R. Boyd 1 February 2010.  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.

Slides:



Advertisements
Similar presentations
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
Advertisements

André Augustinus 15 March 2003 DCS Workshop Safety Interlocks.
André Augustinus 16 June 2003 DCS Workshop Safety.
ATLAS SCT Endcap Detector Modules Lutz Feld University of Freiburg for the ATLAS SCT Collaboration Vertex m.
André Augustinus ALICE Detector Control System  ALICE DCS is responsible for safe, stable and efficient operation of the experiment  Central monitoring.
Atlas SemiConductor Tracker Andrée Robichaud-Véronneau.
1.ATLAS and ID 2.SCT 3.Commissioning 4.Integration 5.Latest Runs 6.Conclusions Commissioning the ATLAS Silicon Microstrip Tracker IPRD08 - Siena Jose E.
IBL CO 2 cooling control system development status Lukasz Zwalinski – PH/DT/DI Maciej Ostrega – PH/DT/DI Florian Corbaz – EN/CV/DC.
Introduction & News SCT Weekly during ID Week Dave Robinson Cambridge University.
Construction and Installation of the CLIC Experimental Area
SR1 ongoing workH.Pernegger21/2/02 Ongoing work in SR1 and preparations for detector macro assembly Heinz Pernegger.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
DCS TCSG November 10th 1999, H.J.Burckhart1 Status of the general purpose I/O system LMB u DCS Architecture u LMB u Local Monitor Box (LMB) u Concept u.
Jon S Kapustinsky 11/17/2010 Jon S Kapustinsky FVTX Commissioning Plan 1.71 Jon S Kapustinsky 1.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester July 8, 2013.
Electrical and Optical Cables Installation at P5 What When How H. Breuker
André Augustinus 16 September 2002 Safety issues.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
CERN, Main challenges for the ATLAS upgrade project in the coming year.
ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 Steve McMahon 1 Steve McMahon : An Introduction Backgrounds and Pre-History –Imperial College London
ICTPP09 R. Kass Radiation-Hardness of VCSELs & PINs Richard Kass The Ohio State University OUTLINE Introduction/ATLAS pixel detector Radiation Hardness.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
Status Report from LHC Safety System Task Force Emmanuel Tsesmelis / TS-LEA on behalf of the Task Force LEAF 11 May 2007.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
1 H. Pernegger/CERNIBL cooling review 15/5/2012 IBL Cooling Requirements H. Pernegger.
M&O status and program for ATLAS LAr calorimeter R Stroynowski (on vacations)
1 Safety and Database Subsection ADO - PO - SA Safety achievement and future activitiesSafety achievement and future activities Database (see K. Pommes.
Operations Kendall Reeves. Past Year Commissioned new SDX1 cooling loop after removing foam insert inadvertently left inside (Denis and Joel) Commissioned.
26 May 2010Hans Postema - CERN Status and plan for the development and construction of CO2 Cooling System for Pixel Upgrade 1.
Status of the Remote HV System 10 June 2015 TileCal week, upgrade session Roméo Bonnefoy, Romain Madar and François Vazeille ● Summary of performances.
ATLAS Inner Detector MO_B 2012 closure 2013 mid-year status 2014 request H. Pernegger / Pixel PL & ID Resource Coordinator D. Robinson / SCT PL and ID.
Michel RAYMOND – April 14 th, 2011 Technical Support Activities in PH-ADO-PO Goals for 2011.
IDE DCS development overview Ewa Stanecka, ID Week, CERN
ALICE Pixel Operational Experience R. Santoro On behalf of the ITS collaboration in the ALICE experiment at LHC.
July 17, 2013 CERN T. Flick University of Wuppertal.
DCS meeting27.Sep.2002 Serguei Zelepoukine (IHEP, Protvino) Contents: 1. Front-end electronics: problems & solutions. 2. DCS cabling outside the ECAL detector.
1 OperationsOperations CSC is stable running since HI run has started. The low CSC occupancy in HI running allows us to operate all HV channels at nominal.
MPE Review – June 2, 2015 A. Erokhin, TE-MPE-EE Upgrade, IST and Powering tests of the Upgrade, IST and Powering tests of the 600A Energy Extraction Systems.
TB Peter Glässel, Heidelberg1 TPC Status Report Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel, Heidelberg.
Alpine pixel layout Integration progress Teddy Todorov For the ATLAS-LAPP group AUW Integration meeting 20/11/2012.
1 Safety and Database Subsection ADO - PO - SA Main safety projects / activities Main safety projects / activities RP issues RP issues Patrols Patrols.
9/17/2008TWEPP 2008, R. Stringer - UC Riverside 1 CMS Tracker Services: present status and potential for upgrade Robert Stringer University of California,
60kW Thermosiphon control system
CMS consolidation activities of detector cooling system Detector cooling project P. Tropea.
André Augustinus Infrastructure  Turbines  Radmon  Thermocouple readout  Netgear redundancy  Other cavern items  Cooling CRs  Other CR and surface.
Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities.
14 November 08ELACCO meeting1 Alice Detector Control System EST Fellow : Lionel Wallet, CERN Supervisor : Andre Augustinus, CERN Marie Curie Early Stage.
RRB scrutiny Report: Muons. Internal scrutiny group for RRB report Internal scrutiny group composition – J. Shank, G. Mikenberg, F. Taylor, H. Kroha,
IBL – UniGe involvements UniGe Team : G. Barbier, F. Cadoux, A. Clark, S. Débieux, D. Ferrère, C. Husi, G. Iacobucci, M. Weber Other member (KEK): Y. Takubo.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
Geoff HallLECC LHC detector upgrades Introductory comments on electronic issues Organisation of this short session.
First discussion on MSS for Katrin March 26, 2013 M.Capeans CERN PH-DT.
GlueX Collaboration May05 C. Cuevas 1 Topics: Infrastructure Update New Developments EECAD & Modeling Tools Flash ADC VXS – Crates GlueX Electronics Workshop.
Interventions on electrical distribution and racks’ infrastructure still to be done during LS1 and their impact W.Iwanski.
TC meeting P2 planning wks 3&4 A.Tauro
Pixel Action Matrix C. Newsom July 15, Overview Critical Parameters Initial Discussion – Top 6 critical failures Discussion - Detailed Documentation.
TDAQ and L1Calo and Chamonix (Personal Impressions) 3 Mar2010 Norman Gee.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
Straw Working group Ferrara 4/9/2014. Outline Status and Plans Installation of Chambers 1-3 Chamber 4 Vacuum test SRB Readout, monitoring and software.
ATLAS Plenary, Feb. 18th, 05Commissioning1 Report on the commissioning activities G. Mornacchi, P. Perrodo and Sub-Systems Collaborators.
David BAILLEUX On behalf of the Caltech group Issues for the Laser Monitoring System M&O - US CMS ECAL IB meeting 19 March Chilled water supply.
Detector Safety System overview DSS is a PLC based system designed to protect ATLAS detector from damages. Front end (hardware) 2 redundant PLC ~700 input.
Detector Control for the Insertable B-Layer Susanne Kersten Wuppertal University ATLAS Upgrade Workshop, February
ATLAS M&O General Comments
HF Test station at P5 A.Mestvirishvili.
SciFi option for neutrino target tracker
GlueX Electronics Review Jefferson Lab July 23-24, 2003
Rack installation and local tests for the MEBT Chopper Rack
Presentation transcript:

R. Boyd 1 February 2010

 Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd

 HVPP4  Reconfigurable patch panel for Pixel sensor bias distribution  Allows delaying of power supply modules until inversion sets in (>300kchf)  Designed by R. Boyd and built by the collaboration at CERN, including D. Jana and R. Labbai  All 1800 (+spares) channels were tested to 1kV  Installed in May 2008  Has provided a convenient service point for troubleshooting bias problems in the Pixel detector

 Counting Rooms Installation (organized by R. Boyd)  Power supplies for 4 * 1800 loads, in two service caverns (US15 & USA15)  DCS computers  Optical fibers  ROD (Read Out Driver) Crates  Pixel monitoring and interlocks in 4 racks in UX15 (experimental cavern)  Cables, cables, cables, cables, cables…

 Assembly in SR1 – connectivity tests  M. Saleem  Started during Pixel Detector integration in SR1, 99.8% of channels working  Repeated after installation and services connection in ATLAS  Still > 99% of channels working  Problems still arise  All the Oklahoma group has contributed to effort to understand opens in sensor bias circuits  Much shift time is spent troubleshooting and tuning unhappy channels, from various causes

 M. Saleem, R. Labbai & D. Jana contributed to DSP code validation for the Pixel Rod’s 2008  Code is validated in SR1 on ToothPix, the Pixel detector test stand  This is a continuing activity, as new code is continuously developed  Other commissioning shifts covered by OU physicists at CERN include  M5 run (data read out stream) 2007  Data quality shifts for off line monitoring 2008  ATLAS engineering run 2008

 Shifts  Category 1 – 42 required, last year, 47 covered  Category 2 -  Pixel - OU physicists  Pixel  DCS (Detector Control System)  DSP code validation  (Off-line monitoring – B. Abbot)  IDGen (Inner Detector cooling, gas, environment) R. Boyd  ID Expert shifts (6/yr.)  ATLAS (R. Boyd)  SLIMOS (Shift Leader in Matters of Safety), since 2005 (2 – 4 /mo.)  Patrol on call (securing cavern safety for beam) – 1 in training (6/yr.)

 In addition to shifts, R. Boyd  Serves as ATLAS (and Pixel) Laser Safety Officer  Documentation  Training  Coordination of laser interventions  Annual inspection and safety tests  Serves on ATLAS safety team, which meets weekly  Manages underground access and other safety issues for Pixel  Pixel DSS (Detector Safety System) responsible  Represents the Pixel detector group in ATLAS Operation Management and Counting Room Management meetings (for infrastructure)  Attends the weekly ID and CERN EN/CV cooling coordination meeting

 OU MS Engineering student L. Devareddy participated with Ohio State and Oklahoma State in a radiation test of new VCSEL’s and PIN diode’s for Pixel upgrades in 2007  OU and Okla. State have provided support for annual irradiation runs since  R. Boyd coordinating electronics effort for upgrade to ID cooling using binary coolant mixtures  Sonar used to determined ratio of mix and as a flow meter  Control signals for cooling plant  IBL (Insertable B layer)  Replacement to be inserted when radiation damage limits usefulness of Pixel b layer  Recently partnered with Okla. State Univ. to develop and deliver a temperature controlled patch panel for the opto boards, which convert electrical signals to optical (and vice versa), just outside the Pixel volume  Anticipate playing a central role in development assembly, testing and installation of IBL at CERN

 All ATLAS detectors have proven performance in recent months  OU personnel have received training in many areas in preparation for running  OU is already booked for 41 of a required 30 shifts in 2010 (Pixel shifts, only)  ID (Pixel) cooling is now running reliably, with regular maintenance (about 2 leaks per week)  Beams resume mid-month  IBL effort is under way