Cooling & Ventilation feed-back M. Nonis – EN/CV.

Slides:



Advertisements
Similar presentations
Engineering Department EN Cooling and Ventilation issues 1 FUTURE EXPLOITATION OF THE EAST AREA EN-CV Michel OBRECHT.
Advertisements

CERN IT Department CH-1211 Genève 23 Switzerland t Mobile services: Sunrise SWAP Rodrigo Sierra IT/CS.
Plasma Wakefield (AWAKE) Project Meeting 18 October 2012 Civil Engineering Feasibility Issues for the West Area EDMS : John Osborne GS-SE.
1 WP 10- High Voltage ’06 March 23 rd HV Trip studies  See previous meetings for the foreseen tests on LBC44  Started late by Clermont people when Clermont.
CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
STTC 20/08/2002 Eva Sánchez-Corral 1 ST Division W2000 Migration status report Organisation and Management Strategy and Planning Review of experience Status.
Bilan du contrat Renco Piping contract F467 TS workshop Archamps Mai 25 th 2005 R. Principe TSCV.
Christophe Delamare EDMS Accelerator Consolidation Workshop GS/ASE activities.
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
IEFC Workshop 2011 David Mcfarlane Superintendent for SPS EN/MEF/ABA 1.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
TS-CV contracts case study LHC pipelines and HVAC for Experimental Areas R. Principe, J. Inigo-Golfin.
Alfa-Omega Team Coordination LS1 Collaboration Seminar, 27 th November 2014 Anna Chrul, IFJ PAN Kraków.
Maintenance Specificities in the CERN Cooling and Ventilation Group Asset and Maintenance Management Workshop CERN, November 2013 I. El Hardouz,
VIRGINIA’S IMPLEMENTATION of the FINAL RULE on WORK ZONE SAFETY and MOBILITY Virginia Department of Transportation’s Instructional and Informational Memorandum-LD-241.
Radiation Protection LS1 - Collaboration with CERN Technical Groups - Lessons learnt Stephane Bally (CERN), Sandro Di Vincenzo (CERN) Indico
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
112/09/2013. Summary  Events on the network  Incidents  Network reconfigurations  Network operation  Update on activities  Tests  Projects and.
EN-CV during LS1: Upgrade, Consolidation, Maintenance, Operation M Nonis EN/CV Chamonix 2012 – LHC performance Workshop On behalf of EN/CV Group.
EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.
Workshop on the Use of Ethernet as a Fieldbus CERN, 28 September 2001 Use of Ethernet in the control systems of the cooling and ventilation infrastructure.
LHC Access System August 2006 LHC Access System – Status and Planning August 2006 Elena Manola-Poggioli Eva Sanchez-Corral TS-CSE on behalf of the LHC.
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
TS Workshop, Archamps, May 24 – May 26, 2005 The LHC Access System Status report – May 2005 P. Ninin & the Access project team TS/CSE.
June 1 rst, Consolidation for E-cloud and High Voltage cards N.Vauthier TE-CRG LS1 projects review:
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
Status of renewal of Buildings 115 & 507 Borge & Erwin Siesling.
1 Safety and Database Subsection ADO - PO - SA Safety achievement and future activitiesSafety achievement and future activities Database (see K. Pommes.
Technical Support Activities in PH-ADO-PO
Assembly Organisation and Duration. Work Site Organisation STORAGE SMA18 UNLOADING CLEAN ROOM CERN-SITE CLEANING MANUFACTURE DIRTY TRIAL ASSEMBLY ISO7.
ST/MAforLHC April 2003Sixth ST workshop1 Summary of ST/MA deliverables for LHC Luigi Scibile for the ST/MA group.
Cooling and Ventilation Activities M. Battistin – EN/CV/PJ IEFC Workshop th March 2012 « CONSOLIDATION and UPGRADE PLANS for the INJECTOR COMPLEX.
Plan. 12/05/ Who are we? PM (Project Management and Resource Planning) – APT – IMPACT – PPTEU2 – Plan LS1 – 2012 –…–… Plan V2 – From LS1 to LS2.
 Overview of the run 2009 for CV  Major improvements in Water treatment - Demineralised water production - Cooling control  Major concerns for.
R2E Mitigation Project P5 Relocation Options - Discussion R2E Mitigation Project CMS Relocation Options Towards An R2E Baseline 1 M. Brugger for the R2E.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
K. Foraz, S. Prodon TS-IC TS workshop – May 2005 Underground logistics K. Foraz, S. Prodon TS-IC.
1 LHCC RRB SG 16 Sep P. Vande Vyvre CERN-PH On-line Computing M&O LHCC RRB SG 16 Sep 2004 P. Vande Vyvre CERN/PH for 4 LHC DAQ project leaders.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Briefing Chilled Water and Temperature Stability Chris Channing Sr. Project.
First results from the study of the LHC cycle power consumption FCC I&O meeting 24 th June 2015 Davide Bozzini With the contribution of G. Burdet, B. Mouche,
LS1 Day EN-CV M. Nonis on behalf of CV group / CERN
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
LS2 Cooling & Ventilation Activities M. Battistin EN/CV Acknowledgements: P. Barriere, R. Bozzi, A. Broche, O. Crespo,
T. KurtykaLinac4 meeting 12 March 2009 Guidelines from the sLHC Specification Committee 1). sLHC Specification Committee 2). Schedule of tenders for Linac4.
TE-CRG-CE OMP Meeting 06 / 11 / 2014TE-CRG-CE OMP Meeting.
LS1 Review P.Charrue. Audio/Video infrastructure LS1 saw the replacement of BI and RF analog to digital video transport Was organised in close collaboration.
NA62 CV activities Piero Valente 5 th September
For more information, please contact 14/12/2010 EN/CV/DC Technical specification IT-3684 by Elena Perez Rodriguez.
Survey activities during LS1 Dominique Missiaen On behalf of the SU section.
SAFETY SERVICES PROVISION I. Bejar Alonso. Transfer Executive Safety Tasks from SC to Departments In application of the document “Safety policy at CERN”
17 th November 20061M. Battistin CERN LEAF Committee 2/R-030 8h30 – November 17 th 2006 Michele Battistin (TS/CV/DC) TS/CV Detector Cooling On call and.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
18, 19, 20 February 2002 Power Converters for magnets (PBS 1.2.3) R. GENAND SL/PO 1 Power Converters for Magnets –Introduction –Specification Magnet characteristics.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
R2E relocation & shielding LS1 preparation Anne Laure Perrot EN/MEF- LE Discussion with OP colleagues, 5 th July 2012.
ID week 27 th of April 15 C3F8 cooling- Compressors & C3F8 status O. Crespo-Lopez EN/CV.
SMB SMB-SE group L. Scibile 1. SMB Mandate The SMB-SE Group is responsible to provide, to operate, maintain and to renovate the civil engineering infrastructures.
CV works in the non- LHC accelerator complex during 2008 and plans for 2009 ATOP days 2009.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
LHC experience with installation Katy Foraz March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop ***********************************
LHC intervention scheduling with the Work Acceptance Tool
EN-CV activities for LHC during LS2
CERN Construction Planning and Scheduling (LHC installation)
Francois and Lau EATM 17 July 2012
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
Renovation of the 45-year old PS magnets
East Hall under construction
Presentation transcript:

Cooling & Ventilation feed-back M. Nonis – EN/CV

Contents Some figures: LS1 for EN/CV Issues, good and less good: Preparation phase Staff Contracts Specific case: welds Safety Internal organisation Conclusions 2

Duration of LS1 - LHC 3 Stop of one system/circuit. Temporary solutions installed (flying chillers) CV/OPCV/DC No stop for: Ventilation underground & surface Chilled water Compressed air Raising systems Drinking water supplies Fire hydrants network

Workload: M&O hours 4

TEMPORARY SYSTEMS INSTALLED Linac 2 back up chiller during replacement of the PS chilled water pipes Flying chiller for experiments during maintenance CMS – February - May ALICE – June - October LHCb - November - March ATLAS (CNGS one) – September - December 867 radioactive workshop: local demineralised water production during the refurbishment of the 378 production 5

Orders Contract typeNo.kCHF F2211’078 B6627’750 E81424’014 C2972’131 S144’254 others4’09716’224 [kCHF] Carry overTotal Payments13’30028’01022’7401’29065’250 Orders24’37024’91015’97065’250

Logistics ventilation PS tunnel Work areas: Ventilation rooms Galleries Phases:Dismantling - 4 months Installation -1 year 7 Radioactive temp. storage Worksite barracks New material storage Transport: 2 persons 8h00 – 16h00 RP: bi weekly Site manager: weekly + as needed. Storage areas : Wastes: PS  151  ISR (twice per week) for 3 years New: 180, 353,…  PS Route Goward: ok - planned passages Air locks asbestos: Continuous underpressure Inside ventilation rooms

General (personal) feed back: 1.Everything went well, much better than what I thought at the start of LS1! 2.Key factor of success: everyone collaborating, pushing in the same direction. 8

Preparation phase 9 Limited access to work areas before/during studies: Real issue for newcomers; Claim from contractor; Working on pictures/drawings is not optimal. Early requests for information by other services difficult to answer (with a certain reliability): Number of welds to check Storage needs near worksite Transport need Use of – ref. K. Foraz talk Late start of some project (re engineering)… lack of resources

Staff 10 Detailed preparation of LS1 since end 2011: Staff tired already beginning 2013, No break until end Fragmentation of work: Projects approved according to need, not really to available resources, High number of projects per PL, work supervisor, draftmen, control…, Less focused, More time consuming  higher workload. Would it be better to focus on less areas but cover all systems in the area? Late arrival Staff (May 2012…) PJAS (March 2013) Staff already «experienced» of CERN project. Estimated increase of people: +50% (mainly contractors’ personnel)

Frame contracts 11 Specially adapted for works such as R2E, late requests, and to catch up delays; Not for major intervention (drain of resources). Existing ones did not really cope with our needs: Limited additional resources, Reluctant to provide personnel for short period, Good level of competency. Additional contracts for works would have been quite useful….but less people in each of them Dismantling: asbestos &/or activated material: PS ventilation, chilled water pipes in PS and NA, SRs, CCC; Need for large contract for all CERN?

Contractors (supply) MS, 22 major contracts 2010 – 2011: effort to increase the portfolio of possible contractors not to depend on too few contractors and to increase competition. New contractors: 5 (UK, E, F, 2 x I) only 2 with no previous experience of work at CERN at beginning of LS1 Start up phase a bit difficult: Safety training courses Most of problems related to claims for additional costs not knowing CERN procedures and contract clauses. Not really ready to work on shifts (lack of personnel), systematically willing to work during holidays.

X RAY TEST FOR WELDS 13 Contractually every contractor is supposed to subcontract this check to any company he choses. In practice, all contractors ask Qualitech, one single contractor for all CERN. Figures for CV: Number of welds checked: 1’708 (94% Qualitech) Number of interventions: 196 (90% Qualitech) Total time spent: 1’583 hrs (95% Qualitech) Everything went well, not one single disruption, delay or issue to report over the two years! However, is there a risk in depending from one single contractor?

Safety Extremely good collaboration and valuable help during the preparation phase (RP issues, asbestos….). A bit of confusion on: Training courses Radioactive material containers Vacuum cleaners Electrical habilitation Different procedures per complex (IMPACT) mainly for late decision wrt work start. 14

CV Retreat – November 2014 Retreat internal to the group to share experience and wrap up lessons learnt… Actions: Evaluation of workload (real vs estimate) Commissioning team Planning manager 15

Conclusions Need for additional resources. Prepare in advance! Be flexible with contracts. Most effective where we can concentrate on one single major project wrt fragmentation in several smaller interventions. Very good collaboration among groups and services… everyone had the same objective. 16

Wrap up 17 Good It looks like it works! Collaboration among groups Planning, flexibility New contractors Improve Preparation: access to areas, arrival of people Reduce the number of system to be kept in operation Better adjust staff to workload Resources provided by IS contract Internal organization: planning mgr, commissioning team…

A big thanks to all people who collaborated with us during LS1 Questions? 18