STATE ROAD 100 CRA Update to City Council November 13, 2012 Workshop
BACKGROUND State Road 100 Corridor Community Redevelopment Agency
Prosperity 2021
Background State Road 100 Corridor Community Redevelopment Agency (SR100 CRA) Established in 2004 City Council Serves as SR100 CRA Board (separate entity) 30 Year Time Horizon Master Plan Updated in 2008 (Lists Eligible Projects/Programs) Funded through Tax Increment Property Values Frozen in 2004 for City and County Increase in Value = Tax Increment Tax Increment Deposited in SR100 CRA Trust Fund Projects can be Financed based on Dedicated Funds
SR100 CRA Area
Background SR100 CRA Purpose Reduce or Eliminate Blight Whispering Pines Midway Increase Tax Base and Encourage Public/Private Investment Establish City’s Downtown or Urban Core Establish Another Commercial Corridor (In Addition to PC Parkway)
Background Completed Projects Master Plan Updated Central Park Improvements Land Acquisitions in Target Areas (74% of Lots) I-95 / State Road 100 Gateway Features Bulldog Drive Project Development and Engineering Report
Private Sector Investment Target Center Red Lobster/ Olive Garden Publix Shopping Center Epic Theatres Pinnacles Professional Park City Centre Hilton Garden Inn Panera Bread Imagine School Medical Offices Banks, Banks, & More Banks
FY2012/2013 CRA Budget
MAJOR PROJECTS State Road 100 Corridor Community Redevelopment Agency
Bulldog Drive Improvements Original Plan (October 2010) Construct Complete 4-Lane Urban Roadway (Multi-Use Path, Sidewalk, Landscaped Median, and SR100 Intersection Improvements) in One Phase Property Acquisitions of All Property Abutting Bulldog Drive Necessary School Board Interlocal Agreement for Property Most Private Property Acquired (Except One Owner) Revised Plan (September 2011) Phase Project to Meet Current Needs and Avoid Eminent Domain Reconstruct 2-Lane Roadway with Intersection Improvements at SR100 Change Traffic Circulation on SR100 and FPC Improve Stormwater Management to Minimize Flooding of FPC Pedestrian Improvements
Bulldog Drive Improvements Original Contract with WilsonMiller, Inc. Approved in October 2010 for $348,000 Based on Original Plan Design Contract for Phase 2 Change Order in Amount of $212, Necessitated by Revised Plan (Phasing of Project) Discussed with City Council in September 2011
Bulldog Drive Improvements
Refinancing Debt Issued in April 2010 Amount: $4,000,000 Payment: $365,000 per year, 15 years Interest Rate: 4.34% Refinancing Take Advantage of Low-Interest Rates Possible Saving of $28,000-$32,000 Per Year Borrow Additional Funds to Complete Construction of Bulldog Drive Improvements ($2,000,000) Adequate Coverage for Debt Payment Estimated Total Debt Payment of $530,000 - $550,000 Estimated Tax Increment for FY2013 = $1,314,581
Land Acquisition in Target Area Strategy to Reduce or Eliminate Blight Antiquated Subdivisions (No Infrastructure, Prone to Flooding) SR100 CRA Board Direction to Purchase Property at Appraised Value from Willing Sellers Pazyniak Property – Appraised Value of $146,500
Interfund Loan City provided Interfund Loans starting in 2004 to carry out SR 100 CRA Projects and Programs Outstanding Principal Balance of the Loan is $5,792,529 SR100 CRA Interest only (5%) Annual Payments of $285,751
Next Steps Next Week Change Order for Phase 2 of Design Contract Pazyniak Property Acquisition Future Debt Refinancing Bulldog Drive Construction Contract Additional Property Acquisitions