Spectrometer Solenoid Fabrication Status and Schedule RF Cavity / Coupling Coil Module Plan and Progress Steve Virostek Lawrence Berkeley National Lab.

Slides:



Advertisements
Similar presentations
MICE RF Cavities and RFCC Module Update Derun Li Lawrence Berkeley National Laboratory MICE RF Workshop Daresbury Laboratory, UK April 17, 2012 April 17,
Advertisements

MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
MICE Superconducting Solenoids: Status and Update RAL: T W Bradshaw M Courthold J Rochford M Hills D Baynham Oxford: J Cobb W Lau S Yang MICE.
Plans for 201-MHz Cavities Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory November 18, 2010.
MUTAC Review, 9 April MuCOOL and MICE Coupling Magnet Status Michael A. Green Lawrence Berkeley Laboratory Berkeley CA
RF Measurement Plan Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory January 20, 2011 MICE Video Conference Meeting.
Magnet quench during a training run Magnet electrical circuit schematic PROGRESS ON THE MODELING AND MODIFICATION OF THE MICE SUPERCONDUCTING SPECTROMETER.
UPDATE of RFCC MOUDLE Derun Li, Steve Gourlay Lawrence Berkeley National Laboratory MICE MICO Meeting December 21, 2011.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
-1- Wang, Li The 23rd MICE Collaboration Meeting to 17 HIT/CHINA WANG, Li Institute of Cryogenics and Superconductivity Technology.
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
23 October 2005MICE Meeting at RAL1 MICE Tracker Magnets, 4 K Coolers, and Magnet Coupling during a Quench Michael A. Green Lawrence Berkeley Laboratory.
Spectrometer Solenoid Report and Coupling Coil Update Michael S. Zisman MICE Operations Manager Center for Beam Physics Lawrence Berkeley National Laboratory.
Cooling Channel Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICE Collaboration.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
9 June 2006MICE CM-15 Fermilab1 Progress on the MICE Cooling Channel and Tracker Magnets since CM-14 Michael A. Green Lawrence Berkeley Laboratory.
1 The Genoa Tracker Solenoids and their Contribution toward a New Design Michael A. Green Lawrence Berkeley National Laboratory and Pasquale Fabbricatore.
Update on Be Wall Cavity Steve Virostek Lawrence Berkeley National Lab MTA RF Workshop November 15, 2010.
MICE Video Meeting, 10 Jan 081 Spectrometer Magnet Progress Michael A. Green Lawrence Berkeley Laboratory.
1S. Virostek - LBNL Spectrometer Solenoid Fabrication Update S. Virostek and M. Green are visiting vendor today for progress update Vendor expects to complete.
Spectrometer Solenoid Update Steve Virostek - LBNL MICE Video Conference #145 December 15, 2011.
Status of 201 MHz Prototype and RFCC Module Derun Li, S. Virostek, M. Zisman Center for Beam Physics Lawrence Berkeley National Laboratory In collaboration.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
1S. Virostek - LBNL Spectrometer Solenoid Fabrication Update Vendor still expecting to complete first magnet by the end of November, before X-mas more.
RFCC Module Tech Board Schedule Discussion Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 4, 2009.
MICE Spectrometer Solenoid Design and Fabrication Update Mike Green and Steve Virostek Lawrence Berkeley National Laboratory MICE Video Conference December.
12 March 2006NFMCC Meeting, IIT, Chicago1 Progress on the MICE Cooling Channel and Tracker Magnets Michael A. Green Lawrence Berkeley Laboratory.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE Collaboration Meeting #26 University of California.
MICE Magnets - Virostek 11 MICE Magnets Steve Virostek Engineering Division Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Spectrometer Solenoids and Coupling Coils Primary Activities and Risks Going Forward Spectrometer Solenoids Completion of SS#2 magnetic mapping Completion,
RF Cavity / Coupling Coil Module
Progress on the MuCool and MICE Coupling Coils * L. Wang a, X. K Liu a, F. Y. Xu a, A. B. Chen a, H. Pan a, H. Wu a, X. L. Guo a, S. X Zheng a, D. Summers.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
Office of Science 3/8/ LBNL MICE Project Status Spectrometer Solenoids, Coupling Coils and RFCC Modules Steve Gourlay MICE Project Board March.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
Status and Integration of the Spectrometer Solenoid Magnets Steve Virostek Lawrence Berkeley National Lab MICE RAL June 15, 2007.
Status of RFCC-Module Development Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MICE Collaboration Meeting at INFN-LNF, Frascati,
Magnet quench during a training run Successfully trained to peak currents and operationally tested Thermal performance requirements met 3D magnetic bore.
MICE Coupling Coil Update Steve Virostek for Allan DeMello Lawrence Berkeley National Laboratory MICO January 23, 2013 January 23, 2013.
Abstract: The Muon Ionization Cooling Experiment (MICE) is an international effort sited at Rutherford Appleton Laboratory, which will demonstrate ionization.
Spectrometer Solenoid Overview Roy Preece 31 st January 2011.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
MICE Cooling Channel Magnets: Spectrometer Solenoid Procurement RF Module Coupling Coil Proposal Steve Virostek Lawrence Berkeley National Lab NFMCC 07.
Magnet vacuum vessel w/radiation shield and cold mass in place Magnet leads (left) and the three cryocoolers on the top of the spectrometer solenoid service.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Collaboration Meeting #28 Sofia, Bulgaria.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM29 at RAL, UK February 17, 2011.
MICE RFCC Module Status Derun Li Lawrence Berkeley National Lab NFMCC-MCTF Collaboration Meeting LBNL, Berkeley, CA January 25, 2009.
MICE RF Cavities and RFCC Module Update Allan DeMello and Derun Li Lawrence Berkeley National Laboratory MICE CM32 at RAL, UK February 9, 2012 February.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab NFMCC at LBNL January 25, 2009.
MICE/MuCool Coupling Magnets to 22 ICST/HIT MICE/Muool Coupling Magnets Progress Li Wang for MICE Group Institute of Cryogenics.
22 October 2005MICE Meeting at RAL1 Tracker Solenoid Overview Michael A. Green Lawrence Berkeley Laboratory MICE Collaboration Meeting 22 October 2005.
MICE RF Coupling Coil Magnets Update Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory October 6, 2010 Sofia, Bulgaria.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
MICE/MuCool Coupling Magnets ICST/HIT Progress and Schedule for the MICE/MuCool Coupling Coil Project HIT MICE CC Project Group.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory Oxford, UK July 7, 2011 July 7, 2011.
Progress on MICE RFCC Module for the MICE Experiment * Allan DeMello, Nord Andresen, Michael Green, Derun Li, Heng Pan, Steve Virostek, Michael Zisman.
Status of MICE Coupling Coil Magnets D. Li and M. Zisman Center for Beam Physics Lawrence Berkeley National Laboratory February 16, 2011 MICE CM29-Rutherford.
MICE RFCC Module Update Steve Virostek Allan DeMello Lawrence Berkeley National Laboratory MICE CM27 at RAL, UK July 8, 2010.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
MICE Spectrometer Solenoid Recovery Review - December 3-4, Steve Virostek MICE Spectrometer Solenoid Design and Assembly.
Cooling Circuit Design Steve Virostek Lawrence Berkeley National Lab February 29, 2012 MICE Coupling Coil Cryostat Design Review Lawrence Berkeley National.
MICE CC Magnet Cryostat Design Overview Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MICE CC Cryostat Design Review LBNL, February.
201 MHz Cavity Plans Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory February 11, 2011 MAP Friday Video Conference Meeting.
MICE Coupling Coil Vacuum Vessel Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
RFCC Engineering Status and Plans Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Meeting March 6, 2012 March 6, 2012.
1 MICE Coupling Coil Cryostating and Test Steve Gourlay March 1, Office of Science.
Overview of the RFCC Module and 201-MHz Cavity Design
Spectrometer Solenoid Update
Spectrometer Solenoid Fabrication Status and Schedule
Presentation transcript:

Spectrometer Solenoid Fabrication Status and Schedule RF Cavity / Coupling Coil Module Plan and Progress Steve Virostek Lawrence Berkeley National Lab NFMCC March 18, 2008

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 2 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 MICE Cooling Channel Layout Spectrometer Solenoid 1 Spectrometer Solenoid 2

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 3 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Completion of first magnet has been delayed by a problem with cold mass support clearances A second issue regarding the poor cryocooler performance in an off line test has been resolved Currently expect fabrication of the first magnet to be complete by mid to late April Coil winding, banding, wiring and reinforcement of the 2 nd magnet is finished Completion of the second magnet to follow the first by approximately two months Overview (Spectrometer Solenoid)

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 4 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Passive Quench Protection Space Center Coil Match Coil 1 End Coil 1 Match Coil 2 Coil Cover LHe Space 490 mm 690 mm 2544 mm Coil Spacer Spectrometer Solenoid Cold Mass #1 End Coil 2 Complete

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 5 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Passive Quench Protection Space Center Coil Match Coil 1 End Coil 1 Match Coil 2 Coil Cover LHe Space 490 mm 690 mm 2544 mm Coil Spacer Spectrometer Solenoid Cold Mass #2 End Coil 2 Complete Install Soon

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 6 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Completed Cold Mass Assembly - Magnet #1 Cold mass prior to welding of support bands

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 7 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 MLI Wrapping of Cold Mass Assembly I-beam structure fabricated for step-by-step magnet assembly

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 8 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Outer Thermal Shield Shield assembled from 3/16” aluminum sheet

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 9 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 MLI Wrapped Thermal Shield

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 10 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Installation of Thermal Shield over Cold Mass

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 11 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Installation of Thermal Shield over Cold Mass Thermal shield is positioned with hoist during installation

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 12 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Installation of Thermal Shield over Cold Mass

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 13 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Vacuum Vessel and Support Stand Vacuum vessel ready for assembly with cold mass

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 14 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Inner Vacuum Vessel

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 15 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Service Tower Assembly Service tower accommodates three cryocoolers and fill/vent lines (one cryocooler sleeve assembly shown in place)

Cryocooler Experiment Purpose: Measure cooler K Confirm drop-in mode, measure heat leak Update: 1 st series of tests completed in November Results were not conclusive due to some deficiencies in the test apparatus System was modified including addition of a larger liquid He storage vessel Recent poor performance in testing due to either bad cooler, convective currents between 1 st and 2 nd stages or thermal acoustic oscillations in piping These issues were addressed, and 1.5 W cooling power at 2 nd stage confirmed

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 17 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Cryocooler Expeiment

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 18 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Magnet #2: Cold Mass Winding Assembly 2 nd magnet to follow 1 st by ~2 months

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 19 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Spectrometer Solenoid Iron Shields Design integrated with TOF shield, and all fabrication drawings are near complete Two sets of shields needed at FNAL and two sets at RAL Quote obtained from JK Mfg near FNAL; need final drawings before placing order One of two shields at FNAL may be shipped to RAL, 2 nd set fabricated in UK

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 20 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Updated Schedule Summary

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 21 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, st magnet expected to be complete in April Magnet to be tested at vendor, shipped to FNAL Completion delayed by cold mass support issue and cryocooler/condenser performance problem Coil winding, banding, reinforcement and wiring of 2 nd magnet finished Cryocooler test modified and performance verfied Magnet #2 to follow ~2 months after #1 Iron shield fabrication to start soon Summary (Spectrometer Solenoid)

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 22 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Overview (RFCC module) A bottoms-up, WBS based plan (including a cost estimate and schedule) has been developed for completion of two RFCC modules A task list of ~300 items includes: engineering, design, reviews, procurement, fabrication, assembly, testing and shipping Current plan calls for funding and/or effort from the following institutions: Lawrence Berkeley National Lab, ICST/HIT at Harbin, University of Mississippi, UC Riverside and Oxford Physics

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 23 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Funding and Schedule The early finish schedule and no contingency cost estimate results in delivery of the completed RFCC modules near the end of FY09 Currently projected funding may be sufficient to complete the project on the two year schedule Contingency and float can be provided by the use of FY10 funds and by stretching the schedule into FY10, if necessary RF cavity design and fab is on the critical path

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 24 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Preliminary Plan The detailed design of the cavities and associated subcomponents will be based on the prototype cavity design developed at LBNL and J-Lab The MuCool and MICE Coupling Coils have been designed and will be fabricated & tested at ICST LBNL engineering will coordinate the fabrication of the cavities using a combination of in-house shops, collaborator shops (U. Miss.) and outside resources (spinning, e-beam welding, etc.)

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 25 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Preliminary Plan (cont’d) Subcomponent procurements (Be windows, RF windows and couplers, vacuum system, cryocoolers, power supplies) will be specified by LBNL & purchased w/funds from various sources Coupling coils, cavities and other components will likely be integrated into RFCC modules at LBNL using in-house technical resources Module testing will take place at LBNL prior to shipping to the MICE hall at RAL

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 26 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Preliminary RFCC Module Schedule

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 27 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Engineering, Design & Technical Resources An additional FTE engineer (Alan DeMello) at LBNL has been assigned to work on the module along with M. Green & S. Virostek ICST has the engineering and technical resources needed to complete the design and fabrication of the coupling coils (with some LBNL oversight) Technical resources, machine shops & assembly facilities are currently available at LBNL

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 28 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Funding Plan Projected available funding through LBNL (FY07- FY09), U. Miss. and UC Riverside may be sufficient to cover the estimated project costs ICST is funding the manpower & a portion of the raw material costs for completion of the coupling coils (bulk of material is coming from the US) The current cost estimates do not contain contingency - additional project $ to be available in FY10 should provide adequate contingency

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 29 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Updated RFCC Module 3D CAD Model 201 MHz RF cavity Automatic tuners Cavity suspension

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 30 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Coupling Coil Update An MOU between LBNL and ICST/HIT at Harbin for the Coupling Coil Project is in place The MOU includes an addendum with milestones and funding information as well as a technical agreement containing the magnet specifications 260 km of superconductor ordered (137 km rec’d) Additional procurements are under way – first shipment of materials has been received at ICST ICST has completed the magnet final design and is ready to wind a pair of test coils

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 31 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Coupling Coil Design

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 32 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Coupling Coil Components Al coil mandrel G-10 insulation Coil Al banding Cover plate Cooling circuit Cold mass supports Cryocoolers Heat shields Vacuum chamber He collection box LHe distribution container He condenser

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 33 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Coupling Coil Analyses

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 34 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Coil Winding Tooling

MICE Spectrometer Solenoid Fabrication Update and Schedule StatusPage 35 Steve Virostek -- Lawrence Berkeley National Laboratory -- March 18, 2008 Summary (RFCC module) A detailed plan has been developed for the design and fabrication of two RFCC modules Both funding (?) and manpower required to complete the effort are available (new engineer on the LBNL) ICST has completed the Coupling Coil design and is prepared to start winding a pair of test coils Material orders and shipment to ICST of Coupling Coil components are ongoing Design & analysis of the MICE 201 MHz cavity is under way A revised beryllium window design has been developed, and quotes have been obtained from the vendor