Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 GC Contract Sum:$9,061,000 Total Project Cost:$11,067,360 Change Orders to Date (1):$3,152 Current Phase:1 (On Schedule) Estimated Completion:34% September 2009
Cassidy Elementary – Renovation Rendering of Final Façade September 2009
Cassidy Elementary – Renovation Work Completed in Last 30 Days: Concrete seating walls complete at playground and mulch in place. Storm sewers at rear of building complete. Morton parking lot extension complete. Second floor joist and slab structure complete at new additions. Masonry load bearing walls complete on Admin Addition. Brick Veneer complete on rear addition. Mechanical and electrical work rough-ins continue in new additions. September 2009
Cassidy Elementary – Renovation Current Work Effort (September): Storm sewer and underground detention system to complete. Stage floor to be poured and masonry load bearing walls installed. Roof joists and deck to be installed. Roofing finish to start before end of month. Interior metal framing to begin in enclosed areas. Elevator installation to be complete by end of month. Sprinkler rough-ins to begin. Rooftop mechanical units to be installed. Electric transformer to be installed. September 2009
Cassidy Elementary – Renovation New Admin. Addition New Classroom Wing Corridor 2 nd Fl September 2009 New Media Center from 2 nd Fl. New Stage Addition