1 Feedback on Warm Magnet Activities during LS1 J.Bauche, on behalf of the TE/MSC/MNC section With contributions from: P. Catherine, M. Dumas, P. Fessia,

Slides:



Advertisements
Similar presentations
Accelerator Complex Status P. Collier. Linac2, Booster and PS Startup on-time, according to the schedule. Only minor problems Rapidly set-up the major.
Advertisements

Long shutdown 2013: Electrical distribution activities 09/03/2012 IEFC 2012 Workshop F. Duval on Behalf of EN/EL group.
CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
Session 8 - Long Shutdown 2 Strategy and Preparation LIU Planned Activities Reference : RLIUP Oct.2013 (indico) “Work Effort in the LHC Injector Complex,
Consolidation program SPS Main Power Converters (Dipole & Quadrupole) K. Kahle / Q. King / G. Le Godec (TE-EPC) IEFC Workshop, 9 March 2012.
HLTC 15 th April 2014 EDMS: Y. Muttoni EN-MEF-INT with the contribution of P. Fessia.
Fibres & copper Cabling activities LIU meeting 27/09/2013 F Duval 27/09/2013 F Duval Cabling acxtivities LIU 1.
TE-MPE –TM, 16/05/2013, Mateusz Bednarek, TE/MPE-EE ELQA testing during and beyond LS1.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
CRYOGENICS AND POWERING
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System October 24-26, 2012 THE HIGH-VOLTAGE NETWORK OF CERN.
Status of handling studies for PSB-LIU Caterina Bertone EN-HE LIU-PSB 17/09/2015 Courtesy: A. Newborough EDMS
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
ATC / ABOC Days – Session 4 – January D. Smekens AT-MCS-MNC 1 MAGNETS FOR SPS & BEAM LINES MTTR & Spare Policy for the LHC Injectors & Exp.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
Major power converter issues for the restart of PS & SPS machines and their experimental areas in 2006 Jean-Paul BURNET for AB/PO PS&SPS days January.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
Davide Tommasini Status and prospects of the PS magnet consolidation program ATOP Days March 4 th – 6 th 2009 Status and prospects of PS magnets programs.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
12th February 2010David Mcfarlane EN-MEF-ABA1. History of Booster The accelerator was built in The Proton Synchrotron Booster is the first, in the.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Risk Analysis P. Cennini AB-ATB on behalf of the n_TOF Team  Procedure  Documents in preparation  Conclusions Second n_TOF External Panel Review, CERN,
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
The integration of 420 m detectors into the LHC
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Beam Instrumentation during LS1 Ray Veness on behalf of the BE/BI group.
IEFC Workshop 9 th March 2012 – Magnet activities in IEF during LS1 – J. Bauche 1 Magnet activities during LS1 J.Bauche, on behalf of the TE/MSC/MNC section.
EN-EL Activities for LS2 LIU, Consolidation, Maintenance, Operation Nicolas Bellegarde on behalf of EN-EL.
TE-CRG Activities D. Delikaris, TE-CRG.
LSC May 2013 Outcome of the magnets tests from the PS, Leir and transfer lines Dominique Bodart.
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 1 SPS Magnet Test Campaign and Consequences for LS1 J. Bauche*, P. Catherine,
LMC 1 (Pre Chamonix) DN200 relief valve position DN200 relief valve position On top wherever possible. Open W bellows for MLI protection. On top wherever.
High Energy Dump of the Super Proton Synchrotron at CERN – Present and Future designs A. Perillo-Marcone (EN-STI) Contributions from several colleagues.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
18/March/2008OP-days S.Mataguez / O.Hans1 Hardware Problems in the PS complex LINAC 2 BOOSTER PS AD Thanks to all that helped and provided information,
LIU Configuration Management EDMS Documentation, Layout and ECRs This presentation follows the LIU-PSB specific presentation done on 9 th October 2014.
EDMS N° V.1 TE-EPC Activities during LS1 V. Montabonnet [TE-EPC]
Warm Magnets - LS1 Feedback J. Bauche, on behalf of the TE-MSC-MNC Team.
PS - SPS Day 18-Jan-2006 PS Ring by Ray Brown.. 2.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
Electrial Safety LS2 days November 2016 AP
Magnet activities in SPS during EYETS
LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
TE-MSC activities in SPS during LS2
Ongoing consolidation of magnets
AD consolidation activities in LS2
Hollow e- lens, Cryogenic aspects
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
Renovation of the 45-year old PS magnets
the CERN Electrical network protection system
EN-CV interventions during EYETS for PS and PSB
TE-MSC activities in SPS during YETS
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
Magnet electrical and hydraulic (dis)connections for coating
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
Experimental Areas – LS2 planning
Presentation transcript:

1 Feedback on Warm Magnet Activities during LS1 J.Bauche, on behalf of the TE/MSC/MNC section With contributions from: P. Catherine, M. Dumas, P. Fessia, A. Newborough, P. Thonet, and D. Tommasini

2 Outline Magnet maintenance program in LS Review of TE/MSC/MNC activities in LS1 Foreseen Unforeseen Feedback Support from/to other groups Coordination Electrical and radiation safety Infrastructure (incl. access) Resources Summary

3 Main Conclusions LS meets well magnet maintenance program; magnet inspection dedicated period at start of LS period shall be kept Overall feedback: LS1 work well prepared, well in advance (commitment of resources already at this stage). Initiatives like IEFC workshop 03/2012 helped a lot. Excellent collaboration with other groups, good communication in technical coordination meetings Additional workload from inspection results or from external requests SMACC priority committed a lot of MNC resources. Support with external collaborations (BINP & NCBJ) helped to recover some Margin to be considered in schedules in particular for restart phase (late activities / issues found during restart tests) Prioritization of projects is of utmost importance for resource allocation Radiation aspects well addressed (e.g. TDC2 / LSS1+); few electrical safety issues: reminder of basic safety rules Safety rules and procedures demanding more and more resources

4 Spare slides from IEFC workshop 03/2012

5 Magnet baseline strategy for LS1  Memorandum addressed in October 2011: TE/MSC/MNC activities in IEF during LS1 (EDMS )  We intend to complete: Full inspection of the magnets Corrective maintenance Preventive maintenance and necessary consolidations Necessary actions in highly radioactive areas LIU activities to be done during LS1  To reserve resources for LHC splice consolidation, we will put on hold: Less urgent consolidations (SMIT quadrupoles in L2, L3 and PSB; SPS pole shims, PS busbars and PFW’s, NEA interlock cabling, etc.) Many desirable but less urgent maintenance activities Most of it could not be done during short shutdowns of the last 3 years

6 Maintenance and consolidation in IEF  Detailed inspection of magnets Removal of the magnet covers Electrical tests Audio-visual inspection in pulsed mode Thermal inspections  Machine conditions Machine closed to non-MNC personnel during power tests Power, cooling, interlocks, access operational  Support from other groups BE/OP to power the magnets and lock the accesses TE/EPC support for power converters operation  To be done in the beginning of LS1 (except zones!) In all machines Loose electrical connection

7 Maintenance and consolidation in IEF  Corrective / preventive maintenance Repair / replacement of faulty magnets Shimming in-situ or replacement of magnets with critical coil movement Refurbishment of defective magnets in workshops Cleaning of all magnet filters  Machine conditions Free access for handling and transport in the tunnel (coactivity)  Support from other groups EN/HE, TE/VSC, BE/ABP for magnet replacements  Activity spread over the whole LS1 duration, ending with the most radioactive zones In all machines Clogged filter Clogged coil

8 Maintenance and consolidation in IEF  Revise most critical auxiliary magnet cooling circuits Missed preventive maintenance Replacement of internal flexible hoses Check hoses crimping system  Activity spread over the whole LS1 duration PS Booster ONO/XNO/QSK-Type IA OSK/XSK/DVT/DHZ (Type B)

9 Maintenance and consolidation in IEF  Removal of unused magnet in beam lines 7000 and 8000 Required for the ELENA project  Machine conditions Opening the concrete roof of AD  Support from other groups EN/HE, TE/VSC AD transfer lines BHZ 8000 – 30 T BTI 8002 – 7.5 T Layout of transfer line 8000

10 Maintenance and consolidation in IEF  Refurbishment in-situ of separator magnets GPS and HRS Missed preventive maintenance  Support from other groups None if work in-situ EN/HE, TE/VSC, BE/ABP, if major refurbishment in workshop is needed  After radiation cool-down period ISOLDE GPS 70 deg. magnet HRS 60 deg. magnet HRS 90 deg. magnet

11 Maintenance and consolidation in IEF  Replacement of PFW sets on main units #55 and #75 Corrective maintenance Crimped contact resistance increase monitored recently  Support from other groups EN/HE, TE/VSC, BE/ABP  After radiation cool-down period PS ring PS main unit Typical increase of contact resistance PFW internal assembly

12 Maintenance and consolidation in IEF  Refurbishment of most critical quadrupole cooling circuits Corroded brazed hydraulic connections on several magnets Degraded internal soft hoses to be replaced  Support from other groups EN/HE, TE/VSC, BE/ABP for replacement of some of the magnets TT2 transfer line Degraded hydraulic connection brazed joints TT2 quadrupoles

13 Maintenance and consolidation in IEF  Refurbishment of defective magnets F61N.DVT01 out of service due to water leak, replacement requires to dismount part of the concrete block shielding around F61N.DHZ01 in degraded state, no spare Magnets to be refurbished in workshop  Support from other groups EN/HE, TE/VSC, BE/ABP East Area F61N.DVT01 F61N.DHZ01

14 Maintenance and consolidation in IEF  Replacement of the SMH.01 splitter by a “standard” dipole Control system of mechanical movement is “orphan” equipment Split functionality not needed anymore with modification of beam distribution mode (replacement of MNP23 septum by MCB)  Support from other groups EN/HE, TE/VSC, BE/ABP  Start after radiation cool-down period East Area MEP35 splitter MCB dipole

15 Maintenance and consolidation in IEF  Special inspections and tests of main magnet circuits Inspection of the busbars  removing of all BB covers Completion of capacitive discharge tests campaign (3/3): 250 dipole coils  Machine conditions Sectors 1-2 and 2-3 not accessible during a few days (capacitive discharge)  Support from other groups TE/EPC to separate the SMD’s from the load in sector 6-1 and 1-2  After cool-down time for works in half- sextants 1+ and 2- SPS Inter-turn short-circuit on MBB during capacitive discharge campaign 2/3 in 2011 SPS cross-section at MBB

16 Maintenance and consolidation in IEF  Replacement of all cooling supply flexible hoses Consolidation approved, all 2000 hoses already purchased in 2010 Equipment stored since then, could not be installed during previous short shutdowns  Support from other groups EN/CV to empty demineralized water circuits in all sextants  When all inspections requiring cooling water will be completed SPS and transfer lines Delaminated cooling hose Burst cooling hose

17 Maintenance and consolidation in IEF  Expected exchange of 10 to 15 main magnets, following audio-visual inspection results Standard preventive and corrective maintenance (few spares)  Machine conditions Need access to material lift  Support from other groups EN/HE, TE/VSC, BE/ABP SPS Main dipole exchange in the SPS

18 Maintenance and consolidation in IEF  Refurbishment of the 10 most critical MBA magnets with corroded manifold brazed joints Brazed joints corrosion  sign of future water leaks Problem identified on 70 dipoles, mostly MBA  Machine conditions Possibility to do it in ECX5 to avoid logistics in surface? TBC Otherwise, need access to material lift  Support from other groups EN/HE, TE/VSC, BE/ABP SPS Corroded brazed joint

19 Maintenance and consolidation in IEF  Suppression of weak electrical contacts of water pressure and water temperature interlocks False triggering of interlock system  important part of piquet interventions Decision to be taken about technical solution  Support from other groups Possibly TE/MPE, depending on technical solution  After cool-down period North Experimental Area – TCC2 kg/cm² Interlock circuit Manometer with gold tip contacts corroding due to water pressure oscillations

20 Maintenance and consolidation in IEF  Improvements to magnet supply circuits Reduction of hoses interconnections in radiation exposed areas Replacement of obsolete electro-valves by manual valves Proper sleeving of power cables connections on the ground  After radiation cool-down period North Experimental Area – TCC2 Quick connector gaskets degraded by irradiation Improper electrical connections to be sealed with appropriate sleeves

21 Maintenance and consolidation in IEF  EN/EL - Removal of magnets in SPS – LSS1+ To allow access to cable trays for irradiated cable replacement campaign  To be confirmed Requests from other groups Layout of dumping region Requests to other groups  DGS/RP – Support needed in all interventions described above  TE/EPC – Consignation of power converters  EN/CV – Maintain flow in demineralized water circuits

22 LHC Injector Upgrade activities  Upgrade of cooling circuits of the main bending and quadrupole magnets Necessary to allow 2 GeV operation of main magnets Cannot fit with other modifications in LS2 planning Removal of flow-switches and installation of additional temperature interlocks Upgrade of hydraulic connections  Activity spread over the whole LS1 duration, ending with the most radioactive zones LIU-PSB PSB main Quadrupole magnet PSB main bending magnet

23 LHC Injector Upgrade activities  Installation of the PSB injections magnets To reduce congestion during the connection of LINAC 4 BI.BVT10 – required for LINAC 4 (160 MeV) operation BI.QNO 50 & 60 – Consolidation action (profit of vacuum opening)  Support from other groups EN/HE, TE/VSC, BE/ABP  To be confirmed based on magnet availability and planning agreement LIU-PSB Design of new BI.BVT 10 Magnets BI.BVT10 (red) and BI.QNO 50 & 60 (green)

24 LHC Injector Upgrade activities  Coating of 16 dipoles and 4 quadrupoles in 2 adjacent cells of sextant 5 Validation of both magnetron sputtering and hollow cathode coating of VC with a-C during 2014 MD’s Dipoles removed from machine to be coated in workshop (50% to be rebuilt) Installation of pre-coated VC in quadrupoles  Machine conditions Access needed to material lift  Support from other groups EN/HE, TE/VSC, BE/ABP  All magnet should be removed from SPS at the beginning of LS1, and put back in place at the end in a single batch LIU-SPS (e-cloud mitigation) Magnetron sputtering * Hollow cathode coating * * Pictures: courtesy of P.Costa Pinto – TE/VSC

25 LHC Injector Upgrade activities  Modification of the MDHD for injection dogleg compensation Modification of the coils powering scheme from series to parallel to increase strength Required to be done in workshop  Machine conditions Access needed to material lift  Support from other groups EN/HE, TE/VSC, BE/ABP LIU-SPS (Q20) Layout of half-cell 118 MDHD11832 (green)

26 Resources MNC staff and FSU resources MNC resources distribution per activity in 2011MNC resources distribution per activity during LS1

27 Summary  Baseline strategy described in EDMS –More than half of the staff and FSU personnel of MNC will be involved in the LHC splice consolidation –We will perform all the necessary actions to ensure a reliable operation of the magnets in the CERN accelerator complex, including the ones only possible during a long shutdown –We will perform all the necessary actions required by the LIU and the other approved projects –We must postpone less urgent consolidation and maintenance  We acknowledge in advance our colleagues for: –Their support to our activity –Ensuring the availability of the technical services during the inspections –To avoid interrupting the water flow in magnets for long periods