Scheduling News. Magdalena Kowalska
Injector schedule since last meeting 2 Confirmation of 2 week proton prolongation – until December 17 th : 35 -> 37 weeks of physics (vs 29 weeks in 2011)
ISOLDE schedule since last meeting 3 => new ISOLDE schedule v4.0, 26 th Oct: All GPS runs rescheduled (some shifts cut), partly in 2 additional weeks Failed summer run (11Be) also rescheduled CaO and offline 44Ti on GPS => No IS experiment cancelled (3 collection LOIs cancelled) GPS HRS Mid-October: GPS problem - extraction electrode stuck in the middle of target valve -> only light targets allowed
Schedule 2012 Shift balance: 1009 open shifts for IS experiments, 53 shifts for LOIs Shift requests: 833 shifts for 71 IS exp vs in 2010; 40 shifts for 14 LOIs 20 IS experiments with no beam requests REX requests: shifts (IS + LOIs) 4 Scheduled runs (since July – 2wk prolongation & GPS problem): ScheduledOct 2012July All shifts (IS+LOI+MD) Shifts for IS exp Shifts for LOIs # of IS exp5153 # of LOIs1013 REX runs & exp ? - 14 REX shifts (IS +LOI) Average shifts/day
Physics runs since last meeting Very successful LOI runs based on new experimental techniques: Jul: spin polarization with tilted foils behind REX - % beta-NMR signal on 8Li Aug: beta-NMR on liquids for biophysics – 1 st liquid beta-NMR signal (31Mg in ionic liquid) Aug & Oct – CRIS shows expected detection efficiency and reaches 202Fr Miniball runs: Po, Rn, Zn, K (instead of 30Na), 5
Physics runs since last meeting TISD: LIST target, new n-converter geometry Collections: Tb for cancer studies in PSI (Ulli) and Lausanne (MEDICIS), Cd and Ag for bio- and SSP Successful experiments with new setups & by new groups: 21Na and 31Mg with REX scattering chamber (Lund and Tokyo); 6He with opt. time-proj. chamber (Warsaw); 34Mg with fast tape-station (Bucharest) 12 Be with MAYA; In-source spectroscopy with decay detection (windmill) and MR-TOF (new method at ISOLTRAP): At and Au beams Backup beam: Ba-> Cs – SAHA-Kolkata, Cu-> Rb – ISOLTRAP, 30Na-> 48K – Koeln The only run with no beam – 11Be (rescheduled in December) 6 => Many new setups and groups and mostly successful runs
Upcoming Long shutdown 1: Presently: first protons to ISOLDE at the end of June 2014 Access to ISOLDE: with permanent dosimeter, helmets and safety shoes; under discussion whether safety equipment will stay after LS1 7 : New method and groups - incomplete fusion with T-REX: Milano & Cracow TISD: CaO-Helicon (on GPS) to produce C and possibly Ar beams The only WITCH run this year 44Ti for astrophysics (GPS): 44Ti source from PSI, setup behind REX Mn for COLLAPS (Manchester) and some SSP users Hg for TAS (1st run since a few years) and priority collections 11Be which failed in the summer Runs coming before shutdown: