Apr 29, 2003SSWG1 Prime Focus Imaging Spectrograph Status Passed CDR- moving into fabrication phase Mechanism design complete: fabrication drawing packages.

Slides:



Advertisements
Similar presentations
University College London, Optical Science Laboratory bHROS Progress bench-mounted High Resolution Optical Spectrograph bHROS bHROS Progress General.
Advertisements

MMIRS 1 MMIRS MMT and Magellan Infrared Spectrograph Brian McLeod.
SALT RSS-NIR MID-TERM REVIEW MAY 20 & 21, 2009 ANALYTIC OPTICS KENNETH NORDSIECK UNIVERSITY OF WISCONSIN.
1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
NGAO Instrumentation Overview September 2008 Updated Sean Adkins.
M2FS: Michigan/Magellan Fiber System. M2FS (Michigan/Magellan Fiber System) Fiber-fed MOS w/2 independent and identical spectrograph arms 256 total fibers.
PALM-3000 High-order Wavefront Sensor Update Christoph Baranec Team Meeting #9 10/22/2008.
1 Michael Rowen 1 SXR Instrument FAC SXR Instrument Michael Rowen – Engineering Physicist June 9, 2009.
Lab5 Production Status: Optics and RBX integration Pawel de Barbaro U. of Rochester.
Status of IPBSM Improvement N. Terunuma, KEK 2012/July/13 ATF2 Weekly Meeting.
Oct 17, 2001SALT PFIS PDR - Structure1 Structure Interface/ constraints Loads Structure design rationale Truss Weight and CG Finite Element Analysis/ Image.
Oct 22, 2007SSWG #18 UKZN1 Robert Stobie Prime Focus Imaging Spectrograph Status Optics repair Schedule Status of other fix and improvement projects Budget.
SALT Technology Development Lisa Crause India-South Africa Astronomy Workshop – SAAO 6 August 2012.
Magellan F/5 System Status A.Szentgyorgyi/SAO/30 Apr 2005.
Nov 6, 2005SSWG1 Robert Stobie Prime Focus Imaging Spectrograph Status Reassembly and retesting in Cape Town Estimated CTC $343,000 (7.3%) over PDR cap.
Intermediate review - ERC – February 9, 2009 – L. Pinard 1 Mirrors Sub-System Overview  Introduction  Scope of the subsystem, main tasks  Job done since.
August 2 and 3, 2010 Project Cost, Schedule, Risk and Contingency Jay Elias.
LIGO-G M May 31-June 2, 2006 Input Optics (IO) Cost and Schedule Breakout Presentation NSF Review of Advanced LIGO Project David Reitze UF.
Oct 17, 2001SALT PFIS Preliminary Design Review Optical Integration and Test Plan 1 Southern African Large Telescope Prime Focus Imaging Spectrograph Optical.
PACS IIDR 01/02 Mar 2001 Instrument Interfaces1 PACS FPU Opto-mechanical Design Overview and Interfaces J. Schubert MPE.
Magellan F/5 System Status A.Szentgyorgyi/SAO/25 Sept 2004.
ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
Multiplexed High Res Spectroscopy at Keck – J. Cohen (PI), H. Epps (Optical Design), M. Rich (Project Scientist) Keck instruments for optical spectroscopy.
Magellan F/5 System Status A.Szentgyorgyi / Ann Arbor 25 Sept 2005.
Oct 17, 2001SALT PFIS Preliminary Design Review1 PFIS/ IMPALAS Issues Outside Reviewer's Comments Post-PDR tasks Valuation Issues.
PACS IBDR 27/28 February 2002 PACS Grating Assembly1 Grating Assembly E. Renotte Centre Spatial de Liège (B)
Oct 30, 2003PFIS - Student Wkshop1 The Prime Focus Imaging Spectrograph – Old Challenges and New Ones K. Nordsieck, Principal Investigator Jeff Percival,
Opto-Mechanics for SNAP at UM
Compressor status AWAKE Technical Board meeting 19 August 2015.
The Prime Focus Imaging Spectrograph Design and Capabilities
MAXIM Periscope ISAL Study Highlights ISAL Study beginning 14 April 2003.
3.1.1 Optics, Optical Corrector, Mechanical Systems M. Johns, C. Claver.
Delta II 7925H - 10L Baseline workup Launch Vehicle TheirsOurs Delta II 7925H Launch Vehicle 10L Composite Fairing 10L Stretch Composite Payload Fairing.
Oct 26, 2007SALT Workshop UKZN1 Robert Stobie Prime Focus Imaging Spectrograph Science Rationale Modes –Fabry-Perot Spectral Imaging –Grating Spectroscopy;
Oct 17, 2001SALT PFIS Preliminary Design Review1 Southern African Large Telescope Prime Focus Imaging Spectrograph Mechanical Mechanism Design Michael.
Binospec - Next Generation Optical Spectrograph for the MMT
Oct 24, 2006SSWG1 Robert Stobie Prime Focus Imaging Spectrograph Status On-telescope throughput analysis Ghost analysis Repair plan Status of other current.
DBSP-R Upgrade Progress Review The DBSP-R Team DBSP-R Progress Review.
1 ME1/1 ODMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project.
ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 1 Monthly Status Report Report due 3/25/00 Schedule statused.
9/24/05MagE Update SAC meeting Developments with MagE Complete layout of Spectrograph structure and camera by B. Bigelow –Structure will be all anodized.
Page 1HMI/AIA Science Meeting – February 13, 2006 HMI Instrument Status HM/AIA Science Meeting February 13, 2006 Barbara Fischer HMI Deputy Program Manager.
Oct 17, 2001SALT PFIS PDR - Optics1 Optics Refractive Optics - Design rationale Performance Slitmasks Gratings Polarimetric Optics Risks and Concerns Kenneth.
Oct 10, 2002SSWG1 Prime Focus Imaging Spectrograph Status Engineering Status Optics Mechanical Control System Management Budget Schedule.
Mar 18, 2003PFIS CDR1 Control System Summary of Changes Since PDR All the motors, drivers, sensors, switches, etc. have been chosen Built up a mechanism.
May 19, 2008SSWG #19 Göttingen1 Robert Stobie Prime Focus Imaging Spectrograph Status Optics repair positive progress: –UV efficiency –Some (repair-caused)
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier NSLS-II Conventional Facilities Schedule Review December 13, 2006.
GMT’s Near IR Multiple Object Spectrograph - NIRMOS Daniel Fabricant Center for Astrophysics.
Executive Committee, Toronto August 3, 2005 TRT Barrel WBS 1.2/3.2 Harold Ogren Indiana University.
Apr 29, 2003SSWG - CDR Comments1 PFIS Critical Design Review Comments Detailed response available in document SALT- 3100BP0011 (PFIS web site) Responses.
Brenna Flaugher, PMG, April 6, 2007 DECam Funding Need Profile (Dec 06) (then yr $, Overhead included) This gave a technically driven schedule resulting.
The Field Camera Unit Results from technical meeting S. Scuderi INAF – Catania.
Oct 17, 2001SALT PFIS Preliminary Design Review Management, Schedule, & Budget 1 Southern African Large Telescope Prime Focus Imaging Spectrograph Management,
Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 1 The DECam Project Closeout, Action Items Hexapod Optical Lenses CCD Readout Filters Shutter 2008.
Design for a New Optical Table of the Shintake Monitor Takashi Yamanaka The University of Tokyo ATF2 weekly meeting 2007/9/26.
ITOP Quartz Procurement Status James Fast Pacific Northwest National Laboratory PNNL-SA
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
Sept 16, 2005Ast 920 Meeting 21 Astronomy 920 Commissioning of the Prime Focus Imaging Spectrograph Meeting 2 Intro; VPH Grating Spectroscopy Ken Nordsieck.
Prime Focus Imaging Spectrograph Status
Jim Fast Pacific Northwest National Laboratory
Telescope Assembly, Integration and Verification (AIV) WBS 04C. 14 J
Prime Focus Imaging Spectrograph Status
Budget Budget Contingency/ Cost Risks Descope Options
Peer Review Agenda (Suggested).
Overview Instrument Role Science Niches Consortium science
Lockheed Martin Canada’s SMB Mentoring Program
Polarimetry: Waveplate Modulation; Calibration
Control System Summary of Changes Since PDR
Presentation transcript:

Apr 29, 2003SSWG1 Prime Focus Imaging Spectrograph Status Passed CDR- moving into fabrication phase Mechanism design complete: fabrication drawing packages for all All 3 PFIS CCD’s delivered: good – excellent VPH complement defined Optical blanks received or due mid-May Lens fabrication, waveplate and beamsplitter awarded 2 of 3 etalons into final figuring Full –up control system using generic mechanism demonstrated With >95% firm quotes, use of budget reserve is 63% Concerns: schedule, weight budget

Apr 29, 2003SSWG2 Full-Up Model of PFIS Detector Electronics PSC2 Box PXI Box Baffling

Apr 29, 2003SSWG3 PFIS – 90 0 Articulation Rotating Baffling

Apr 29, 2003SSWG4 Structure & Mechanisms

Apr 29, 2003SSWG5 Mechanisms Filter Detector Collimator Focus Fold Mirror Grating SlitmaskShutter

Apr 29, 2003SSWG6 The Way Forward Interfaces need to be finalised –UW-SALT – PFIP interface ring, Guider, Utilities –UW-SAAO – Camera-Detector, Electrical Boxes –UW-Rutgers – Etalons, Mounting the actuators, Nests –UW-OptoMech – Guider mount-field lens, Camera Fabrication drawings completed, April 2003 Fabrication, Procure parts - Articulation, May 2003 Procure Invar Tubes for structure fabrication Structure fabrication kick-off, May 2003

Apr 29, 2003SSWG7 Concern: Mass Budget As delivered: –Collimator + fully loaded visible beam + 80 kg trim is within 500 kg ICD limit (trim require to bring CG within 50 mm of axis per ICD) –CDR mass estimate is robust since >92% of mass has detailed design –Trim can be traded for Auxiliary Port, which is under NIR beam NIR beam upgrade path –With goal NIR beam mass budget = Vis Beam = 190 kg, most modes supported at 525 kg if not all dispersors simultaneously loaded –=> Need to save kg, reduce NIR Beam mass budget and/or use payload mass margin when NIR beam delivered –Operational constraint from not having all modes simultaneously is consistent with no longer being sole major instrument (eg HRS) when NIR beam arrives.

Apr 29, 2003SSWG8 Mass vs Configuration

Apr 29, 2003SSWG9 PFIS CCD’s The CCD’s have been delivered. QE equals or exceed the “typical” manufac- turer’s QE curve

Apr 29, 2003SSWG10 VPH complement

Apr 29, 2003SSWG11 Example: Collimator layout Optomechanical Award subcontract for optomechanical to J. Alan Schier –optomechanics for Keck ESI, DEIMOS –comfortable with fluid coupling, salt, solgel Tasks –mounting tolerancing –design, fabricate lens holders –assemble lens groups

Apr 29, 2003SSWG12 Procurement Status Item PDR EstimateNow Low bid Other biddersStatus Company Deliv ery CaF2 Blanks $98,116 $87,460Oken80dBicronAwarded Due15 May Fused Silica Blanks$8,750Dynasil4 wk Corning, OkenReceived NaCl Blanks$4,275Hilger6 wkRubiconIn testing Fused Quartz Blanks$13,650Oken75 dHeraeusShipping Lens Fab- asphere $168,714 $33,000Coastal 20 wk TORC, TinsleyAwarded spheres$53,000Janos8 wk Coastal, TORC, HJOLAwarded MgF2/ Solgel coatings$55,918 Cleveland Crystal8 wk soliciting morePrelim quote Multilayer Coatings$12,300 Spectrum Thin Films6 wkRMIPrelim quote Waveplates$120,000$83,000Halle6 mononeAwarded Beamsplitter$44,100$53,100 Karl Lambrecht 30 wkReynardAwarded

Apr 29, 2003SSWG13 Procurement Status - II Item PDR EstimateCDR Low bid Other biddersStatus Companydeliv VPH Substrates $30,000 $11,850United Lens30 dHJOL, CoastalReceived VPH Coatings$3,975Spectrum Thin FilmsQuotation VPH Fabrication$24,950Wasatch8 wkCSL Quote in progress; waiting for KOSI SR Grating$6,920Richardson9 wknoneQuotation Color Filters$10,000 Estimate Slitviewer Optics$4,700TORC6 wk Coastal, HJOL, Edmund, ZygoQuotation Slitmask Cutter$120,000$120,785US Laser4 monone yetQuotation Total$590,930$587,633

Apr 29, 2003SSWG14 Budget: Cost-to-Completion Used reserve early to control schedule risks With formal quotes for >95% of major purchased equipment, have used 63% of budgeted reserve Remaining $268K available for mishaps and schedule problems Would pay for ~ 7 mo schedule stretch at highest salary burn rate Reserve Use

Apr 29, 2003SSWG15 Budget: Prognosis Expected positive deltas –spare blanks: $32,800 –design subcontractor ~$30K –CDR requested changes: ~$15K –machining underestimates? Expected negative deltas –spare cost recovery if not used –optics testplate redesign ~$25K –cost savings on mechanisms ~$10K -> $220,000 to spend on schedule: 6 months

Apr 29, 2003SSWG16 Concern: Schedule Fabrication phase schedule exercise now underway Structure is critical path until articulation installed, then passes to optics integration & test Optics delivery has only 2 weeks slack –improved to 5 weeks by splitting asphere and sphere award Mechanism “waterfall” easily disrupted –re-order to do articulation, slitmask early, polarimetric last. Testing phase: graduate student, postdoc (UW contribution) Detector delivery has only 6 weeks slack Etalon delivery has 3 months slack Ship 21 June, 2004

Apr 29, 2003SSWG17 Schedule at CDR

Apr 29, 2003SSWG18 Schedule at CDR - II