ABT LIU Project Review 2015 BI.KSW: Magnet November 20 th 2015 L. Feliciano TE/ABT.

Slides:



Advertisements
Similar presentations
Kicker SloW (KSW) magnets and Generators PSB 160 MeV H - injection L. Feliciano TE/ABT.
Advertisements

Backwards Compatibility L4 – L2 W. Weterings LBCC - 14.
PSB extraction and transfer kickers 01/10/2014 LIU-PS ABT review1 L. Ducimetière, L. Sermeus.
1. BI.STR Stripping Foil exchanger: Controls hardware & spending 2 Pieter Van Trappen PVT - TE-ABT-EC.
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
Status of handling studies for PSB-LIU Caterina Bertone EN-HE LIU-PSB 17/09/2015 Courtesy: A. Newborough EDMS
John LeRose March 12, A Program of three “projects” to assemble the Super BigBite Spectrometer for a series of experiments in Hall A There is a.
ENEN H- INJECTION: STATUS ON MECHANICAL DESIGN - VACUUM SECTORIZATION - BHZ162 CHAMBER MODIFICATIONS - DUMP AREA - BHZ11 CHAMBER MODIFICATIONS.
Vacuum sectorisation H- Injection Some history Wim Weterings
New injection region 1L1 Engineering Change Request PSB-L-EC-0001 EDMS Wim Weterings PLI Meeting Wednesday 14 th January 2015.
LIU-ABT systems: SPS B.Balhan, J.Borburgh, H.Day 20 th November 2015.
BI.DIS10: Magnets & generators R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November
Consolidation of the Booster Injection Quadrupole Magnets (part 2) A. Aloev 14 th February 2013.
Outline Injection septum SMH42 Injection bumper Resources Conclusion LIU-ABT review 20/11/2015 Status PS injection septa2.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
Review on shorter PSB main bending magnets Injection layout with short magnets Advantages & Disadvantages Wim Weterings
PSB Injection Overview + Specification changes ABT LIU Project Review Wim Weterings.
POTENTIAL EN-MME DESIGN JOBS IDENTIFIED BUT CURRENTLY NO REQUEST FROM EQUIPMENT OWNERS TO EN-MME EDMS B.RIFFAUD On behalf of EN-MME design team.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
PSB-PS TRANSFER AT 2 GEV - CONCEPTS AND OPTICS W. Bartmann, J. Abelleira et al. ABT LIU Review, 20-Nov-15.
PSB H- injection concept J.Borburgh, C.Bracco, C.Carli, B.Goddard, M.Hourican, B.Mikulec, W.Weterings,
Increase of the T600 maximum drift distance and preliminary considerations for larger aluminum vessels Claudio Montanari INFN-Pavia, Italy 1ICARUS Meeting.
ABT review on the LIU-PSB Systems PSB KSW Magnets September 10 th 2014 L. Feliciano TE/ABT.
PSB Reference Magnet (for the 2.0 GeV upgrade) A.Newborough 16 th October 2014.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
ECR - PSB: New KSW magnet in 16L1 Luis Feliciano, 4 th February.
ELENA KICKERS AND SEPTA ELENA Meeting, Prepared by J. Borburgh, E. Carlier, A. Fowler, L. Sermeus TE/ABT.
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
LINAC3 UPGRADE Source and LEBT modifications for YETS and recommissioning timetable 28/10/2015 Ville Toivanen.
LIU-PSB Overview K. Hanke for the LIU-PSB Working Group K. Hanke, LIU-2011, 25 Nov 2011.
TCDI Project Budget Update François-Xavier Nuiry May 10 th 2015 EN-STI-TCD.
PS-LIU status S. Gilardoni – BE/ABP H. Damerau – BE/RF LIU-PT 27 Aug
PSB HW Commissioning Meeting 8 February 2016 A. Akroh, B. Mikulec.
Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus.
PSB extraction and transfer kickers LIU TE-ABT review, 20 November L. Sermeus.
ELENA installation progress F. Butin / ELENA collaboration.
Wim Weterings Remy Noulibos
26/11/2015 LIU-PSB meeting, Status of BE and BT kickers and septa 2 Extraction and Recombination Septa and Kickers status Jan Borburgh, M. Atanasov, W.
Electrial Safety LS2 days November 2016 AP
Survey on “Chargés de Consignation” Status Update
Vacuum System P. Chiggiato TE-VSC
LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
Linac4-PSB 160 MeV connection readiness review
LIU Wire Scanner Project
LIU – EVM status and next steps
PSB Lock Out Test, Follow-Up AP. Bernardes-/EN-STI, K
LINAC4 ADVISORY COMMITTEE
Brief Status SPS Prototype PSB Prototype Installed in LS1
EYETS David Hay EN-OSS.
ELENA installation and commissioning status
LIU – EVM status and next steps
AD consolidation activities in LS2
LIU–PLI report LIU PSB meeting.
EC Activities Status for the LIU
LIU–PLI report LIU SPS meeting.
EN/HE activities for LIU
TE-ABT Activities for LS2
Status of the BI Work Package in the LIU-PSB frame
ELENA electron cooler and SEM grids status
Spectrometer Solenoid Fabrication Status and Schedule
WPs concerned by L4 connection:
Update on MKP Strategy ACKNOWLEDGEMENTS M.J. Barnes
EYETS septa status Septa activities TE/ABT Thierry Masson
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
Beam Injection and Extraction Scheme
XFEL Collimation and Beam Switchyard Vacuum Issues
LIU-SPS review for BI (no BWS)
Status of the BI Work Package in the LIU-PSB frame
PS magnet status D Bodart 25/06/2019.
Presentation transcript:

ABT LIU Project Review 2015 BI.KSW: Magnet November 20 th 2015 L. Feliciano TE/ABT

Introduction New KSW Layout Kick requirements Hardware Planning Budget Next steps Conclusions BI.KSW: Magnet November 20 th 2015 L. Feliciano 2 Agenda

During the installation of the new H – injection system, the KSW1L1 magnet stack will be removed from its present location to give a place for the new injection system. In order to accomplish the painting bump a series of 4 horizontal kicker stacks (KSW) are used outside the injection region to produce a closed orbit offset of 35 mm at the injection foil. Regarding this, the fourth KSW magnet stack will be installed in section 16L1. BI.KSW: Magnet November 20 th 2015 L. Feliciano 3 Introduction

BI.KSW: Magnet November 20 th 2015 L. Feliciano 4 Present & Future 16L1 section

As for the new hardware, the two major modifications that will come out are: – the 1L1 magnet stack will be removed from his present location to give room to the new injection system. – a new 16L1 magnet stack will be installed in between the bending magnet’s BHZ152 and BHZ161. – Other minor changes includes the move of the present 16L4 to replace the 2L1, which will be reconverted into spare. As a result, the outer magnets 16L1 and 2L1 will be mechanically and electrically identical. Likewise for the inner ones 16L4 and 1L4. All 8 new magnets as well as future spares will be equipped with new vacuum ceramic chambers. BI.KSW: Magnet November 20 th 2015 L. Feliciano 5 New KSW Layout

BI.KSW: Magnet November 20 th 2015 L. Feliciano 6 Kick Requirements

Magnets – All 16 half magnets assembled. – Both magnet sets are finished. BI.KSW: Magnet November 20 th 2015 L. Feliciano 7 Hardware

Ceramic vacuum chambers – Titanium deposit homogeneous. – No vacuum leaks. – Ti Resistivity value within the spec (0.3Ω). BI.KSW: Magnet November 20 th 2015 L. Feliciano 8 Hardware Middle: Coated Ceramic Chamber Left : Mounting set-up prior to pump down. Right : Bottom centring part (cathode and anodes)

The original planning was made on the assumption that the magnets would be ready end % of the project has been completed. Nevertheless its not granted that we will be able to finish on the proposed date. In order to reduce the workload on the injection area during LS2, our proposal is to put in place the 16L1 magnets during the YETS 2015/2016. BI.KSW: Magnet November 20 th 2015 L. Feliciano 9 Planning The two magnet sets are ready as well the associated vacuum chamber. To reduce the workload on the injection area during LS2, we propose to put in place the 16L1 magnets during the EYETS 2016/2017.

BI.KSW: Magnet November 20 th 2015 L. Feliciano 10 Budget Metrics per year in kCHF Year PV EV AC Year PV EV AC Cumulative metrics per year in kCHF

Next steps BI.KSW: Magnet November 20 th 2015 L. Feliciano Close the ECR approval, to be presented to IEFC. Updated Design Office version of the model of the support for the new vacuum chamber to be integrated in the integration 3D model. Confirm if the kicker is installed on the bench with or without additional support (calculation to be done by MME). Start the WDP. Close follow up with third parties (TE/VSC & TE/MSC), the advancement of the new equipment to be installed on 16L1 section of the PSB. 16

BI.KSW: Magnet November 20 th 2015 L. Feliciano12 Conclusions Waiting for EYETS