1 MICE PM report – status of Phase II Target update Spectrometer solenoid FC & coupling coils Schedule considerations Project accommodation & management.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
RFCC Module Update Derun Li Center for Beam Physics LBNL, Berkeley, CA MICO Weekly Phone Meeting March 21, 2011.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
1 UKNF/MICE Oversight Committee Open session Integration of the MICE project Background & local history Progress since 2007 Schedule & planning considerations.
1 MICE Video Conference Reception of FC magnets Andy Nichols, STFC,
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
Spectrometer Solenoid and RFCC Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
1 UKNF/MICE OsC PM report Summary assessment of MICE Risks, pressures and worries Project management Electrical substation, accommodation Redefining the.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 MICE Project Board Schedule and milestones Reconstructing the schedule Present status Monitoring and feedback Key schedule drivers and concerns Andy.
Spectrometer Solenoid and RFCC Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
1 MICE-UKNF Oversight Committee MICE Project Manager Report Contents: New schedule and its implications Preparations for Steps II & III Spectrometer solenoids.
1 MICE CM28 STEP III or STEP IV? – some practicalities Andy Nichols/Tim Hayler, STFC 4 th October 2010 Considerations Step II Step III Step IV Conclusions.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.
1 PM report International & UK programmes Overview Reconstructing the schedule The UK Project Management team Progress with major subsystems Substation.
UKNF/MICE PSAG, 3/5/11 Spectrometer solenoids: –Repair plan still ‘in approval’, already two months late –Workshop/mini review at LBNL 10 th /11 th May.
Infrastructure Update As at 11 th March 2009 Remaining four plates now fitted to North shield wall North & South walls and all galleries are considered.
1 MICE PSAG PM report Brief overview Re-planning the project Solenoids, decay and spectrometer Open issues and worries Andy Nichols, STFC, PSAG, 5/5/10.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
Project manager report paul drumm CM16 October 2006.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
MICE Collaboration meeting (CM20) At RAL 10 – 13 Feb 2008 AFC Magnet – Status and Progress W. Lau, Oxford University.
Technical Board and Safety Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
1 MICE PM Report Outcome of Reviews held at CM22 –Motivation for holding them –Outcomes & actions –Observations & follow-ups MICE Video Conference, 20.
MICE CM35 Status and Goals Alain Blondel 1 WELCOME TO MICE CM35! – Status and Goals - Many thanks to Chris Rogers, Debbie Loader and Rose Hayes for taking.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
1 PM report Schedule comment Coupling magnets Major staffing concerns Andy Nichols, STFC, UKNF/MICE PSAG,
MICE CM 29 Collaboration Board Summary. Agenda 1.Intro 2.Approval of minutesBooth/Bross 3.Spokeʼs remarks & EB reportBlondel 4.PM reportNichols 5.US magnet.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MPB 31 October 2012 and FAC 15 November monitor how well we are doing in assembling step IV ! -- should deliver a ‘realsitic schedule scenario’
1 MICE CM27 PM Report Re-defining the UK project this FY Schedule things Apologies and accommodation Andy Nichols, STFC 7 th July, 2010.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
MICE VC Alain Blondel 1 1. MOM is now Victoria 2. Linda Coney is new MICE Online Group coordinator (rep Jean-Sebastien) May we held.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
1 MICE Schedule Review no 1 Aims of review and description of review charge Motivation and external drivers Aims of the review A few of the problems Description.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
MICE – UK Plan Roy Preece STFC RAL DOE Review of MAP Brookhaven National Laboratory 13 th August 2014.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
Status of MICE RF for Step V’ (at LBNL) Derun Li Lawrence Berkeley National Laboratory December 6, 2014.
UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016.
The MAP 3-Year Plan Mark Palmer Fermilab September 26, 2014.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 MICE Coupling Coil Cryostating and Test Steve Gourlay March 1, Office of Science.
1 MICE CM25 Engineering Session Summary Contents: Infrastructure Diffuser Coupling Coils Radiation Shutter AFC module EMR Andy Nichols, STFC, 4-7 th November.
Schedule and Milestones Colin Whyte STFC RAL Resource Loaded Schedule Review 5 th April 2016.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
Reported by Ron Prwivo for Ian Robson. Overview Response to Recommendations from the RLSR of November 2014 – very good, RF staffing remains an issue Very.
Status of the MICE Construction Project
MICE CM31 Schedule summary
MICE PM Report Progress with the Infrastructure A few problems
Presentation transcript:

1 MICE PM report – status of Phase II Target update Spectrometer solenoid FC & coupling coils Schedule considerations Project accommodation & management Don’t have time for a detailed status report, have a look at: UKNF/MICE PSAG, 11 th January, 2010

Target update Running with online target finished for this year at end of user run, no dust or debris observed at viewport – running completely trouble-free Everything for T2r and T3 is done except plastic bearing liners: Torlon material was machined last week – not preferred material, as it contains PTFE, but will give valuable data/experience for offline running in R78 Vespel delivery (preferred material) has been sad tale – repeated missed deliveries, but alternative billet has been found and ordered Still a good chance we can make mid-lateJan for T2r offline build-up in R78 Stator research/re-work is making reasonable progress Comprehensive target controls rack is complete at Sheffield 2

Spectrometer solenoid Review at LBNL generally went OK: Recommended that given the circumstances, adding the fourth CCR to magnet #2 was the right approach Thermal FEA study of magnet must be progressed urgently Operating margin must be evaluated accurately at cooldown The modifications to magnet #1 should proceed as planned Present status: Magnet #2 (the first one we get) is in final stages of leak- checking this week Cooldown begins 18 th January Powering tests occupy, say 25 th January to 20 th February* Ship to FNAL end February* * AN’s interpretation only! 3

Spectrometer solenoid What happens at the cooldown/powering: MICE has agreed some acceptance criteria via its Technical Board: Must sustain design current for min 24 hours LHe top-ups > six weeks apart (this is ‘not quite’ agreed yet) Declaration of conformity is completed An as-built installation drawing and specification is completed We hope this decision point arrives around mid- February, if all is met and field mapping goes OK, then we get magnet #2 around mid-May. If not, we may have to face a ground-up rebuild (one year) and magnet #1 will overtake 4

5 4 th single stage CCR HTS lead area This plate needs more Cross-section * These connections under Close scrutiny * * This is where the work is

FC, LH2, CC FC: –Design work on the FC making good progress at Tesla –Some nagging doubt that the integration between the LH2 absorber and the FC is not properly understood –Is being dealt with by Technical Board – would prefer to bring the engineering responsibility to STFC –FC delivery still promised for July/August, 2010 –Request at CM to place solid absorber(s) in FC at Step IV –Some minor design/manufacture work to accommodate, will be done by Oxford LH2: –Going well at AS scientific –Parts have arrived to complete the gas panel –Very clear that we have to resume work on the vent system during 2010 to be on time 6

FC, LH2, CC Good progress also with the CC: –Problems in China are being solved: –Engineering drawings of magnet will be done on time –Project management structure at HIT is being re-built –Aim is to let magnet contract to Qihuan by time of Riverside Collaboration Meeting (late March, 2010) –One set of RF cavities (four + one) have been delivered to LBNL – are being polished just now –Real delivery dates of CC magnet will become clear as order is placed 7

Schedule considerations No real changes from last month, ie: –Steps II &III are combined and will aim to be ready for February, 2011 –Significance of Step III.1 is being evaluated by MICE –Have realised though that we need to be working on the H2 vent system during 2010 to be on time for Step IV –Integration steps are now well understood and detailed –We’re critically dependent on the big subsystems, just three dates..... –Next step is to make the plan for the above 2010/2011 period, most of it exists, but some knocking together needed –All the UK preparations for Steps II &III are in place, or will be done by Feb/March (CCR water system and floor drilling, CCR compressor racking) 8

Project Accommodation Looking ahead to Steps V & VI, we will need more space at RAL for: Pre-integration, especially RFCC modules Storage of tooling, materials and finished modules. – Ideally need ~ 350 sqm with 15 tonne crane access – Have expressed interest in R79 – But R40 is excluded – What are the plans for R12 when workshop moves to R79? – R9 might also be available, would be ideal given proximity to UKNF equipment in R8 – Have discovered Blueprint accommodation committee, Justin Greenhalgh is rep for EID – have booked meeting. 9

Project Management Practical steps have been taken to appoint Project Planner: Contact made with Mark Smith company (Andrew Bowyer), waiting for suitable meeting date – had the meeting – very positive Had meeting/MICE visit with UKAEA (Roy Manning), but need to follow up (have followed up) Need to see a few more – no we didn’t No commitments made – have stated that we’re waiting for financial approval Two sensible offers now received from both firms Hope is to parcel up the project monitoring and control function as one discrete task, full time at first, but hopefully becoming part-time It’s a costed line in the C&S review So far efforts to find a person within STFC or MICE have not worked 10

Living within our means (from last PSAG) FY 09/10 must finish on budget Progress on the cuts: – Stop LH2 October (done – end November) – Stop RF power in October (ditto) – Stop PPS in November (done) – Reduce TD effort bookings to skeleton level for three months (done) – Reduce Merit-Merrell/S&T costs by 50% - (done) – Hope we can resume normal service early 2010 – still hoping, but see below! – Target development and Step II infrastructure will be preserved Valuable design and technical staff have now moved to other projects – this is a very uncomfortable situation 11

Concerns & risks Just one this time 2 MVA transformer upgrade is now more serious, but thanks to Ken’s efforts there might be some good news Additional CCR compressors for spectrometer solenoid might mean Step III is at risk rather than Step IV – clearer after review DL group is currently doing the exercise – in progress 12