Joints for Diaphragm Walls

Slides:



Advertisements
Similar presentations
Portal Framed Construction
Advertisements

Concrete Technology Finishing Concrete Joints in Concrete Lecture 20
CASTING A CONCRETE WALL
Concrete Fooring & Roofing System
Tank 85 Foundation  View of poured auger pile.  Setting up for next pile.  This process repeated itself 310.
Cairo Metro Line3 / Medinah Car Park II
Marine Construction SCM 330 Tyler Mason Pratt Tyler Mason Pratt
INAR 243 FLOORS.  Structural element  Proper ground for functions.
PIPE CULVERT By CH. VENKATARAMAIAH.
Advanced Construction Technology
Diaphragm Wall Construction
Design C a s t i n g E r e c t i o n F i n a l S t r u c t u r e D e s i g n C o n s t r u c t i o n P r o c e s s P r e–c a s t C o n c r e t e 3D M o.
Groundwater Control Affects design of: –Permanent Works –Temporary Works May affect viability of scheme Safety Issues –May cause instability of excavation.
Hargrave Street Pumpstation – Site Preparation July 2014.
GROUNDWATER CONTROL.
Ms. Gripshover Landscaping Unit 18 INSTALLING PATIOS, WALKS, AND DECKS.
Foundation Systems.
Foundations. Foundation supports weight of structure –Includes soil and rock under foundation –Building construction described by foundation type Slab.
Bricks Introduction Structural member Load transfer medium
Chapter 7 Metals.
The Good, the Bad, and the Ugly 2 May 2008 Sacramento, CA Alan Macnab
Foundation Fundamentals GSD 6204 Building Technology Harvard Graduate School of Design.
Unit 1 Types of Construction
Estimating Ahmed Elyamany, PhD, AVS. EARTHWORK AND EXCAVATION bank  Earth that is to be excavated is called bank measure. loose  Earth that is to be.
REINFORCED CONCRETE Reinforced concrete is a composite material which utilizes the concrete in resisting compression forces, and steel bars and/or.
Chapter 18 Foundations.
PRE-FABRICATED STRUCTURES
CONSTRUCTING A FIVE CABIN LATRINE
Foundation Engineering CE 483
Chapter 2b Foundations Shallow & Deep Foundations.
Sources of water (RAIN)
Introduction to a pit installation
The new technology for watertight construction joints
BUILDING MATERIAL BUILDING MATERIAL PALESTINE UNIVERSITY chapter No.#7 Mechanical Works Dr. Ali Ibrahim Tayeh.
Percussion drilling By Batch -2. Percussion drilling Cable Tool Drilling Percussion drills have been used to drill thousands of feet, though they are.
BCM 210 Foundation Issues- Fall 2000 refer to Allen Text
Day 20 PRECAST AND PRE-STRESSED CONCRETE Pre Cast concrete comprise units that are made under controlled conditions, with necessary preparations for.
4.4 SOIL NAILING SOIL NAILING IS A REINFORCEMENT METHOD TO REINFORCE THE GROUND WITH STEEL BARS OR STEEL BARS IN GROUT FILLED HOLES. IT IS MAINLY USED.
10/2010 IWLC2010 Global Design Effort 1 Brief Overview of Interaction Region Conventional Facilities in RDR Times Presenter Tom Lackowski.
Chapter 43 Common Commercial Construction Materials.
Progress on Remote Handling Systems TAC 12 Magnus Göhran – WPM 15 th October 2015.
POOL CONSTRUCTION THE 5 MAJOR STEPS 1. Plan2. Dig3. Build4. Finish 5. Swim!
Bulb Piles –Franki Piles or pressure injected footings –Special form of cast in place pile with an enlarged base for increased load bearing F 10-4 Minipiles,
SANKALCHAND PATEL COLLEGE OF ENGINEERING,
Mahatma Gandhi Institute of Technical Education & Research Centre
Understand foundation design and construction
CAISSON FOUNDATION.
FOUNDATIONS.
Sanitary Engineering Lecture 13
Construction Inspection for FO Activities - Geosynthetics
DIAPHRAGM WALLS.
Concrete Repair presented by: Amirhossein Jodeiri Mapua Institute Of Tecnology.
Section Engineers Meeting March 6, 2014 Lexington, KY.
S.T.B.S. College of Diploma Engineering
Footings & Foundation Prepared By: (Vanani Sanket) Department of Civil Engineering B.H.Gardi College of Engineering & Technology.
Leads Institute of Technology & Engineering
Foundation – jay Desai.
Concrete Repair.
Structural Works Assessment
CONSTRUCTION OF A DTF DO’s and DON’Ts.
Trough during installation of Micropiles TITAN and Foundation Plate.
Diaphragm Wall: Construction and Design
Product Presentation January 2010.
CT Reinforced Earth Structures
WELCOME.
Building Construction I Sofia Sebastian 1
Arch205 building construction foundation
MATERIALS AND CONSTRUCTION I
Pier Foundations Piers Suspended floor Ground beam Next slide.
Neutron guide Shielding Concept
Presentation transcript:

Joints for Diaphragm Walls prepared by Erwin Stötzer Nov. 2000

Standard Joints constructed with Stopend Pipes Excavation with Grab length 2.8 m Reinforcement and Concrete Primary panel 2.8 m 1. bite 2. bite 2. bite 2.8 m 2.8 m 2.8 m 6.4 m - 7.0 m Successive panel 1.0 m - 2.8 m 2.8 m Guide for the grab 2. bite 1. bite 0.5 m - 2.8 m 2.8 m Closing panel 2. bite 1. bite

Standard Joints constructed with Stopend Pipes stopend pipe extractor stopend pipes with coupling

Standard Joints constructed with Stopend Pipes stopend pipe extractor concreting primary panel with two stopend pipes

Standard Joints constructed with Stopend Pipes lifting head bolted coupling

Standard Joints constructed with Stopend Pipes Method of Construction: Features excavation of the trench with the grab or cutter installation of the stopend pipe at the end of the trench installation of reinforcement cage pouring concrete into the trench by the tremie method. A sample from every concrete batch will be taken to monitor the curing process of the concrete in the trench. when the concrete starts hardening pulling out the pipe by hydraulic operated casing extractor.Adjust the speed of extraction to the hardening time of the concrete. system is used for a trench depth down to 25 meters guide wall has to be designed for the forces from the casing extractor a job site with one grab unit two sets of Stopend pipes and two casing extractors and for two grab units three sets of pipes and two extractors are required. the watertightness of the joint is sufficient for a water pressure of 4 to 6 m. this system requires experienced staff on on site after finishing the concrete operation the extraction procedure requires at least 6 hours more ( usually night work )

Joints constructed with Prefabricated Concrete Elements waterstop gravel fill to avoid concrete flow primary panel secondary panel

Joints constructed with Prefabricated Concrete Elements precast element waterstop core through precast element and cast in situ concrete panel installation of the precast element

Joints constructed with Prefabricated Concrete Elements with waterstop exposed diaphragm wall with precast element

Joints constructed with Prefabricated Concrete Elements

Joints constructed with Prefabricated Concrete Elements Method of Construction: Features excavation of the trench with the grab or cutter installation of the prefabricated concrete elements at the end of the primary trench installation of reinforcement cage pouring concrete into the trench by the tremie method. To avoid concrete flow behind the PC-element gravel dia 30 to 50 mm will be installed between the end of the trench and the PC- element construction of secondary element under the guidance of the PC - element of the primary panel system is used for a trench depth down to 25 meters or the lifting weight of of the PC - element of 25 tons for greater depth the PC- element can be installed in several pieces and connected together during installation procedure the PC - element guides the grab during the excavation of the secondary element the watertightness of the joint can be improved by placing waterbars in the PC- element

primary panel Joints constructed with Endplate Reinforcement Cage excavation concreting 300 mm 2200 mm 300 mm waterstops fixed to the steel plate grab width 2800 mm Geotextile sheet fixed at the steel plate to prevent concrete flow behind the plate, overlapping 0.5 m H - beams to keep cage in position during concreting, be extracted during concreting

length of secondary panel Joints constructed with Endplate Reinforcement Cage excavation of secondary panel excavated primary panel concreted primary panel H - beam 6.5 m to 7.5 m length of secondary panel Gravel geotextile sheet covers the reinforcement cage steelplate embedded 50 cm into soil

Joints constructed with Endplate Reinforcement Cage lifting head sheeted reinforcement cage filling with gravel behind endplate before concreting

Joints constructed with Endplate Reinforcement Cage

Joints constructed with Endplate Reinforcement Cage Method of Construction: Features excavation of the trench with the grab or cutter installation of the of the H - beams on both sides of the trench installation of reinforcement cage equip- ped with endplate and geotextile sheet fill gravel 30 to 50 mm between steel plate end of the trench pouring concrete into the trench by the tremie method. During concreting the gravel and the H - beam will hold the cage in postion. construction of secondary element under the guidance of the of the steelplate of the primary panel system is used for a trench depth down to 80 meters the endplates guides the grab during the excavation of the secondary element the watertightness of the joint can be improved by placing waterbars at the end- plate

Joints constructed with the CWS ( contignous waterstop) primary panel CWS steelform waterstop primary panel secondary panel

Joints constructed with the CWS ( contignous waterstop) exposed joint with two waterstops system with one or two waterstop

Joints constructed with the CWS ( contignous waterstop) steelforms for CWS system: single waterstop double waterstop

Joints constructed with the CWS ( contignous waterstop) exposed CWS joint

Joints constructed with the CWS ( contignous waterstop) Method of Construction: Features excavation of the trench with the grab or cutter installation of the of the CWS steel form with the waterstops on both sides of the trench installation of reinforcement cage pouring concrete into the trench by the tremie method. construction of secondary element under the guidance of the of the CWS form located in primary panel during excavation remove the CWS form by vibrator or hooks at the grab (Patent by Bachy ) system is used for a trench depth down to 20 meters the watertightness of the joint is improved by the waterstops of the CWS system in every primary panel two CWS forms should be placed, they only can be removed during excavation of the secondary panel

Joints constructed by overcutting the Primary Panels H - beam primary panel cutter

Joints constructed by overcutting the Primary Panels cutter secondary panel primary panel primary panel H - beam to be removed during concreting

Joints constructed by overcutting the Primary Panel cutter wheel with teeth shape of the cuttingjoint

Joints constructed by overcutting the Primary Panel Method of Construction: Features excavation of the trench with the cutter installation of the of the H - beam to keep the reinforcement during concreting in position installation of reinforcement cage pouring concrete into the trench by the tremie method, pull the H - beam out of the soft concrete system is used for a trench depth down to 120 meters the watertightness of the joint is improved when cleaning the overcutted joint before installation of the reinforcement cage by brush