Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.

Slides:



Advertisements
Similar presentations
Update on FCPS Construction/Renovation Projects June 2009.
Advertisements

Update on FCPS Construction/Renovation Projects July 2009.
WEEKLY PHOTO REPORT WEEKLY PHOTO REPORT September 16 th, 2013 – October 25 th, 2013.
Update on FCPS Construction/Renovation Projects September 2009.
Update on FCPS Construction/Renovation Projects May 2009.
WEEKLY PHOTO REPORT WEEKLY PHOTO REPORT Week of: August 5 th, 2013 – August 9 th, 2013.
CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,
Update on FCPS Construction/Renovation Projects April 2009.
THE PROJECT BRIEF… BUILD A CONTEMPORARY HOME ON A SMALL INNER CITY BLOCK WITH NO ROOM FOR ONSITE STORAGE OR SCAFFOLD.
Update on FCPS Construction/Renovation Projects August 2009.
April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.
Bryan Station Middle – Renovation Architect: Clotfelter-Samokar Architects General Contractor: Preston Construction Group Substantial Completion Date:August,
Progress Report 12/13/11. Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall.
Finance and Facilities. DuPage County, IL EAV Growth History (Five Year Average: -2.15%)
Arlington Elementary – Renovation Architect: RossTarrant Architects General Contractor: W/S Construction Substantial Completion Date:August, 2010 Contract.
Leestown Middle – Renovation Architect: Lucas/Schwering Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 GC Contract.
SHEPHERD ELEMENTARY SCHOOL PHASE I SHEPHERD ELEMENTARY SCHOOL PHASE I SITE PLAN.
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
Facilities Modernization Program Funded by Measure B Project Report April 16, 2012.
Bryan Station Middle – Renovation Architect: Clotfelter-Samokar Architects General Contractor: Preston Construction Group Substantial Completion Date:August,
TECHNICAL ASSIGNMENT #1 – NATHAN BRASKEY SUNNYVALE PLAZA [Cooper Carry, Inc.]
Bar joist over kitchen and band room. Setting bar joist over kitchen and electrical/mechanical rooms.
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Dan Packer Construction Management Senior Thesis April 16, 2002
Reading Structural Drawings
Foundation Plan Layout
Board of Education Presentation 2015 Referendum Projects September 9, 2015 Update.
Progress Photos Goodnoe Elementary School Additions and Renovations Project November 2013 Goodnoe Elementary School.
First Baptist Church of Doylestown Senior Thesis Structural Emphasis James Chester Preliminary Phase II Design.
Project Status Project Phasing Questions 2 As of Today Project released for Bid February 7, 2011 Notice of Bid sent to 80+ Contractors on February 2,
Update on FCPS Construction/Renovation Projects March 2009.
Foundation Systems Unit 11. Types of Foundations Pilings Continuous Grade Beam.
Project Status The project is progressing well with both grading aspects and building components. The mason has erected many walls to “scaffold high”
Prof Ralph V. Locurcio, PE CON 2001 CVE Sequence Single Family House - 3,000 square feet Duration 1 General Conditions 21 2 Apply for Permits.
F ACILITIES, P LANNING, AND C ONSTRUCTION December 14, 2015 – Monthly Construction Report.
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
Elevating the Quality of Life in the District. AFTER RENOVATION BEFORE RENOVATION.
Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
October 19, 2011 Construction Progress Report. Construction Progress Report – October 19, 2011 Contract sum to date:$ 162,736,722* Total completed to.
Salmon River CSD Capital Project Phase II Monthly Status Report March & April 2016.
WEST DES MOINES LIBRARY ADDITION Team North Final Presentation Team North The Ace Mentor Program career direction for students in architecture,
1 Update on Off-Campus Development in South County: Update to FPP CAC – August 25, 2015 Siteman Cancer Center Expansion Phase II Development.
TRIGON, INC ARDMORE CITY SCHOOLS 2013 BOND ISSUE PROJECTS.
LIFE CYCLES OF AIKEN COUNTY PUBLIC SCHOOLS CONSTRUCTION PROJECT October 8, 2013.
Parks & Recreation 2016 Bond Referendum Project Information.
Bond Oversight Committee
Bond Oversight Committee
UPDATE ON DOE RUN ELEMENTARY CONSTRUCTION PROGRESS
School Improvement Bond Projects
UPDATE ON DOE RUN ELEMENTARY CONSTRUCTION PROGRESS
Design of a Commercial Shopping Center
Designing a Commercial Shopping Center
Design of a Commercial Shopping Center
ET 494: Senior Design Design of a New Hammond Head Start Center
Capital Improvements Presentation
HANDICAPPED PEOPLE RESIDENT
Progress Report 11/10/11.
1 Semester Project Design A Multi Story Office Building
Minuteman Vocational Technical Regional High School Progress
Lehigh Valley Heritage Center
2007 Bond Issue Capital Improvement Program
Value of contract: Length of contract: Contract start date:
In-Class Scheduling Exercise
Minuteman Vocational Technical Regional High School Progress
Minuteman Vocational Technical Regional High School Progress
Minuteman Vocational Technical Regional High School Progress
Minuteman Vocational Technical Regional High School Progress
Presentation transcript:

Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 GC Contract Sum:$9,061,000 Total Project Cost:$11,067,360 Change Orders to Date (1):$3,152 Current Phase:1 (On Schedule) Estimated Completion:34% September 2009

Cassidy Elementary – Renovation Rendering of Final Façade September 2009

Cassidy Elementary – Renovation Work Completed in Last 30 Days: Concrete seating walls complete at playground and mulch in place. Storm sewers at rear of building complete. Morton parking lot extension complete. Second floor joist and slab structure complete at new additions. Masonry load bearing walls complete on Admin Addition. Brick Veneer complete on rear addition. Mechanical and electrical work rough-ins continue in new additions. September 2009

Cassidy Elementary – Renovation Current Work Effort (September): Storm sewer and underground detention system to complete. Stage floor to be poured and masonry load bearing walls installed. Roof joists and deck to be installed. Roofing finish to start before end of month. Interior metal framing to begin in enclosed areas. Elevator installation to be complete by end of month. Sprinkler rough-ins to begin. Rooftop mechanical units to be installed. Electric transformer to be installed. September 2009

Cassidy Elementary – Renovation New Admin. Addition New Classroom Wing Corridor 2 nd Fl September 2009 New Media Center from 2 nd Fl. New Stage Addition