Chapter 6 Scheduling. 222 Learning Objectives  Estimate the duration for each activity  Establish the estimated start time and required completion time.

Slides:



Advertisements
Similar presentations
Project Management Concepts
Advertisements

Developing the Schedule
Developing the Schedule
Chapter 6 Scheduling. 222 Learning Objectives Estimate the duration for each activity Establish the estimated start time and required completion time.
Chapter 7 Project Management
Chapter 17 Project Management McGraw-Hill/Irwin
Finding the Critical Path
Chapter 13 Project Scheduling: PERT/CPM
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edwards University.
F O U R T H E D I T I O N Project Management © The McGraw-Hill Companies, Inc., 2003 supplement 3 DAVIS AQUILANO CHASE PowerPoint Presentation by Charlie.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects…
Project Management Concepts.  What is a Project?  Common Project Terms  What does a Project Manager do?  What’s in a Project?  Project Management.
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Terminology Project: Combination of activities that have to be carried out in a certain order Activity: Anything that uses up time and resources CPM: „Critical.
2 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Project Management 2.
1 Topics to cover in 2 nd part ( to p2). 2 Chapter 8 - Project Management Chapter Topics ( to p3)
Fall 2001BA Project Management1 BA 301 – Spring 2003.
1 1 Slide © 2005 Thomson/South-Western Q 5 – 13 x 1 = the probability that Station A will take Sitcom Rerun x 2 = the probability that Station A will take.
1 1 Slide © 2004 Thomson/South-Western Chapter 12 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
MGMT 483 Week 8 Scheduling.
1 1 Slide © 2009 South-Western, a part of Cengage Learning Slides by John Loucks St. Edward’s University.
1 1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
Project Management Chapter 13
CHAPTER 4 MANAGING PROJECT PROCESSES. THE CONCEPT A project is an interrelated set of activities that has a definite starting and ending point and that.
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edward’s University.
Chapter 10 Project Scheduling: PERT/CPM
ISP-2010 Network Evaluation & Analysis ISP Project Management.
© 2012 Cengage Learning. All Rights Reserved. This edition is intended for use outside of the U.S. only, with content that may be different from the U.S.
1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times Project Scheduling with Known.
© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.
Operations and Supply Chain Management, 8th Edition
Project Management Techniques.
Project Management An interrelated set of activities with definite starting and ending points, which results in a unique outcome for a specific allocation.
Roberta Russell & Bernard W. Taylor, III
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Copyright 2006 John Wiley & Sons, Inc. Project Management OPIM 310.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Chapter 8 Resource Considerations
1 Project Management Chapter Lecture outline Project planning Project scheduling Project control CPM/PERT Project crashing and time-cost trade-off.
Managing Project Resources. Project Resources Human Resources Project stakeholders: – Customers – Project team members – Support staff Systems analyst.
Project Management (專案管理)
1 1 Project Scheduling PERT/CPM Networks. 2 2 Originated by H.L.Gantt in 1918 GANTT CHART Advantages - Gantt charts are quite commonly used. They provide.
1 1 © 2003 Thomson  /South-Western Slide Slides Prepared by JOHN S. LOUCKS St. Edward’s University.
1 1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
PROJECT MANAGEMENT Approaches
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
Project Time Management
(M) Chapter 12 MANGT 662 (A): Procurement, Logistics and Supply Chain Design Purchasing and Supply Chain Analysis (1/2)
TK3333 Software Management Topic 6: Scheduling. Contents  Estimate the duration for each activity  Establish the estimated start time and required completion.
Prof.Dr. Ahmet R. Özdural – Class Notes_06 - KMU417 Project Planning and Organization – Fall Semester.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Operations and Project Management Session 3 Extra Some Additional Details on CPM and PERT.
Scheduling Scheduling : is the process of converting a project action plan into an operating time table. Why scheduling ? To answer the following questions:
Project Management (專案管理)
Project Management Chapter Topics
Chapter 17 Project Management McGraw-Hill/Irwin
Chapter 6 Scheduling
PERT and CPM.
Chapter 6 Scheduling
Developing the Schedule
Chapter 16 – Project Management
Slides Prepared by JOHN LOUCKS
Project Management CPM/PERT Professor Ahmadi.
Chapter 6 Scheduling
Presentation transcript:

Chapter 6 Scheduling

222 Learning Objectives  Estimate the duration for each activity  Establish the estimated start time and required completion time for the overall project  Calculate the earliest times at which each activity can start and finish, based on the project’s estimated start time

3 Learning Objectives (Cont.)  Calculate the latest times by which each activity must start and finish in order to complete the project by its required completion time  Determine the amount of positive or negative slack  Identify the critical (longest) path of activities

4 Real World Example Vignette: The World Cup Tournament South Africa is the host country for the Federation Internationale de Football Association (FIFA) World Cup tournament in The South African government is projected to invest more than R400 billion on infrastructure projects. Additionally, between R2 billion and R5 billion will be spent on information and communication technology projects. Large investments will be made to ensure all transit systems form an effective public transport network. Additionally $1.1 billion has been earmarked for new and renovated stadiums to hold the games of the World Cup. Unfortunately there are reports of schedule delays and budget overruns. “Many people do not fully understand the details of project management as a specific entity – such as detailed work breakdown structures and critical paths.” Link 1Link 2

5 Real World Example Vignette: Fast-Track Innovation in Indiana The major improvements necessary on a stretch of the combined I-65 and I-70 arteries posed numerous challenges to the Indiana Department of Transportation (INDOT). Project would involve 33 bridges and 35 lane miles of highway, and one side of the highway would need to be shut down. The project, was completed in just 55 days, earning its name, ‘‘Hyperfix.’’ To decrease the duration of construction time, the whole stretch of affected highway would be closed and numerous contractors would be working each day, 24 hours a day, 7 days a week. Excellent project management at all phases of this project resulted in successfully and quickly improving the highways, while minimizing any inconvenience to the drivers.  Massive communications effort  Met with community stakeholders for buy-in

6 Activity Duration Estimates The first step in scheduling is to estimate how long each activity will take. The duration estimate is the total elapsed time for the work to be done PLUS any associated waiting time. The person responsible for performing the activity should help make the duration estimate.

Activity Duration Estimates (contd) An activity’s duration estimate must be based on quantity of resources expected to be used.  Estimate should be aggressive, yet realistic. Playing the game of inflating or padding duration estimates is not a good practice. Over the life of a project that involves many activities, delays and accelerations will tend to cancel one another out. 7

8

9 Project Start and Finish Times It is necessary to select an estimated start time and a required completion time for the overall project. These two times define the overall window (envelope) of time in which the project must be completed. The project’s required completion time is normally part of the project objective and stated in the contract.

10 Schedule Calculations A project schedule includes:  the earliest times (or dates) at which each activity can start and finish, based on the project's estimated start time (or date)  the latest times (or dates) by which each activity must start and finish in order to complete the project by its required completion time (or date)

11 Earliest Start and Finish Times Earliest start time (ES) is the earliest time at which a particular activity can begin. Earliest finish time (EF) is the earliest time by which a particular activity can be completed. EF = ES + Duration Estimate

12 Earliest Start and Finish Times Rule #1 The earliest start time for an activity must be the same as or later than the latest of all the earliest finish times of all the activities leading directly into that particular activity.

13 The earliest start time for an activity must be the same as or later than the latest of all the earliest finish times of all the activities leading directly into that particular activity

14 Latest Start and Finish Times Latest finish time (LF) is the latest time an activity must be finished in order for the entire project to be completed by its completion time. Latest start time (LS) is the latest time an activity must be started in order for the entire project to be completed by its completion time. LS = LF – Duration Estimate

15 Latest Start and Finish Times Rule #2 The latest finish time for a particular activity must be the same as or earlier than the earliest of all the latest start times of all the activities emerging directly from that particular activity.

16 The latest finish time for a particular activity must be the same as or earlier than the earliest of all the latest start times of all the activities emerging directly from that particular activity

17 Total Slack, Defined Total slack (TS) or float is the difference between the calculated earliest finish time of the very last activity and the project’s required completion time. Total Slack = LF - EF or Total Slack = LS - ES

18 Total Slack (Cont.) If total slack is positive, it is the maximum time the activities on the path can be delayed. If total slack is negative, it is the amount of time the activities on the path must be accelerated. The total slack for a particular path of activities is common to and shared among all the activities on that path.

20 Critical Path The critical path is the longest path in the diagram. The activities that make up the critical path have the least slack. All activities with this value are on the critical path.

21 Types of Critical Paths Noncritical paths have positive values of total slack. Critical paths have zero or negative values of total slack. The most critical path is the longest critical path.

22 Free Slack The amount of time an activity can be delayed without delaying the start of other activities. It is the relative difference between the amounts of total slack for activities entering into the same activity. It is always a positive value.

A F G I BEH D 34 C

24 Scheduling for Information System Development Some common problems that push IS projects past their required completion time:  Failure to identify all user requirements  Logical design flaws  Continuing growth of project scope  Underestimating learning curves for new software packages

25 Project Management Software Allows one to perform scheduling functions. Activity durations can be estimated in a variety of ways. Project start and finish times can be entered in a variety of ways. Can calculate dates, times, total and free slack.

Appendix 1 Probability Considerations (will not cover for undergraduate class) 26

27 Probability Considerations Activity Duration Estimates Optimistic time: time to complete an activity if everything goes perfectly well. Most likely time: time to complete an activity under normal conditions. Pessimistic time: time to complete an activity under adverse circumstances.

28 Probability Considerations The Beta Probability Distribution When using three time estimates, it is assumed that they follow a beta probability distribution. The expected duration is calculated using the following formula: t e = (t o + 4(t m ) + t p ) / 6

Peak represents most likely time; divides curve into two equal parts

30 Probability Considerations Probability Fundamentals Network planning that uses three time estimates for each activity can be considered a stochastic or probabilistic technique, since it allows for uncertainty. Any technique that uses only one time estimate is considered to be a deterministic technique.

31 Probability Fundamentals (Cont.) The total probability distribution is a normal probability distribution. The variance for the beta probability distribution of an activity is: Variance =  2 = ((t p – t o ) / 6) 2 The standard deviation, , is another measure of the dispersion of a distribution and is equal to the square root of the variance.

Standard deviation measures dispersion Normal Distribution

33 Probability Fundamentals (Cont.) The total probability distribution of the critical path activities is a normal distribution. The mean equals the sum of the individual activity expected durations. The variance equals the sum of the individual activity variances.

34 Calculating Probability The probability of completing a project before its required completion time: Z = (LF – EF /  t )  LF = the required completion time (latest finish).  EF = the earliest expected finish time (mean of the normal distribution).   t = the standard deviation of the total distribution of activities on the longest path.  Z = number of standard deviations between EF and LF on the normal probability curve

99% 95% 68% 50% %