resources Reduce amount of safety time added to individual tasks and then add some fraction back as project buffer –activity durations set so that there is a high probability the task will not be finished on time

19 The Critical Chain Longest chain of consecutively dependent events –considers both precedence relationships and resource dependencies Project Buffer Feeding Buffer

20 Critical Chain Rules 1. Projects should not be started ASAP 2. Tasks and resources should not be precisely scheduled during planning 3. Adding explicit buffers into projects makes them run faster

21 Buffer Management Taking the appropriate action No action needs to be taken, consumption of the buffer is expected Identify the tasks consuming the buffer, develop a recovery plan Implement recovery plan Use information on task performance for future improvement activities

22 Why not start projects ASAP? All three projects started ASAP Constant resource shuffling Priorities not synchronised All projects are delayed Start dates are staggered Resources stay focused Tighter synchronisation All projects finish faster More projects can be done

23 Why not schedule precisely? Schedules set in planning Uncertainties are unavoidable Wanting to be reliable, people add safeties into estimates Safeties get wasted in execution Schedules set in Execution Estimates are used only to plan projects Task schedules determined in execution, when tasks are closer to being started

24 How safety or contingency time is wasted Task dependency – Gains are wasted and delays are passed on Student Syndrome / Cherry Picking – Starting work is delayed Parkinson’s Law – “Work expands to fill the time available” Multi Tasking – A resource has to divide its time between two or more tasks

25 Benefits PROJECTS: coming in on-time completing within budget completing without cutting scope reduced project lead-times Improved efficiency

26 A resource allocation example

27 Often estimates of the time taken are quite inaccurate

28 Plan with Resource Allocation

29 Revised Plan with Resource Allocation

30 Plan with Levelled Resources and Warm Toast