ASTA Accelerator Directorate Review Project Plan and ES&H Carsten Hast May 20, 2014.

Slides:



Advertisements
Similar presentations
PEPPo Weekly Status Meeting February 16, 2011 & 6MSD Planning Meeting February 23, 2011 Part 1 – Technical summary of layout Part 2 – Month-by-Month Installation.
Advertisements

Kathleen Ratcliffe BC2/Linac Installation April 16, BC2 / Linac Installation Coordination Kathleen.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
MONALISA installation at the ATF2 ATF2 weekly meeting.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
Stefan Moeller XES FAC Review – April 16, 2006 X-Ray Endstation Systems (XES) Status Stefan Moeller.
Richard M. Boyce FAC April 16, LCLS Installation & Planning Integration process – IMT 2007 Installation Planning BTH.
1 Stefan Moeller 1 AMO Instrument Schedule ARR AMO Instrument Schedule Stefan Moeller – XES Manager June 30, 2009.
John Arthur Photon Systems April 16, LCLS Photon Systems Status Technical status and accomplishments Response to.
John Arthur Photon October 29, Photon Systems Update FAC recommendations Current status New plan for Photon Systems.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Bill White Laser Installation and April 20, Laser Installation and Commissioning April 20, 2006 Procedures.
David H. Dowell Injector April 29-30, 2004 LCLS Injector Overview D. H. Dowell, SLAC FAC Review April 29-30, 2004 Injector.
John Arthur Photon October 12, Photon Systems Update John Arthur SLAC 1.
Status of IPBSM Improvement N. Terunuma, KEK 2012/July/13 ATF2 Weekly Meeting.
Compressor status AWAKE Technical Board meeting 19 May 2015.
PIP Update June 25 th Agenda Summary Update – Current Activities/Updates – Ryan Crawford: Anode Supply Update – Peter Prieto: BPM Update – CY Tan:
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
AWAKE electron source New Electron Source WP at CERN
PIP Update April 30 th Agenda Summary Update – Current Activities/Updates – Nathan Eddy – Booster Longitudinal Damper.
LIGO-G M May 31-June 2, 2006 Input Optics (IO) Cost and Schedule Breakout Presentation NSF Review of Advanced LIGO Project David Reitze UF.
UED ASTA Mechanical Mechanical Design Status Eric Bong 20 May 2014.
ASTA roadmap to EPICS and other upgrades Remote monitoring and control DAQ Machine protection Dark current energy spectrometer.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Linac-4 current situation and outlook U. Raich, F. Roncarolo, F. Zocca.
Integration, Installation & Infrastructure Ans Pardons, with input from the WP4 members September 2014.
Update on Laser Beam Lines Christoph Hessler, Mikhail Martyanov, Valentin Fedosseev (CERN laser team)‎ Thanks to M. Battistin, N. Chritin, F. Galleazzi,
Installation issues - update, July 2006A.Fabich1 MERIT installation: Update July 2006 A.Fabich CERN AB-ATB July 2006.
Compressor status AWAKE Technical Board meeting 19 August 2015.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
FACET User Support Carsten Hast Accelerator Research Division Test Facilities Department
Update on the Laser Beam Line
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
Patrick’s Updates - 8/30/11 (one slide for each of the following) 1.XTCAV Project 2.ASTA Gun Test Facility Instrumentation & Controls 3.Fast wire scanner.
Next Linear Collider 8-Pack Project D. Atkinson MAC Review, May 2002 The 8-Pack Project at NLCTA An overview of the schedule and budget for the project.
1 CTF3 CLEX day July 2006 CLEX day 2006 Introduction G.Geschonke CERN.
FETS-HINS Videoconference 23rd Feb 2007 FETS Mechanical Design Issues by J. Pozimski On behalf of P. Savage.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
WBS – 30 Straight Section Reconfiguration g-2 Accelerator – 30 Straight Section Reconfiguration D. Still Fermilab Muon g-2 IDR, June 5-7.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
LEReC System 1. Project Schedule 2015 shutdown COMPETE! Move beam line equipment from IP 01:00 Install cooling section beam line 2016 shutdown Install.
Laser Line work package (WP6) AWAKE Technical Board meeting 19 May 2014.
ASTA Latest Update E. Harms April Photoelectrons first produced at ASTA on 20 June 2013 –Molybdenum (uncoated) cathode ‘Routine’ Electron operation.
The Next Generation of a Gamma Irradiation Facility GIF++
CBETA Technical Review
Drive-Laser Commissioning Status and Plans
CLEX Building Layout, Conventional Facilities, TL2, TL2’,
CLEX* Status and Plans CTF3 complex CLEX
Commissioning plan for
X-ray Pump-Probe Instrument
SLAC Production Status
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
Advanced Research Electron Accelerator Laboratory
J. Seeman Assistant Director for PPA/LCLS
Injector / Linac Installation Current Status
Project Management Issues John N. Galayda, SLAC April 24, 2002
Linac LLP Outline LINAC Long Lead Procurements
Endstation Systems, Installation Costs and Schedule J. Hastings
LCLS Undulator System Production Management
BC2 / Linac Installation Coordination Kathleen Ratcliffe
LCLS e- Beams Systems Manager
Polarized 3He target installation
Presentation transcript:

ASTA Accelerator Directorate Review Project Plan and ES&H Carsten Hast May 20, 2014

ASTA Project Milestones Overall Schedule -Started April Ends September 30 th 2014 with results ASTA Infrastructure -General layout and consensus what to do agreed upon in late April New optical tables, mini girders, new gun location, support stages, various chambers, etc. New AC design and installation for laser room Relocate some LCW feeds, 110V outlets Improve ventilation in ASTA -Moved X-band devices (Done) -AC project is in purchasing (eta mid August) -Mini girders (June 13 th ) -Optical benches (June 13 th ) 2

ASTA Project Milestones Beam line components -Overall beam line layout done Ready to order bellows this week (eta mid July) -Designed sample chamber (going to purchasing this week, installation ~ Aug. 4 th ) Motorized stages to be ordered this week (eta mid July) -Designing diagnostics chamber (no long lead items) -Designing detector chambers (no long lead items) Screens and reflecting mirrors, Faraday cup etc. available -Various support stages are in fabrication (T-1 and various supports) (June-July) -Ion pumps and controllers are available: surplus from NLCTA -Turbo pump(s) need to be ordered soon Laser parts -Ready to order, details in Ryan’s talk Modulator stabilization available in July (Minh’s talk) 3

ASTA Installation Schedule Infrastructure work June 16 th - June 27 th -During night and weekend will operate X-band (most of the time) -Remove old laser optics infrastructure -Move gun -Move LCW -Install mini girders -Install new optical tables (maybe a shelve over one) -Provide plenty of 110V outlets -Improve ventilation in ASTA -Additional penetration -Pull additional cables -More Ethernet 4

ASTA Installation Schedule Cathode laser work 2 weeks in July -During night and weekend will operate X-band (most of the time) -First round of controls work for motors, cameras, etc. -Install existing GTL detector chamber for testing beam line -Test the new stable modulator voltage with beam (Minh’s talk) Turn on new AC (August 18) Experiment laser work 2 weeks in August -During night and weekend will operate X-band (most of the time) -Install all new chambers and complete beam line -Finish controls work for motors, cameras, etc. Commissioning starts September 1 st (latest) 5

ASTA What’s Missing? Controls Work -In June: Need to layout what we need, want and how to do it -Preliminary work in July -Commissioning in August RF / Laser Timing -Need a schedule (Joe F.) Better M&S estimate, both what else we need and overall costs Better labor estimate, both what else we need and overall costs 6

ASTA ES&H ASTA is really small -Egress issues were discussed and agreed upon with Fire Marshall -Ergonomics LCW and electricity will be relocated to maximize space around laser tables X-Band table was raised to allow some room under it for the detectors Cryo-stand was moved to increase walking space Unnecessary equipment was and will be removed Cables and hoses were and will be rerouted to minimize obstruction in bunker New lights were installed BIO Reviews X-Band table (done) AC Project (partly done) Optical tables and mini girder (needs to start soon) Location of PPS devices review late June Laser SOP update in July Radiological Review has started -Results June 16 th Safety Assessment Document Review has started -Signatures by July 14 th 7

ASTA Project Plan and ES&H Summary Most critical items have been/will be ordered this week Installation will allow existing programs to continue Schedule has not much float Let’s all work together for: Want UED? Come to SLAC! Let’s all work together for: Want UED? Come to SLAC! 8

ASTA Layout 9