LS2 Cooling & Ventilation Activities M. Battistin EN/CV Acknowledgements: P. Barriere, R. Bozzi, A. Broche, O. Crespo,

Slides:



Advertisements
Similar presentations
Engineering Department EN Cooling and Ventilation issues 1 FUTURE EXPLOITATION OF THE EAST AREA EN-CV Michel OBRECHT.
Advertisements

CERN IT Department CH-1211 Genève 23 Switzerland t Mobile services: Sunrise SWAP Rodrigo Sierra IT/CS.
Long shutdown 2013: Electrical distribution activities 09/03/2012 IEFC 2012 Workshop F. Duval on Behalf of EN/EL group.
CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
Christophe Delamare EDMS Accelerator Consolidation Workshop GS/ASE activities.
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
Chilled water Meyrin consolidation Study 1 st Part Many thanks for their contribution to: Pasquale Alemanno, Fortunato Candito, Alexander Putzu.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
Maintenance Specificities in the CERN Cooling and Ventilation Group Asset and Maintenance Management Workshop CERN, November 2013 I. El Hardouz,
CONSOLIDATION ON CIVIL ENGINEERING AND TECHNICAL INFRASTRUCTURE P. Alves, M. Nonis, P. Pepinster, W. van Baaren 6 th ST Workshop – March 2003.
European Organization for Nuclear Research - Organisation européenne pour la recherche nucléaire 1CERN - 4th November 2011 Experience from Construction.
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
EN-CV during LS1: Upgrade, Consolidation, Maintenance, Operation M Nonis EN/CV Chamonix 2012 – LHC performance Workshop On behalf of EN/CV Group.
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
IT-4082 Design, Supply, Installation and Commissioning of the ventilation of the BAF3 building Alexandre Broche EN-CV-PJ.
Cryogenics in SPS & LHC (2 K / 4.5 K) LHC-CC11, 14 November 2011 L. Tavian, CERN, TE-CRG With the contribution of N. Delruelle, G. Ferlin & B. Vullierme.
Status of renewal of Buildings 115 & 507 Borge & Erwin Siesling.
Consolidation and Upgrade of the SPS Electrical Networks Current Status JP. Sferruzza, on behalf of EN/EL.
Cooling and Ventilation Activities M. Battistin – EN/CV/PJ IEFC Workshop th March 2012 « CONSOLIDATION and UPGRADE PLANS for the INJECTOR COMPLEX.
Thursday 6 th May 2004 C. Martel – Cooling Ventilation - CERN TS/CV TS/CV/BE COOLING VENTILATION TECHNICAL DESIGN OFFICE TS Workshop Archamps 2004.
J. Direito - M. Battistin – 28 th May 2010EN/CV/DC J. Direito, M. Battistin (EN/CV/DC) 28 th May 2010 Detector Cooling Project III Thermosiphon Workshop.
EN-CV interventions during YETS
 Overview of the run 2009 for CV  Major improvements in Water treatment - Demineralised water production - Cooling control  Major concerns for.
CMS Proposal for a Maintenance & Operation agreement with EN/CV/DC for fluorocarbon detector cooling circuits v.2 P. Tropea For the CMS experiment.
COOLING & VENTILATION FOR THE DRIVE BEAM TUNNEL M Nonis – EN/CV – 16/9/2009 CLIC TWO BEAM MODULES REVIEW
The Building 180 Cryogenic infrastructure water cooling system Stefano Moccia, EN-CV Coordination meeting 26/09/14.
First results from the study of the LHC cycle power consumption FCC I&O meeting 24 th June 2015 Davide Bozzini With the contribution of G. Burdet, B. Mouche,
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
5 th May 20061M. Battistin CERN LEAF Committee 2/R-030 8h30 - May 5 th 2006 Michele Battistin (TS/CV/DC) TS M&O agreement for Detector Cooling installations.
Cooling & Ventilation feed-back M. Nonis – EN/CV.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
CMS consolidation activities of detector cooling system Detector cooling project P. Tropea.
TE-CRG-CE OMP Meeting 06 / 11 / 2014TE-CRG-CE OMP Meeting.
Cryogenics for crab cavities – SPS/LHC 2 nd HiLumi LHC meeting – Frascati (Italy) 15 November 2012 K. Brodzinski and L. Tavian on behalf of cryogenic team.
For more information, please contact 14/12/2010 EN/CV/DC Technical specification IT-3684 by Elena Perez Rodriguez.
INFRASTRUCTURE CHANGES AND UPGRADES Presented by: Fernando Baltasar dos Santos Pedrosa in the name of the four LHC experiments.
Building 180 NORMATEF TEST FACILITY Demineralized cooling water station upgrade R. Bozzi / EN-CV.
Engineering Department EN Cooling and Ventilation issues 1 FUTURE EXPLOITATION OF THE EAST AREA EN-CV Michel OBRECHT.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
EN-EL Activities for LS2 LIU, Consolidation, Maintenance, Operation Nicolas Bellegarde on behalf of EN-EL.
TE-CRG Activities D. Delikaris, TE-CRG.
110 th November 2010EN/CV/DC Detector Cooling Project - advancement status of Work Package N3 Thermosiphon project Michele Battistin 18 May 2011.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
SMB SMB-SE group L. Scibile 1. SMB Mandate The SMB-SE Group is responsible to provide, to operate, maintain and to renovate the civil engineering infrastructures.
Technical Review EHN1 Extension Cooling Systems and Pipework Jérôme Rodary / EN-CV.
CV works in the non- LHC accelerator complex during 2008 and plans for 2009 ATOP days 2009.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
EDMS N° V.1 TE-EPC Activities during LS1 V. Montabonnet [TE-EPC]
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/14.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/02/04.
Update on the PSB Cooling and Ventilation Systems
EN-CV activities for LHC during LS2
AD consolidation activities in LS2
EN-CV Progress EHN1 Extension Project
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
CV maintenance works during YETS
Cooling systems for HL-LHC (WP17.3)
SPS activities during LS2 TE-EPC (Power Converter Group)
EN-CV interventions during EYETS for PS and PSB
COOLING & VENTILATION INFRASTRUCTURE
East Hall under construction
EN-CV: P8 systems and Detector Cooling
Experimental Areas – LS2 planning
Aziz AMAMOU EACM – 21th May 2019
LINAC 3 Meeting ICL machines Injectors
Presentation transcript:

LS2 Cooling & Ventilation Activities M. Battistin EN/CV Acknowledgements: P. Barriere, R. Bozzi, A. Broche, O. Crespo, S. Deleval, M. Nonis, S. Moccia, P. Pepinster.

Agenda Introduction Projects Presented in geographical order Some details on main projects CV Maintenance Conclusions M. Battistin EN-CV2

Introduction LS2 workload CV presents the list of potential projects and expected worksite duration (design & tendering phases are not shown); Not all the list is supposed to be realised; CV-Consolidation: to be approved by consolidation PL (M. Benedikt); CV-clients interactions to define new installation requirements; CV-MEF iterations to define planning (plan tool); Real duration of LS2 for CV Some CV installation needs to be available in the middle of LS2 (LS2 for CV will be shorter). M. Battistin EN-CV Good planning + increase of flexibility 3

List of possible CV activities Geographical groups: Meyrin PS – PSB – EA Prevessin – NA SPS LHC Machine LHC Experiments General CERN Tentative time slot + duration of each work phase. M. Battistin EN-CV4 An overview first of all…

General overview (months of worksites) M. Battistin EN-CV 2015 YETS EYETS YETS LS TOTAL Meyrin PS + PSB + EA Prev + SPS + NA LHC + LHC Exp Divers Total CV LS1 consolidation workload represented about 25 MCHF, the consolidation activities in this list for LS2 correspond to about 45 MCHF. CV consolidation strategy: LS1-LHC, LS2-PS, LS3-SPS. 5 How to deal with these figures…

M. Battistin EN-CV6

Meyrin Projects M. Battistin EN-CV Bdg 107 and 311 projects are the to major project on Meyrin (out of accelerators zones) Activities mainly free from LS2 constraints 7

AD complex consolidation M. Battistin EN-CV CV considers the AD complex consolidation more critical than the East Area one. New air handling units for the AD hall In addition the the HVAC system is supplied by drinking water in open circuit and represents a considerable consumption (up to 110 m 3 /h). New local chilled water production (1.5 MW); Chilled water production: CV is evaluating a general strategy for the chilled water production in the PS-PSB-513-ISOLDE- AD area; New cooling tower (7 MW) + demi water station; The AD target zone CV installation shall be completely refurbished  design well advanced with STI; ASBESTOS removal is a general problem  see dedicated slide later 8

PS – PSB – EA The PS consolidation represent the largest effort for CV during LS2. M. Battistin EN-CV9

Consolidate PSB water cooling plant Primary water (Bat. 237) Old cooling towers (increased legionella risks), pumping equipment and hydraulic accessories to be replaced; Demineralized water (Bat. 237) For radioprotection constraints, the surface premises circuit shall be separated from the tunnel circuit; New magnets increased pressure drop -> the tunnel circuit pressure rating to be increased from PN16 to PN25; New cooling system for to C16-RF cavity (on drinking water today); New piping distribution in Bat. 361 (BRF2 room) for new Power Converters. Considering the amount of work foreseen in this area for LS2, CV plans the installation of the primary water system (new towers on top of Bat. 141 or 269 plus some piping) before the start of LS2. This project is not officially approved in the Consolidation Plan yet. M. Battistin EN-CV10

Consolidation of PSB ventilation Underground ( ≈ 300 kW, air 20°C ) Dismantling of the old ventilation units Installation of two new air handling units (2 x 35’000 m 3 /h); Surface system ( ≈ 500 kW, air 20°C): Dismantling of the old ventilation units; Installation of two new handling units (2 x 63’000 m 3 /h); Smoke extraction Chilled water: Refurbishment of the production; Asbestos: uncertainty on the cost the presence of asbestos to be removed radioactive waste management? concrete structure of existing units to be demolished. One of the 4 AHU’s to replaced  It is not foreseen to change any existing ducts.  At least 6 months for demolishing existing units and installation of the new ones.  NO mechanical ventilation up to the installation of the new AHUs (manual mode) about 6 months at the LS2 start-up  No advance work will be possible before start of LS2.  Overlap with other activities in the same area (i.e. PSB cooling or chilled water) still to be investigated. M. Battistin EN-CV11

Adiabatic cooling units for Converter Hall Cooling towers (redundancy) VRV Unit for offices Demi water pumping station. 2 Separate circuits (copper and aluminum) N+1 redundancy for cooling towers fans and pumps POPS-B (new MPS for the PSB-LIU) B 245 User requirements well defined for CV (EDMS ); demi water cooling power about 500 kW; ventilation cooling power about 170 kW; general integration is running now; 245 building under construction; Small demi water cooling skid to be installed at POPS for the dummy load magnets;  CV installation to start end of 2016;  Cooling and HVAC commissioned by August 2017; M. Battistin EN-CV S. Moccia contribution 12

EAST AREA M. Battistin EN-CV This project (cooling + ventilation) is not considered as a priority within the CV consolidation plan; in the present conditions the systems should be still operational after LS2 and could be refurbished during LS3. However, this project is presented following a request to plan a complete consolidation for the EA hall in LS2 and has to be considered only within that frame. 13

East Area Hall VENTILATION Consolidate the existing HVAC system (hall + barracks) Keep the existing configuration (radiant panels + AHUs) Replace the overheated water distribution network Works duration: 6 months M. Battistin EN-CV P. Pepinster contribution COOLING Separate radioactive and not radioactive the cooling circuits; Create a new cooling station in bldg.157 dedicated to the primary zone, with cooling towers outdoor (locations to be studied / validated);  Works duration: 12 months. 14

East Area - Primary Zones Ventilation Provide dynamic confinement to the zone NB: a good static confinement (air-tightness) of the zone is required to assure the confinement of the nuclear installation Works: Similar to nTOF and CHARM/IRRAD Primary zone in underpressure < -5 Pa New HVAC system including HEPA filtration on air extraction Works duration: 6 months M. Battistin EN-CV P. Pepinster contribution 15

Prevessin – NA MEF proposes a large consolidation activity of EHN1 in The BAs buildings in the North Area complex have been built in the late 70’s and never refurbished since. The major problems encountered are related to their aging conditions and the increasing number of breakdowns. Chilled water network phase II: asbestos removal and radioactive waste M. Battistin EN-CV16

SPS projects BB3-BA3 cooling system revision is the large strategic project in the SPS area for LS2 Safety issues on reject of SPS infiltration water into the SPS loop SPS ventilation safety improvement project started now possible important impact on tunnel ventilation M. Battistin EN-CV17

Second phase of the BB3-BA3-BAF3 project M. Battistin EN-CV LS1: primary cooling pipe from SPS loop to 905 Now: upgrade of the chilled water production of BA3 May 2016: temporary skid 850 kW in RF amplifiers LS2: modify the primary cooling system in BB3-BA3 18

LHC machine projects New cooling tower at point 18 is the major intervention for LHC zone; The HL-LHC design and purchase phases run during LS2 -> resources. M. Battistin EN-CV19

Replacement of STP18 cooling towers M. Battistin EN-CV Upgrade of primary water from 3-cells tower (6 MW) to 2-cells tower (16 MW) Construction of new concrete 2-cells tower in 2018; Installation in the pumps room and buried distribution pipes in 2019; Support from GS is required for the new concrete building. 20

ALICE & ATLAS ALICE: preparatory projects to allow Alice upgrade works in LS2, searching for computer center cooling solution… ATLAS: upgrade of the ventilation of the cavern UX15 M. Battistin EN-CV21

CMS & LHCb CMS: last week announced very large detector cooling revision (+1.5 MW) ready for LS3 -> to be studied. LHCb workshop on 20/2/2015 -> searching cooling solution for large computer center; large detector evolution -> changes in the Detector Cooling. M. Battistin EN-CV22 Activity overview is over, let’s see general issues…

…a solution for ASBESTOS removal M. Battistin EN-CV ASBESTOS: CV suggests to set-up a large “CERN asbestos removal contract” to cope with all, even large, asbestos removal activities at CERN. Second phase of the chilled water piping consolidation PS+NA During LS1  PS ventilation, PS chilled water piping, NA chilled water piping Consolidation of PSB: old concrete + asbestos air handling units PS tunnel: 60 years old ventilation ducts over the machine …a number of medium-small intervention will require asbestos removal 23

Test & Commissioning Given the quantity of CV systems concerned and the important modifications to be performed, the test & commissioning of each CV plant will be a major activity requiring several days per plant. In addition, each equipment Group will need to test & commission his equipment before considering his work completed. During each of these steps the effort required to CV team is not negligible (drain, fill up, balancing of circuits…) and, only after their successful completion, CERN can enter the commissioning phase of each accelerator. 24 M. Nonis - LS1 Day Please enter all test details in PLAN…

Main External Contributions Civil engineering: meeting CV-SE on 9 th September 2015 to share the list of larges request of contribution: New cooling towers of Pt18 + AD; Roofs consolidation (CCC, 237, 351, etc.); A number of asbestos removal worksites. EN/EL: Provide the needed power for the different installations, supply of cubicles; The plan tool will be used to announce the CV requests for each project. Radio Protection: Assess the activation of existing equipment to be dismantled; ALARA Level 3 analysis will be probably required for the PSB projects; Radioactive waste production is foreseen in the PSB, PS and NA areas. Pipe welds x-ray test: 95% of contractors requested Qualitech intervention: all ok in LS1 but risk of one single point of failure. Shall we have two contractors there? Safety coordination: very good collaboration and valuable help during LS1 Difficult to estimate the workload now. Transport: waste handling during CV systems demolishing M. Battistin EN-CV25

Maintenance and Operation The work to perform for the maintenance of existing installation is expected be similar as LS1: Mechanical revision ( of working hours) of motors, pumps and fans; Cleaning of heat exchangers; Repairs of the cooling towers; Re-qualification of vessels; Replacement of the desiccant of the air dryers; Calibration of the sensors; Chiller replacement / mechanical revision As the program is similar LS1 the workload expected should be about 120% of a “run year”; The new cryo-back-up cooling tower (installed in LS1) will limit the unavailability impact of the LHC cooling tower during maintenance (2 months each) M. Battistin EN-CV26 This will imply unavailability of installations…

20192 months (cryo excepted) weeks (cryo excepted) month weeks month weeks week day CV Installations’ Unavailability – Any Complex 27 M. Battistin EN-CV27

M&O Organisation During LS1 the requests of CV operation from other groups implied a sensible engagement of manpower for the entire duration of the LS1: We need to anticipate it → sharp requests in Plan!! The request to provide mobile temporary installation to re- establish the service during maintenance shall be limited; CV recommends to reduce as much as possible the systems in operation to allow to transfer operation resources to works and projects. M. Battistin EN-CV28

Conclusions The “shopping list” of possible CV projects is extremely large: the manpower will be the critical resource of LS2 for CV, if possible even more critical than during LS1; new PLs should arrive well in advance (beginning 2017 at latest). CV recommends to focus consolidation activities in a defined zone instead of dispersing forces in a number of zones; CV consolidation strategy: LS1-LHC, LS2-PS, LS3-SPS. Asbestos removal would need a general CERN coordination for all projects. Large incertitude in cost and planning related to dismantling of asbestos & radioactive material. PLAN PLAN PLAN !!! M. Battistin EN-CV29

Thanks for your attention and contribution. Any Question?