LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.

Slides:



Advertisements
Similar presentations
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Advertisements

SRF Cryomodule Assembly Facility Plans Tug Arkan AAC, May 10-12, 2005.
G. Olry for the IPN Orsay team 5 th SPL collaboration meeting, 25-26/11/2010, CERN.
G. Olry, H-M Gassot, S. Rousselot (IPN Orsay) EuCARD-SRF annual review 2011, 4-5 May, IPN, Orsay Unité mixte de recherche CNRS-IN2P3 Université Paris-Sud.
ESS cavities interfaces
Summary of WG 2 - cavities W. Weingarten 15th SPL Collaboration Meeting CERN - 25/26 Nov Cavity WG.
LCLS-II cryomodule alignment. 2 Wednesday meeting, 6/17/2015 Topics Alignment of Components inside the CM Tunnel Network Tolerances LCLS-II cryomodule.
CERN status - Nb cavity – Manufacturing 1 15/Nevember/2010, Ofelia Capatina EN/MME 1 SPL Cavity Working Group Meeting TaskExternal Company CERN Provide.
Harry Carter – LCFOA Meeting 5/1/06 1 LCFOA Technical Briefings: Cryomodules H. Carter Fermilab Technical Division.
Accelerator/WP High Beta Structures Alan Wheelhouse HIGH-BETA CAVITY DELIVERY April 21, 2015.
The ESS Linear Accelerator
Americas Cavity Specification C.M. Ginsburg (Fermilab) On behalf of the Fermilab cavity crew October 20, 2010.
Manufacturing process, validation and factory test
HIGH-BETA CAVITY DELIVERY P McIntosh ASTeC, STFC Daresbury Laboratory ESS Technical Advisory Committee Lund 1 – 2 April 2015.
Accelerator/ Medium Beta Cavities Paolo Michelato INFN Milano - LASA April 21, 2015.
Medium Beta Cavities Paolo Michelato, Paolo Pierini, and Carlo Pagani INFN Milano - LASA.
Medium beta cavities Paolo Michelato, Paolo Pierini, Carlo Pagani INFN Milano - LASA.
SPL cavity design by IPN Orsay Guillaume OLRY November rd SPL collaboration meeting.
Carlo Pagani University of Milano INFN Milano-LASA & GDE ILC and XFEL Cryomodules Preliminary thoughts for convergence ILC EDR Kick-off Meeting DESY,
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
CM2 Helium Circuit Vacuum Leak & Repair Tug Arkan, 6/18/
Overview on DESY Infrastructure and up date/ grade Activities schedule status and plans Axel Matheisen DESY.
C.MADEC - TTC meeting E-XFEL cryomodule assembly : prototyping phase at Saclay.
Experience for vacuum plants during XFEL cavity production at companies and at LASA Paolo Michelato TTC Topical Workshop on SRF Cryomodule Clean Room Assembly,
Pierre Bosland 4 TH OF FEBRUARY 2016 COORDINATION COMMITTEE FR-SW AGREEMENT STATUS OF THE FRENCH ACTIVITIES UNDER THE RESPONSIBILITY OF CEA.
W. Singer. SRF2011, July 25 ‐ 29, 2011, Chicago, Illinois, U.S.A. XFEL Cavity Recipe for Mechanical Fabrication and Treatment Waldemar Singer/DESY.
SRF COLLABORATION MEETING MAY.2016 ESS MEDIUM BETA CAVITY MANUFACTURING CEA Saclay/ESS ECCTD WU Cavités | Enrico Cenni.
LASA status for medium-beta cavity Paolo Michelato.
7th SRF Materials Workshop FRIB SRF Cavities 7/16/12 Chris Compton.
A Proposal for FJPPL (TYL) Development of Frequency Tuners Optimization and Cryomodule Integration for 1.3 GHz SRF Cavities G. Devanz, F. Nunio, O. Napoly.
Wish list from ESS Christine Darve H-ECCTD Kick-off meeting 16 March
S. Barbanotti - DESY Requirements Conformance for SRF Cryomodules Workshop 16/10/2014 – ESS, Lund XFEL cryostat main components: Quality Assurance and.
ESS WP4 Strategy for series production ESS TAC10 – 5th to 6th November Lund Sébastien Bousson WP 4 leader.
H-ECCTD KICK-OFF DESCRIPTION AND CHALLENGES 16/03/2016 F. PEAUGER.
Accelerator/ Medium Beta Cavities Rocco Paparella on behalf of INFN Milano – LASA ESS Team April 21st, 2016.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
Quality Plan Documentation Management & Non Conformities ESS PDR, INFN-LASA, 19 May 2016Laura Monaco, INFN LASA.
RF SC CAVITIES –a story AMICI Industry days – Padova April 2017.
WP High Beta Cavities Delivery
The Evolving ILC Project
Strategy and Status of Reference Cavities for European XFEL
Status of the M-ECCTD F. Peauger - P. Bosland
“CENTRAL SUPPORT FRAME” -
Cryomodule test stand at ESS site
Status and plans for the 3.9 GHz section of XFEL
WP5 Elliptical cavities
ESS cavity procurement via in-kind contributions
T5.2: Harmonization - Material and Component Reference
WP-46 XFEL 3rd harmonic system XFEL Project Progress Report (1-2010)
WG-1 Session Cavity Performance Cryomodule Performance
Activities of Cavity Fabrication Facility at KEK
ELLIPTICAL SCRF CAVITIES
Definition of work flow for string DESY Example on critical operation
EZ Infrastructure for SC cavities production
UK RFD Pre-Series cryomodule
WP 3 coordination meeting Saclay May 2008
Highlights from EU Global Design Effort
HIE-LINAC status report
IHEP Cryomodule Status
Development of Large Grain Cavities at DESY
Retreatment of Superconducting Cavities for the European XFEL
SPOKE Cavities frequency preparation plan and RF control procedures
A. Bignami on behalf of LASA SRF Group
Daresbury ESS In-Kind Contributions
Cryomodule ESS FAT & SAT SRF meetinG on 07/11/2017
Incoming inspection of the cavities at saclay
Double-Spoke Cavities
ESS High Beta Cavities Quality Assurance and Control - Learning and Planning Workshops, CEA Saclay, 30 June - 1 July 2016 Mark Pendleton STFC, Daresbury.
Work Unit AIK 11.2 CDR of the CDS-SL Mechanics
Paolo Michelato LASA - Status of cavity documentation, fabrication, inspection and NCRs Laura Monaco INFN – LASA 10° ESS SRF Collaboration Meeting, 25.
Presentation transcript:

LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015

Summary Nb material: LG and FG, defects. Interfaces, mechanical constrains, tolerances, boundaries condition, etc for cavities and tank Frames for cavity handling QA / QC and Quality control strategy

Nb LG and FG for prototypes Nb LG (diam. 480 mm), from CBMM arrived in Europe, sliced at Heraeus Hanau. RRR: about 300 Next steps BCP (a few  m) and heat treatment for dehydrogenation and stress release at EZ Dies preparation Deep drawing test Order for FG material for LG cavity prototype (tubes, stiffening) and for FG cavity prototype (sheets, tubes, stiffening) for the second medium beta is under way.

Nb defects Still open the question of defects? XFEL statistics: between 0.6% and 2% (company dependent) for a XFEL sheet (265 x 265 mm 2 ). “Propagation” of defects probability for ESS? Linear? Sheets would be around 500 x 500 mm 2. Surface ratio: about 3.2 Expected defects ratio for ESS? Scanning needed? All defects seen with eddy current are dangerous? The BCP treatment reduce the risk: it would corrode and remove “easily” defects with respect to EP Acceptable?

Mechanical construction, interfaces and plug compatibility LASA plug compatible design needs for a full clarification of interfaces requirements. Interfaces must be clarified: definitions, dimensions, tolerances, maximum misalignments, etc. to ensure the cavities acceptance and their installation in the cryomodule. Present CEA cavity design should be updated and improved to be ready for series production. E.G. for cavity length (XFEL +/- 3 mm), definition of reference surfaces, flange tolerances, alignments, etc. These activities already started after the Interface Meeting at LASA of November 2 – 3 and it is in progress.

Tank design Present CEA tank design doesn’t permit the adjustment of the tank length with respect to the cavity length. Tank is “custom-made” and adapted to the cavity. Present tank design makes quite hard the extraction of the cavity from the tank: from EXFEL experience some cavities could need a further etching and therefore a cavity retuning for field flatness restoring. The suggestion, coming from the past experience, is to insert an L structure sliding join on the tank: this will permit the adjustment of the tank length (one tank design for all cavities) and an easier removal of the tank and the installation of a new one after retreatment.

Tank design Implication of the presence of the join on the cavity installation in the module are under investigation by CEA (fixed point, tie rods distances and connections to the cryomodule frame, position of the sliding part w.r.t. coupler, etc)

Frames for cavity movement, support, cold test CEA frames will be used for medium beta cavity support, handling, movement, cold test, transportation. Same interaxis distance of rods for naked cavity and cavity with tank Rods: Titanium Verification of compatibility at the industry (cleaning, rinsing, BCP, HPR) under way.

Quality Control strategy Based on our experience for XFEL cavity production cavities (1.3GHz) fully produced at the industry cavities (3.9 GHz) produced at the industry (assembly of cavities ancillaries and last HPRs done at LASA), test done at LASA For the 32 medium beta cavities for ESS: Companies are responsible for QA/QC Companies hand over required info to the Contractor (INFN) INFN Team of experts (mechanical, RF, treatments, vacuum, etc.) check and approve documents (“external” QC, process control) “on-line” check of production quality (feedback to the Companies) Only if requirements are fulfilled, the cavity go on with production (Acceptance levels overcome) Non Conformities: If the required property of a component is not provided, a nonconformity report is emitted by the Company and further action are discussed and approved by the contractor: acceptance or quarantine Check list for any outcoming / incoming steps INFN supervise the Quality Control by: Periodic Visit at the companies, scheduled meetings, actions of experts in case of problems.

QA / QC: How it will work (ESS) (Data Transfer, Flow of documents and data between INFN and Industry) Industry QC: responsibility of the Company; 3 acceptance levels to overcome Flow of documents for the «external» QC (LASA) INFN Check of all documents (parameters/process); experts do the check and acceptance; Prompt feedback to the Industry LevelCavity status Needed documentsIf Level reached One “Naked” cavity after fabrication Mechanical Fabrication documents Proceed to Level Two workflow Two Cavity after surface treatments Treatment documents Proceed to Level Three workflow Three Cavity integration and last treatments Integration and last treatment documents Integrated cavity ready to be RF tested Managing of documents/ database Industry must be released for each Al before going on with production NCR must be emitted and repair action approved by INFN

Flow of cavities INTERNAL Managing System Quality Control Industry Cold RF test Q 0 vs. Eacc CEA STRING ASSEMBLY CAVITY with TANK MODULE ESS

QC / QA:How it will work (ESS) (Data Transfer, Flow of documents and data) Cavity production data INTERNAL Managing System Quality Control INFNIndustry INFN Managing system Database (parameter analysis) INFN Experts Check Cold RF test Q 0 vs. Eacc CEA STRING ASSEMBLY CAVITY with TANK Documents for cold RF test acceptance Documents for full equipped cavity acceptance (for string assembly) MODULE ESS (approval) NCR

Clean Room (ISO7) Clean Room (ISO4) Example: ESS Prototype Cavities Treatment Flow