THEMIS Instrument PDR Bill Donakowski/ EFI Radial Boom 1 UCB, October 15-16, 2003 EFI Radial Boom EFI Radial Boom Mechanical (SPB Spin Plane Boom) Bill.

Slides:



Advertisements
Similar presentations
THEMIS Instrument PDRRob Duck 1 UCB, October 15-16, 2003 EFI Axial Booms (AXB) Preliminary Design Review Rob Duck Mechanical Engineering Department and.
Advertisements

SPP Fields Antenna TRL6 Review Pre-PDR Mechanical Design Jeremy McCauley SSL UCB 7/18/2013 Current Configuration: SPP Spacecraft FIELDS, SPP-ANT-MEC-000.
THEMIS Instrument CDR 1 UCB, March 24-25, 2004 EFI AXIAL BOOMS (“AXB”) Critical Design Review Rob Duck Mechanical Engineering Department Space Sciences.
Space Debris Conceptual Design Review Cole Bostrom Corey Godwin Jonathan Kirchmaier Emily Logan Sean Murphy Seanna Renworth
0 Beach Cities Robotics FRC Team 294 Summer Academy Motors and Gears July 20, 2008 Rick Wagner, Mentor, Beach Cities Robotics FIRST Team 294.
EKT314/4 Electronic Instrumentation
1 UCB, May 04, 2005 Magnetometer Booms Vibration Issues Berkeley Composites Laboratory Department of Mechanical Engineering University of California at.
SPP FIELDS V5 Antenna Mechanical Peer Review Draft 2 David Glaser, Paul Turin, Jeremy McCauley, John Bonnell, Dennis Seitz SSL UCB 7/17/13.
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 Integration and Test Critical Design Review Rick Sterling University of California – Berkeley Thm_CDR_IT_Revc.
3-4 Sept. 2008EFW INST+SOC PDR141 Electric Field and Waves (EFW) Spin Plane Boom (SPB) Gregory Dalton Space Sciences Laboratory University of California.
THEMIS Instrument Thermal Peer Review 1 UCB, February 26, 2004 THEMIS T IME H ISTORY OF E VENTS AND M ACROSCALE I NTERACTIONS DURING S UBSTORMS RESOLVING.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Test Plan Michael Ludlam Space Sciences Laboratory.
1 PFP Peer iCDR /9-11 Particles and Fields Package (PFP) Peer Instrument Critical Design Review SWIA Mechanical Gregory Dalton Gregory Johnson UCB-SSL.
THEMIS Instrument PDR 1 UCB, October 15-16, 2003 IDPU Mechanical / Thermal Preliminary Design Review Heath Bersch University of California - Berkeley.
THEMIS Instrument CDR 1 UCB, April , 2004 EFI Axial Booms Thermal Christopher Smith Thermal Engineer
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 THEMIS Electric Field Instrument Fabrication, Integration, and Testing.
THEMIS Instrument CDR(1) UCB, April 19 & 20, 2004 Mission Assurance Critical Design Review Ron Jackson University of California - Berkeley.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 Boom Electronics Board (BEB) Engineering Peer Review Apr. 20, 2004 Hilary Richard.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW Boom PER 30 June RBSP EFW Spin Plane Booms Greg Dalton Space Sciences.
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 Boom Electronics Board (BEB) Engineering Peer Review Apr. 20, 2004 Hilary Richard.
SAND SAMPLING APPARATUS Eglin Air Force Base Gina Teofilak Richard Klimas Dan Mortensen Ruben De Sousa.
FM1 Instrument Suite Pre-Ship Review (PSR)Thermal-1UCB, September 21, 2005 THEMIS FM1 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) THERMAL Chris Smith University.
1 SPP FIELDS MEP Main Electronics Package Preliminary Design Review Bill Donakowski UCB/SSL 13/14 NOVEMBER 2013 MAVEN PFDPU Flight.
Sept. 2008EFW INST+SOC PDR IDPU Chassis Mechanical Design and Development Bill Donakowski Mechanical Engineer UCB/SSL
THEMIS PER 1 UCB, May 02, 2005 Magnetometer Booms Pre Environmental Review Prof. Hari Dharan Berkeley Composites Laboratory (Presenter: David Pankow) Department.
THEMIS Mission PDR/CAR 1 UCB, November 12-14, 2003 Instrument Integration & Test Dr. Ellen Taylor University of California - Berkeley.
Sept. 2008EFW INST+SOC PDR EFW AXB Jeremy McCauley Aerospace Engineer Space Sciences Laboratory, UCB AXB Spacecraft +Z.
THEMIS MISSION PDRMAG BOOM- 1 UCB, November, 2003 Magnetometer Booms (MAGS) Mission Preliminary Design Review Hari Dharan Space Sciences Laboratory University.
THEMIS Instrument FM2/FM3 PEREnvironments- 1 Teleconference 8/30/2005 THEMIS Instrument FM2/3 Pre-Environmental Review Environments Jeremy McCauley University.
STEREO IMPACT Critical Design Review 2002 November 20,21,22 Acuña1 MAGNETOMETER (MAG) M. H. Acuña NASA/GSFC Laboratory for Extraterrestrial Physics.
THEMIS SUITE PRE-ENVIRONMENTAL REVIEW 1 UCB May 2, 2005 THEMIS Pre-Environmental Review Instrument Verification Overview Ellen Taylor University of California.
THEMIS IDPU PDR I&T REQUIREMENTS- 1 UCB, October 16, 2003 I&T REQUIREMENTS Ellen Taylor University of California - Berkeley.
1 Team Mieux Critical Design Review ASME Bulk Material Transporter AME 470 Ltd. December 7, 2004.
THEMIS Instrument PDR 1 UCB, April 19-20, 2004 Spin Plane and Axial Boom Preamps & Sensor Cable Fabrication Critical Design Review Daniel Schickele University.
THEMIS Instrument CDR Bill Donakowski/ EFI Radial Boom 1 UCB, April EFI Radial Boom (SPB Spin Plane Boom) Bill Donakowski
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 Flux Gate Magnetometer and Boom Thermal Christopher Smith Thermal Engineer
1 PFDPU Mechanical Packaging PEER REVIEW MAVEN PFDPU Particle and Fields Data Processing Unit Mechanical Packaging and Design Overview May 09, 2011 Bill.
THEMIS Instrument PDRGSE- 1 UCB, October 15-16, 2003 IDPU Ground Support Equipment Preliminary Design Review F. Harvey University of California - Berkeley.
SWT Overview 1 UCB, Nov15/16, 2006 THEMIS SCIENCE WORKING TEAM MEETING Mission Overview Peter R. Harvey Project Manager University of California - Berkeley.
FM1 Instrument Suite Pre-Ship Review (PSR)Magbooms- 1 UCB September 21, 2005 THEMIS FM1 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) MAGNETOMETER BOOMS Paul.
FM1 Instrument Suite Pre-Ship Review (PSR)INT- 1 UCB September 21, 2005 THEMIS FM1 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) INTEGRATION AND TEST PLANS Jeremy.
1 SPP FIELDS MEP Main Electronics Package Peer Review Bill Donakowski UCB/SSL 18 NOV 2014 MAVEN PFDPU Flight Unit SPP MEP Baseline.
THEMIS MISSION PDRINSTRUMENT OVERVIEW- 1 UCB, November, 2003 THEMIS INSTRUMENT PAYLOAD SYSTEM OVERVIEW Dr. Ellen Taylor University of California - Berkeley.
Autonomous Silicon Microrobots
THEMIS Engineering Peer Review 1 UCB, October 15-16, 2003 Electric Field Instrument (EFI) Operational Concept.
1 PFP Peer iCDR 2011/5/11 Particles and Fields Package (PFP) Peer Instrument Critical Design Review STATIC Mechanical Gregory Dalton Gregory Johnson UCB-SSL.
109-IDPU-Chassis-Donakowski 1 30 Sep – 01 Oct 2009DRAFT RBSP EFW ICDR 109-IDPU-Chassis-Donakowski IDPU Chassis Mechanical Design and Development Bill Donakowski.
Concept Design for LBNF Far detector (LAr single phase)
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 EFI Preamp Sensor G.T. Delory, A. Hull, D. Schickele, J. Bonnell & The EFI Team University of California.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW CDR /30-10/1 535 IDPU Chassis Bill Donakowski Mechanical Engineer UCB/SSL.
THEMIS MRRSystems - 1 GSFC, Jan 5, 2007 Systems Engineering.
THEMIS Engineering Peer Review 1 UCB, October 15-16, 2003 Electric Field Instrument (EFI) Engineering Peer Review Overview Dr. John W. Bonnell and the.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW CDR /30-10/1 Thermal Design Christopher Smith RBSP Thermal Engineer Space.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Systems Engineering Michael Ludlam Space Sciences.
FM4/FM5 IPSRSYS - 1 UCB, May 5, 2006 THEMIS INSTRUMENT SUITE FM4/FM5 PRE-SHIP REVIEW SYSTEM OVERVIEW Ellen Taylor University of California - Berkeley.
INTRODUCTION TO ROBOTICS Part 3: Propulsion System Robotics and Automation Copyright © Texas Education Agency, All rights reserved. 1.
DC MOTOR. Magnetism Opposites Attract / Likes Repel.
Rose Navarro HMI Lead Thermal Engineer
FIELDS Mission Assurance Manager University of California, Berkeley
Bill Donakowski Mechanical Engineer UCB/SSL
Spacecraft Interface and I&T
THEMIS MISSION PRE-SHIP REVIEW
Mars Atmosphere and Volatile EvolutioN (MAVEN) Mission
MISSION PRE-ENVIRONMENTAL REVIEW MASS PROPERTIES & SPIN BALANCE
University of California, Berkeley
Spacecraft Structures
Dave Akin, Lockheed Martin
Integration and Test Organization Chart
LARP Rotatable Collimators for LHC Phase II Collimation
Presentation transcript:

THEMIS Instrument PDR Bill Donakowski/ EFI Radial Boom 1 UCB, October 15-16, 2003 EFI Radial Boom EFI Radial Boom Mechanical (SPB Spin Plane Boom) Bill Donakowski Mechanical Engineer Space Sciences Lab University of California Berkeley

THEMIS Instrument PDR Bill Donakowski/ EFI Radial Boom 2 UCB, October 15-16, 2003 Requirements Structure, Testing, Materials Mechanical-Verification-Spec-1c (Swales/THEMIS specific) THEMIS PAIP GEVS A/R (GSFC General Environmental Verification Specification) Thermal Near Exterior Solar Panel, device gets cold Predicts: -17 C Cold; +36 Hot Range for Deploy: 0 to +20 C Magnetic Cleanliness Mass <1881 grams (Currently: 1757) On-Orbit Deployment is Mission Critical Robust Device with adequate margins Proper Handling of Wire –Storage and Handling –Hand Winding during Flight Build and Following Test Deploys

THEMIS Instrument PDR Bill Donakowski/ EFI Radial Boom 3 UCB, October 15-16, 2003 Design Overview 4 x Attach Legs with G10 Spacers for Thermal Isolation Brushless Gearmotor With Bevel Gears Meter Wheel Base (Magnesium) Sphere and Preamp Release Doors (Spring Preloaded) Main Wire Spool Exit Tube

THEMIS Instrument PDR Bill Donakowski/ EFI Radial Boom 4 UCB, October 15-16, 2003 Flight Heritage Radial Boom Design goes back 25+ years Polar Cluster FAST Mature Designs/Vendor Familiarity Many Design Reviews and Test Data from prior Programs Critical Component Vendors for THEMIS (Wire) Test Fixtures and Procedures in-house at SSL Personnel ramping up to take over Wire Boom ‘Gray Beard’ (Dave Pankow) Dr. Pankow to remain as advisor to program

THEMIS Instrument PDR Bill Donakowski/ EFI Radial Boom 5 UCB, October 15-16, 2003 Customization of Design for THEMIS Use Wire Length Increased to 18m Packaging for mounting to THEMIS Probe Structure Attachment Magnesium replaced 6061 Al for weight savings Sphere Coating Titanium Nitride replaced DAG 213 DC Gearmotor Same Motor Manufacturer (Globe Motors) Similar Performance (300 ounce-inches Torque) Brushless Unit Selected over Brushed –Brushless better design in vacuum –Better Thermal Characteristics –Less Stray Magnetic Field –Higher Performance in smaller package New Electronics Drive Package Required –Designed in-house –Prototype up-and-running 3 weeks without problems

THEMIS Instrument PDR Bill Donakowski/ EFI Radial Boom 6 UCB, October 15-16, 2003 Theory of Operation Integration and Launch Stowed and Unpowered Wire Wound about Spool, constrained by pinch wheels Release Doors Closed Sphere/Pre-Amp Constrained by Release Doors Deployment Release Doors Opened via SMA Pin-Puller Spin of S/C puts outward force on Sphere and Preamp Motor Acts as brake to prevent motion; coaxial wire in tension Motor powers rotation of Meter Wheel Sphere and Preamp is payed out Release Doors Close Back Around Wire As Centrifugal Force exceeds 2G at Sphere, Sphere Key Reel Spring force is overcome and Sphere moves away from Preamp Monitoring –Limit Switch on Shaft counting Rotations –Tension Sensor to sense High Tensile Force Science Ops Deployed Booms Configuration Unchanged

THEMIS Instrument PDR Bill Donakowski/ EFI Radial Boom 7 UCB, October 15-16, 2003 Theory of Operation Meter Wheel Preamp Motor Main Wire Spool Pinch Rollers Release Doors Sphere Motor Drive Electronics

THEMIS Instrument PDR Bill Donakowski/ EFI Radial Boom 8 UCB, October 15-16, 2003 Materials and Construction Standard UCB Construction Most Components Machined Aluminum –6061 T6 and 7075 T73 –Alodined and Anodized Machined Plastics –PEEK Machined Magnesium Alloy AZ31B –Chosen for Weight Relief in Structure –Not MSFC-SPEC-522 High Resistance to SCC –Table II ‘Moderate Resistance’ –Requires MUA for use Thermal Treatments Surfaces covered with VDA tape or blankets No Heaters Required Common manufacturing techniques used No Unusually Tight Tolerances No Difficult Fabrications

THEMIS Instrument PDR Bill Donakowski/ EFI Radial Boom 9 UCB, October 15-16, 2003 Long Lead Hardware Multi-Conductor Wire Vendor: Gore Custom to UCB Spec (THM-SPB-M101) 8 single conductors/ 1 coax Lead Time: 6 weeks RFQ in process Spares: 100% Over DC Brushless Gearmotor Vendor: Globe Motors Custom based on OTS Globe Gearmotor –Braycote 601 lubricant –Nickel Plating replaces Cadmium Lead Time: approx. 90 Days RFQ has gone out Spares: 12 units

THEMIS Instrument PDR Bill Donakowski/ EFI Radial Boom 10 UCB, October 15-16, 2003 Issues and Concerns Scientist’s Mantra: “More Wire=More Science” Care must be taken to resist pushing heritage design too far Full Deploy Testing Difficult Mass See above With 20 units on-board at launch, margins are tight Packaging on Probe ongoing Issue Larger Probe Tanks slightly impinging Tighter Packing being worked Random Vibration Test Inputs 14.7 grms inputs are high, increases risk to Instruments On-going discussion with Swales to decrease Handling/Storage/Build/Accounting of Wire and Parts Build and Test of Radial Booms tedious and labor intensive THEMIS ‘mass production’ of instruments mandates strict parts tracking and accounting paperwork